| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 2 - BARRIERE CONSTRUCTION CO., LLC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-H |
removal of guard rail
|
936   |
LNFT |
12.00 |
11,232.00 |
6.00 |
5,616.00 |
|
|
|
|
| 203-07 |
borrow (vehicular measurement)
|
2,200   |
CUYD |
15.00 |
33,000.00 |
19.00 |
41,800.00 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
200   |
EACH |
10.00 |
2,000.00 |
10.00 |
2,000.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
2,700   |
LNFT |
1.60 |
4,320.00 |
1.60 |
4,320.00 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
1,054   |
CUYD |
23.00 |
24,242.00 |
40.00 |
42,160.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
15,457.4 |
TON |
69.00 |
1,066,560.60 |
67.00 |
1,035,645.80 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
2,240.0 |
TON |
128.00 |
286,720.00 |
10.00 |
22,400.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
97,974   |
SQYD |
1.25 |
122,467.50 |
2.20 |
215,542.80 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 3,062   |
CUYD |
0.10 |
- 306.20 |
6.00 |
- 18,372.00 |
|
|
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
6,430   |
SQYD |
63.00 |
405,090.00 |
45.00 |
289,350.00 |
|
|
|
|
| 510-02 |
pavement widening
|
21,700.5 |
SQYD |
35.00 |
759,517.50 |
47.00 |
1,019,923.50 |
|
|
|
|
| 701-02-D/E |
cross drain pipe arch (24" equiv. rcpa or 30" equiv.
cmpa) |
84   |
LNFT |
210.00 |
17,640.00 |
200.00 |
16,800.00 |
|
|
|
|
| 701-02-F/G |
cross drain pipe arch (36" equiv. rcpa or 42" equiv.
cmpa) |
600   |
LNFT |
250.00 |
150,000.00 |
250.00 |
150,000.00 |
|
|
|
|
| 701-02-G/H |
cross drain pipe arch (42" equiv. rcpa or 48" equiv.
cmpa) |
80   |
LNFT |
310.00 |
24,800.00 |
300.00 |
24,000.00 |
|
|
|
|
| 701-02-J/L |
cross drain pipe arch (60" equiv. rcpa or 72" equiv.
cmpa) |
238   |
LNFT |
500.00 |
119,000.00 |
470.00 |
111,860.00 |
|
|
|
|
| 701-02-N/P |
cross drain pipe arch (84" equiv. rcpa or 96" equiv.
cmpa) |
112   |
LNFT |
725.00 |
81,200.00 |
700.00 |
78,400.00 |
|
|
|
|
| 704-03 |
blocked out guard rail
|
375.0 |
LNFT |
20.00 |
7,500.00 |
20.00 |
7,500.00 |
|
|
|
|
| 704-07-A |
guard rail bridge attachments (single thrie beam)
|
50.0 |
LNFT |
45.00 |
2,250.00 |
45.00 |
2,250.00 |
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
275.0 |
LNFT |
55.00 |
15,125.00 |
54.00 |
14,850.00 |
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
15   |
EACH |
2,200.00 |
33,000.00 |
2,200.00 |
33,000.00 |
|
|
|
|
| 707-04 |
asphaltic curb
|
80.0 |
LNFT |
63.00 |
5,040.00 |
50.00 |
4,000.00 |
|
|
|
|
| 711-03-C |
riprap (30 lb)
|
88.4 |
TON |
110.00 |
9,724.00 |
120.00 |
10,608.00 |
|
|
|
|
| 713-01 |
temporary signs and barricades
|
lump |
LUMP |
33,000.00 |
33,000.00 |
100,000.00 |
100,000.00 |
|
|
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
22   |
LNFT |
1.00 |
22.00 |
1.00 |
22.00 |
|
|
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
24.660 |
MILE |
130.00 |
3,205.80 |
50.00 |
1,233.00 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
10.580 |
MILE |
325.00 |
3,438.50 |
300.00 |
3,174.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
50.780 |
MILE |
525.00 |
26,659.50 |
480.00 |
24,374.40 |
|
|
|
|
| 713-05-D |
temporary pavement legends and symbols (rr crossing)
|
4   |
EACH |
220.00 |
880.00 |
200.00 |
800.00 |
|
|
|
|
| 726-01 |
bedding material
|
111.3 |
CUYD |
80.00 |
8,904.00 |
80.00 |
8,904.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
146,000.00 |
146,000.00 |
360,000.00 |
360,000.00 |
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
114   |
EACH |
77.00 |
8,778.00 |
75.00 |
8,550.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
1,086   |
EACH |
6.00 |
6,516.00 |
5.50 |
5,973.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
11   |
LNFT |
3.50 |
38.50 |
7.00 |
77.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
25.390 |
MILE |
2,600.00 |
66,014.00 |
2,500.00 |
63,475.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
5.290 |
MILE |
650.00 |
3,438.50 |
700.00 |
3,703.00 |
|
|
|
|
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
2   |
EACH |
475.00 |
950.00 |
450.00 |
900.00 |
|
|
|
|
| 735-01 |
mailboxes
|
191   |
EACH |
1.00 |
191.00 |
5.00 |
955.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
151   |
EACH |
125.00 |
18,875.00 |
125.00 |
18,875.00 |
|
|
|
|
| 735-04 |
mailbox supports (multiple)
|
12   |
EACH |
250.00 |
3,000.00 |
350.00 |
4,200.00 |
|
|
|
|
| 739-01 |
hydro-seeding
|
4.98 |
ACRE |
1,000.00 |
4,980.00 |
1,200.00 |
5,976.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
20,000.00 |
20,000.00 |
38,000.00 |
38,000.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
3,535,013.20 |
|
3,762,845.50 |
|
|
|
|
|