Each project in the letting is listed with descriptive information. Click on a project to obtain a tabulation of item bids for each bidder. It includes the unit bid for each item as well as the total item bid. Also shown are the bidder totals and ranking for each project.
| Lead Project: 005-01-0077 | |
| Parish: ST MARY | |
| Routes: US 90-W | |
| Description: E. END GREENWOOD OVERPASS - W. END BAYOU BOUEF BRIDGE | |
| Type Const:
grading, drainage structures, in-place stabilized base course, pavement patching, cold planing asphaltic concrete, superpave asphaltic concrete overlay and related work. | |
| Low Bidder: BARRIERE CONSTRUCTION CO., LLC | |
| Amount: $1,370,236.13 | |
| Estimated Construction Cost: $1,550,594.07 | |
| Federal Number: | |
| Lead Project: 005-02-0049 | |
| Parish: ASSUMPTION | |
| Routes: LA 182 | |
| Description: WEST JCT. LA 662 - TERREBONNE PARISH LINE | |
| Type Const:
grading, cold planing asphaltic concrete pavement, superpave asphaltic concrete overlay, pavement patching, and related work. | |
| Low Bidder: HUEY STOCKSTILL, INC. | |
| Amount: $2,175,498.92 | |
| Estimated Construction Cost: $2,243,278.64 | |
| Federal Number: | |
| Lead Project: 006-03-0052 | |
| Parish: ORLEANS | |
| Routes: US 90 | |
| Description: JEFFERSON PARISH LINE TO S. CARROLLTON | |
| Type Const:
grading, cold planing asphaltic pavement, superpave asphaltic concrete pavement, pavement patching, and related work. | |
| Low Bidder: BARRIERE CONSTRUCTION CO., LLC | |
| Amount: $1,434,593.00 | |
| Estimated Construction Cost: $1,208,378.90 | |
| Federal Number: | |
| Lead Project: 007-07-0051 | |
| Parish: ASCENSION, E BATON ROUGE | |
| Routes: US 61 | |
| Description: JCT. LA 427 - PECUE RD. | |
| Type Const:
grading, drainage structures, cold planing asphaltic concrete pavement, superpave asphaltic concrete pavement, pavement patching, and related work. | |
| Low Bidder: BARBER BROS. CONTRACTING CO., L.L.C | |
| Amount: $6,579,922.95 | |
| Estimated Construction Cost: $5,940,075.97 | |
| Federal Number: | |
| Lead Project: 008-05-0035 | |
| Parish: ST LANDRY | |
| Routes: US 71 | |
| Description: 1.2 MI. N. OF FLOODWAY LEVEE - W. LA 10 | |
| Type Const:
pavement patching, cold planing asphaltic pavement, superpave asphaltic concrete pavement and related work. | |
| Low Bidder: DIAMOND B CONSTRUCTION CO., L.L.C. | |
| Amount: $3,521,293.52 | |
| Estimated Construction Cost: $4,508,179.82 | |
| Federal Number: | |
| Lead Project: 016-03-0025 | |
| Parish: MOREHOUSE | |
| Routes: US 165 | |
| Description: MAINTENANCE MOWING AND LITTER COLLECTION DISTRICT 05 (MO) | |
| Type Const: contract mowing and litter collection and related work | |
| Low Bidder: MID-SOUTH RESOURCES, INC. | |
| Amount: $35,279.80 | |
| Estimated Construction Cost: $30,200.00 | |
| Federal Number: | |
| Lead Project: 026-07-0027 | |
| Parish: FRANKLIN | |
| Routes: LA 15 | |
| Description: WINNSBORO - BASKIN | |
| Type Const:
grading, drainage structures, cold planing asphaltic concrete, superpave asphaltic concrete overlay, asphaltic surface treatment, pavement patching, and related work. | |
| Low Bidder: D & J CONSTRUCTION CO., INC. | |
| Amount: $4,675,743.49 | |
| Estimated Construction Cost: $5,262,017.01 | |
| Federal Number: | |
| DBE GOAL FED | |
| Lead Project: 029-03-0029 | |
| Parish: VERNON | |
| Routes: LA 468 | |
| Description: US 171 - LA 8 BRIDGES | |
| Type Const:
grading, removal of bridges, drainage structures, lime treatment,class ii base course, superpave asphaltic concrete pavement, concrete slab span bridges, and related work. | |
| Low Bidder: W. E. MCDONALD & SON, LLC. | |
| Amount: $6,383,813.92 | |
| Estimated Construction Cost: $6,177,060.75 | |
