Letting of 10/31/2007 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 834-06-0011
Parish: MOREHOUSE
Routes: LA 8301
Description: JCT US 425 TO BASTROP CITY LIMITS
Type Const: superpave asphaltic concrete overlay, ashpaltic surface treatment, cold planing,
pavement patching, and related work.
Estimated Construction Cost: $861,537.21
 
RankLicenseBidderConstruction Bid
1 12487 DIAMOND B CONSTRUCTION CO., L.L.C. $1,276,774.65
2 05789 D & J CONSTRUCTION CO., INC. $1,414,235.74
 
Item Number Item Description Quantity Unit of Measure - 1 -
DIAMOND B CONSTRUCTION CO., L.L.C.
- 2 -
D & J CONSTRUCTION CO., INC.

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-01 removal of structures & obstructions lump      LUMP 4,000.00 4,000.00 15,000.00 15,000.00        
202-02-D removal of concrete walks & drives 402      SQYD 20.00 8,040.00 15.00 6,030.00        
202-02-F removal of concrete combination curb & gutter 54.0    LNFT 20.00 1,080.00 15.00 810.00        
203-07 borrow (vehicular measurement) 15      CUYD 25.00 375.00 75.00 1,125.00        
401-02 aggregate surface course (adjusted vehicular
measurement)
234      CUYD 65.00 15,210.00 50.00 11,700.00        
502-01 superpave asphaltic concrete 3,405.3    TON 120.00 408,636.00 145.00 493,768.50        
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
669.9    TON 220.00 147,378.00 145.00 97,135.50        
507-01-A asphaltic material (crs-2p emulsion) 2,436      GAL 3.00 7,308.00 5.00 12,180.00        
507-02-B aggregate (s2) 3,582      SQYD 8.50 30,447.00 4.00 14,328.00        
507-02-C aggregate (s3) 3,582      SQYD 8.00 28,656.00 4.00 14,328.00        
509-01 cold planing asphaltic pavement 20,150      SQYD 4.00 80,600.00 4.00 80,600.00        
509-02 contractor retained reclaimed asphaltic pavement - 809      CUYD 0.10 - 80.90 0.01 - 8.09        
510-01-B pavement patching (12" minimum thickness) 1,363      SQYD 130.00 177,190.00 225.00 306,675.00        
602-02-A cleaning and resealing existing longitudinal pavement
joints
1,240      LNFT 4.00 4,960.00 4.50 5,580.00        
602-02-B cleaning and resealing existing transverse pavement
joints
1,612      LNFT 4.00 6,448.00 4.50 7,254.00        
701-01-G cross drain pipe (18" rcp/pcp) 50      LNFT 175.00 8,750.00 200.00 10,000.00        
701-12-I corrugated metal pipe (extension)(24") 10      LNFT 200.00 2,000.00 250.00 2,500.00        
701-15 concrete collar 1      EACH 850.00 850.00 750.00 750.00        
702-04-A adjusting manholes 30      EACH 2,000.00 60,000.00 1,750.00 52,500.00        
702-04-B adjusting catch basins 2      EACH 3,000.00 6,000.00 3,000.00 6,000.00        
706-02-C concrete drive (6" thick) 400.1    SQYD 80.00 32,008.00 75.00 30,007.50        
707-03 combination concrete curb & gutter 54.0    LNFT 30.00 1,620.00 30.00 1,620.00        
713-01 temporary signs & barricades lump      LUMP 25,000.00 25,000.00 65,000.00 65,000.00        
713-03-A temporary pavement markings (broken line)(4" width)(4'
length)
4.337  MILE 150.00 650.55 225.00 975.83        
713-03-B temporary pavement markings (broken line)(4" width)
(10' length)
0.048  MILE 400.00 19.20 250.00 12.00        
713-04-A temporary pavement markings (solid line)(4" width) 9.566  MILE 800.00 7,652.80 250.00 2,391.50        
716-01-A mulch (vegetative) 2.5    TON 500.00 1,250.00 1,200.00 3,000.00        
717-01 seeding 56      LB 10.00 560.00 15.00 840.00        
718-01 fertilizer 1,250      LB 0.50 625.00 0.75 937.50        
726-01 bedding material 16.7    CUYD 1,000.00 16,700.00 105.00 1,753.50        
727-01 mobilization lump      LUMP 125,000.00 125,000.00 110,000.00 110,000.00        
729-16-B object marker assembly (type 2) 4      EACH 60.00 240.00 100.00 400.00        
731-02 reflectorized raised pavement markers 202      EACH 6.00 1,212.00 12.00 2,424.00        
732-02-A plastic pavement striping (solid line) (4" width) 3.502  MILE 3,000.00 10,506.00 3,500.00 12,257.00        
732-03-A plastic pavement striping (broken line)(4" width) 0.016  MILE 1,000.00 16.00 15,000.00 240.00        
735-01 mailboxes 86      EACH 1.00 86.00 5.00 430.00        
735-02 mailbox supports (single) 49      EACH 150.00 7,350.00 125.00 6,125.00        
735-03 mailbox supports (double) 11      EACH 250.00 2,750.00 250.00 2,750.00        
735-04 mailbox supports (multiple) 2      EACH 450.00 900.00 350.00 700.00        
740-01 construction layout lump      LUMP 21,000.00 21,000.00 10,000.00 10,000.00        
741-11 adjusting water valve and meter box 5      EACH 1,000.00 5,000.00 1,000.00 5,000.00        
S-001 saw cutting concrete drives (6" depth) 167      LNFT 10.00 1,670.00 12.00 2,004.00        
S-002 sawing and sealing longitudinal joints in asphaltic
concrete overlay
1,240      LNFT 5.00 6,200.00 4.00 4,960.00        
S-003 sawing and sealing transverse joints in asphaltic
concrete overlay
1,612      LNFT 5.00 8,060.00 4.00 6,448.00        
S-004 sawcuts in asphaltic concrete lifts 2,852      LNFT 1.00 2,852.00 2.00 5,704.00        
                       
 CONTRACTOR TOTAL       1,276,774.65   1,414,235.74        