Lead Project: 006-03-0052
Parish: ORLEANS
Routes: US 90
Description: JEFFERSON PARISH LINE TO S. CARROLLTON
Type Const: grading, cold planing asphaltic pavement, superpave asphaltic concrete pavement,
pavement patching, and related work.
Estimated Construction Cost: $1,208,378.90
 
RankLicenseBidderConstruction Bid
1 06276 BARRIERE CONSTRUCTION CO., LLC $1,434,593.00
2 02179 BOH BROS. CONSTRUCTION CO., LLC. $1,687,968.50
 
Item Number Item Description Quantity Unit of Measure - 1 -
BARRIERE CONSTRUCTION CO., LLC
- 2 -
BOH BROS. CONSTRUCTION CO., LLC.

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-01 removal of structures & obstructions lump      LUMP 12,000.00 12,000.00 1,000.00 1,000.00        
202-02-F removal of concrete combination curb & gutter 600.0    LNFT 11.25 6,750.00 25.00 15,000.00        
203-07 borrow (vehicular measurement) 250      CUYD 50.00 12,500.00 50.00 12,500.00        
502-01 superpave asphalt concrete 5,821.9    TON 80.00 465,752.00 85.00 494,861.50        
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
720.0    TON 100.00 72,000.00 150.00 108,000.00        
509-01 cold planing asphaltic pavement 50,436      SQYD 4.00 201,744.00 3.50 176,526.00        
509-02 contractor retained reclaimed asphaltic pavement - 2,101      CUYD 1.00 - 2,101.00 5.00 - 10,505.00        
510-01-A pavement patching (6" minimum thickness) 750      SQYD 60.00 45,000.00 40.00 30,000.00        
510-01-B pavement patching (12" minimum thickness) 2,500      SQYD 90.00 225,000.00 100.00 250,000.00        
510-03 pavement joint repair 100.0    TON 100.00 10,000.00 200.00 20,000.00        
602-03 cleaning and sealing random cracks 10,686      LNFT 2.00 21,372.00 3.00 32,058.00        
702-04-A adjusting manholes 108      EACH 100.00 10,800.00 100.00 10,800.00        
702-04-B adjusting catch basins 10      EACH 1,000.00 10,000.00 1,000.00 10,000.00        
706-01-A concrete walk (4" thick) 200.0    SQYD 75.00 15,000.00 60.00 12,000.00        
706-04 handicapped curb ramps 20      EACH 1,375.00 27,500.00 1,000.00 20,000.00        
707-03 combination concrete curb & gutter 600.0    LNFT 44.50 26,700.00 65.00 39,000.00        
713-01 temporary signs & barricades lump      LUMP 46,000.00 46,000.00 220,000.00 220,000.00        
713-02-C temporary pavement markings (8" width) 3,000      LNFT 0.10 300.00 0.30 900.00        
713-02-D temporary pavement markings (12" width) 1,800      LNFT 0.20 360.00 0.80 1,440.00        
713-02-E temporary pavement markings (24" width) 1,000      LNFT 0.30 300.00 1.00 1,000.00        
713-03-A temporary pavement markings (broken line)(4" width)(4'
length)
6.640  MILE 200.00 1,328.00 500.00 3,320.00        
713-03-B temporary pavement markings (broken line)(4" width)
(10' length)
6.640  MILE 20.00 132.80 325.00 2,158.00        
713-04-A temporary pavement markings (solid line)(4" width) 6.640  MILE 30.00 199.20 525.00 3,486.00        
727-01 mobilization lump      LUMP 140,000.00 140,000.00 160,000.00 160,000.00        
731-02 reflectorized raised pavement markers 500      EACH 6.00 3,000.00 6.00 3,000.00        
732-01-C plastic pavement striping (8" width) 1,500      LNFT 1.00 1,500.00 1.00 1,500.00        
732-01-D plastic pavement striping (12" width) 900      LNFT 2.00 1,800.00 2.00 1,800.00        
732-01-E plastic pavement striping (24" width) 500      LNFT 3.50 1,750.00 3.00 1,500.00        
732-02-A plastic pavement striping (solid line) (4" width) 3.320  MILE 3,000.00 9,960.00 2,500.00 8,300.00        
732-03-A plastic pavement striping (broken line)(4" width) 3.320  MILE 800.00 2,656.00 700.00 2,324.00        
740-01 construction layout lump      LUMP 35,000.00 35,000.00 10,000.00 10,000.00        
741-11 adjusting water valve and meter box 3      EACH 430.00 1,290.00 1,000.00 3,000.00        
S-001 dynamic message sign unit 2      EACH 5,000.00 10,000.00 8,000.00 16,000.00        
S-002 tree trimming 20      EACH 600.00 12,000.00 700.00 14,000.00        
S-003 tree pruning 20      EACH 100.00 2,000.00 150.00 3,000.00        
S-004 cleaning catch basins 50      EACH 100.00 5,000.00 200.00 10,000.00        
                       
 CONTRACTOR TOTAL       1,434,593.00   1,687,968.50        