| Federal Number: BR-226-1(008) | |
| Lead Project: 038-03-0024 | |
| Parish: MOREHOUSE | |
| Routes: US 425 | |
| Description: LOG CABIN - ARKANSAS STATE LINE | |
| Type Const:
grading, drain struct, lime trmt, class ii bc, superpave acp (alt. a-1), pccp (alt. a-2), concrete girder bridge, and related work | |
| Low Bidder: EUTAW CONSTRUCTION CO. INC. | |
| Amount: $24,278,565.19 | |
| Estimated Construction Cost: $29,804,676.54 | |
| Federal Number: | |
| Lead Project: 053-06-0017 | |
| Parish: RED RIVER | |
| Routes: LA 1 | |
| Description: NATCHITOCHES PARISH LINE -JUNCTION US 84 (SOUTH SECTION) | |
| Type Const:
cold planing asphaltic pavement, pavement patching, superpave asphaltic concrete overlay, asphaltic surface treatment and related work | |
| Low Bidder: MADDEN CONTRACTING CO., INC. | |
| Amount: $1,165,927.40 | |
| Estimated Construction Cost: $1,010,166.70 | |
| Federal Number: | |
| Lead Project: 064-05-0081 | |
| Parish: LAFOURCHE | |
| Routes: LA 1 | |
| Description: REPAIRS TO WEST LAROSE BRIDGE | |
| Type Const:
construction of new machine house, installation of new aerial cables, electrical repairs | |
| Low Bidder: C.E.C., INC. | |
| Amount: $366,000.00 | |
| Estimated Construction Cost: $295,000.00 | |
| Federal Number: ER-ERE1(024) | |
| DBE GOAL FED | |
| Lead Project: 066-05-0025 | |
| Parish: ALLEN | |
| Routes: LA 10 | |
| Description: LA 372 - EVANGELINE PARISH LINE | |
| Type Const:
grading, cold planing, pavement patching, pavement widening, superpave asphaltic concrete pavement and related work. | |
| Low Bidder: DIAMOND B CONSTRUCTION CO., L.L.C. | |
| Amount: $785,450.73 | |
| Estimated Construction Cost: $774,110.67 | |
| Federal Number: STP-0206(500) | |
| Lead Project: 087-01-0029 | |
| Parish: WEBSTER | |
| Routes: LA 159 | |
| Description: LOG MILE 9.500 - JUNCTION LA 2 | |
| Type Const:
grading, drainage structures, pavement patching, superpave asphaltic concrete overlay, and related work. | |
| Low Bidder: MADDEN CONTRACTING CO., INC. | |
| Amount: $2,558,080.34 | |
| Estimated Construction Cost: $2,615,693.63 | |
| Federal Number: | |
| Lead Project: 112-02-0007 | |
| Parish: SABINE | |
| Routes: LA 174 | |
| Description: JCT. LA 191 - JCT. US 171 | |
| Type Const:
grading, drainage structures, cold planing asphaltic concrete, superpave asphaltic concrete, cement treated base course, lime treatment, pvmt. patching, and related work. | |
| Low Bidder: MADDEN CONTRACTING CO., INC. | |
| Amount: $2,036,846.42 | |
| Estimated Construction Cost: $1,887,886.06 | |
| Federal Number: | |
| Lead Project: 123-04-0021 | |
| Parish: WINN | |
| Routes: LA 34 | |
| Description: JCT. LA 3136 - 6.7 MILES NORTH | |
| Type Const:
grading, cold planing asphaltic concrete pavement, lime trea tment,cement treated base course,pavement patching,superpave asphaltic concrete pavement and related work. | |
| Low Bidder: MADDEN CONTRACTING CO., INC. | |
| Amount: $2,771,345.54 | |
| Estimated Construction Cost: $3,146,417.31 | |
| Federal Number: | |
| Lead Project: 209-02-0016 | |
| Parish: JEFF DAVIS | |
| Routes: LA 101 | |
| Description: CALCASIEU PARISH LN. - 3.115 MILES N. OF PARISH LN. | |
| Type Const:
cold planing asphaltic concrete pavement, pavement patching, superpave asphaltic concrete overlay and related work. | |
| Low Bidder: DIAMOND B CONSTRUCTION CO., L.L.C. | |
| Amount: $1,122,110.90 | |
| Estimated Construction Cost: $1,274,273.24 | |
| Federal Number: | |
| Lead Project: 404-02-0015 | |
| Parish: ST MARTIN | |
| Routes: LA 328 | |
| Description: LA 336-1 - CSLM 0.42 | |
| Type Const:
cold planing asphaltic pavement, superpave asphaltic concrete overlay and related work | |
| Low Bidder: H & S CONSTRUCTION CO., INC. | |
| Amount: $205,903.10 | |
| Estimated Construction Cost: $165,899.18 | |
| Federal Number: | |
| Lead Project: 412-01-0008 | |
| Parish: TERREBONNE, LAFOURCHE | |
| Routes: LA 316 | |
| Description: LA 24 - LAFOURCHE PARISH LINE AND LA 3087 - LA 182 | |
| Type Const:
cold planing asph pavement, superpave asphalic conc ovly, pavement patching and related work. | |
| Low Bidder: HUEY STOCKSTILL, INC. | |
| Amount: $1,104,689.80 | |
| Estimated Construction Cost: $1,426,533.18 | |
| Federal Number: | |
| REBID | |
| Lead Project: 451-06-0144 | |
| Parish: OUACHITA | |
| Routes: I-20 | |
| Description: MAINTENANCE MOWING DISTRICT 05 (MO) | |
| Type Const: maintenance mowing & litter collection and related work | |
| Low Bidder: CRAFT ENTERPRISES, LLC | |
| Amount: $180,000.00 | |
| Estimated Construction Cost: $200,110.00 | |
| Federal Number: | |
| Lead Project: 451-08-0072 | |
| Parish: MADISON | |
| Routes: I-20 | |
| Description: MAINTENANCE MOWING AND LITTER COLLECTION DISTRICT 05 (MO) | |
| Type Const: contract mowing and litter collection and related work | |
| Low Bidder: CLARK COMMERCIAL SERVICES LLC | |
| Amount: $374,196.90 | |
| Estimated Construction Cost: $318,833.00 | |
| Federal Number: | |
| Lead Project: 610-01-0022 | |
| Parish: ORLEANS | |
| Routes: | |
| Description: ADMINISTRATION BUILDING EXPANSION | |
| Type Const: building, electrical, mechanical, and related work | |
| Low Bidder: JAROY CONSTRUCTION, INC. | |
| Amount: $3,799,661.00 | |
| Estimated Construction Cost: $3,102,250.00 | |
| Federal Number: | |
| READV | |
| DBE GOAL FED | |
| Lead Project: 742-17-0150 | |
| Parish: E BATON ROUGE | |
| Routes: | |
| Description: CENTRAL THRUWAY BRIDGES (COMITE AND BEAVER BAYOU NO. 1) | |
| Type Const: precast-prestressed concrete girder span bridges and related work. | |
| Low Bidder: L & A CONTRACTING CO. | |
| Amount: $23,830,132.62 | |
| Estimated Construction Cost: $31,259,475.00 | |
| Federal Number: STP-1705(523) | |
| Lead Project: 824-12-0012 | |
| Parish: IBERVILLE | |
| Routes: LA 76 | |
| Description: JCT. LA 77 - JCT. LA 3000 | |
| Type Const:
grading, lime treatment, in-place cement treated base course, cold planing asphaltic concrete pavement, superpave asphaltic concrete pavement and related work. | |
| Low Bidder: F.G. SULLIVAN, JR. CONTRACTOR LLC | |
| Amount: $2,462,007.20 | |
| Estimated Construction Cost: $2,503,084.32 | |
| Federal Number: | |
| DBE GOAL FED | |
| Lead Project: 826-03-0012 | |
| Parish: JEFFERSON | |
| Routes: LA 3152, LA 3139 | |
| Description: CLEARVIEW / EARHART DRAINAGE IMPROVEMENTS (PHASE 2) | |
| Type Const:
grading, excavation and embankment, drainage structures, water and sewer modifications, and related work. | |
| Low Bidder: PHYLWAY CONSTRUCTION LLC | |
| Amount: $4,831,575.00 | |
| Estimated Construction Cost: $5,195,062.30 | |
| Federal Number: DE-2606(512) | |
| Lead Project: 834-06-0011 | |
| Parish: MOREHOUSE | |
| Routes: LA 8301 | |
| Description: JCT US 425 TO BASTROP CITY LIMITS | |
| Type Const:
superpave asphaltic concrete overlay, ashpaltic surface treatment, cold planing, pavement patching, and related work. | |
| Low Bidder: DIAMOND B CONSTRUCTION CO., L.L.C. | |
| Amount: $1,276,774.65 | |
| Estimated Construction Cost: $861,537.21 | |
| Federal Number: | |
| DBE GOAL FED | |
| Lead Project: 853-27-0022 | |
| Parish: TANGIPAHOA | |
| Routes: LA 443 | |
| Description: JCT U.S. 190 - JCT LA 40 | |
| Type Const:
grading, drain struct, cold planing asph pvmt, superpave ac ovly, pavement widening, pavement patching and related work | |
| Low Bidder: DIAMOND B CONSTRUCTION CO., L.L.C. | |
| Amount: $3,535,013.20 | |
| Estimated Construction Cost: $4,975,036.70 | |
| Federal Number: STP-5306(515) | |