| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - EUTAW CONSTRUCTION CO. INC. |
- 2 - AUSTIN BRIDGE & ROAD, LP |
- 3 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 4 - JAMES CONSTRUCTION GROUP LLC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing and grubbing
|
lump |
lump |
770,000.00 |
770,000.00 |
900,000.00 |
900,000.00 |
500,000.00 |
500,000.00 |
500,000.00 |
500,000.00 |
| 202-01 |
removal of structures & obstructions
|
lump |
lump |
167,500.00 |
167,500.00 |
50,000.00 |
50,000.00 |
40,000.00 |
40,000.00 |
45,000.00 |
45,000.00 |
| 202-02-A-01 |
removal of 2-span timber bridge (sta. 27+128.0)
|
1   |
ea |
12,000.00 |
12,000.00 |
50,000.00 |
50,000.00 |
15,000.00 |
15,000.00 |
9,000.00 |
9,000.00 |
| 202-02-A-02 |
removal of 2-span timber bridge (sta. 29+958.6)
|
1   |
ea |
12,000.00 |
12,000.00 |
50,000.00 |
50,000.00 |
15,000.00 |
15,000.00 |
9,000.00 |
9,000.00 |
| 202-02-A-03 |
removal of 2-span timber bridge (sta. 33+922.8)
|
1   |
ea |
12,000.00 |
12,000.00 |
50,000.00 |
50,000.00 |
15,000.00 |
15,000.00 |
9,000.00 |
9,000.00 |
| 202-02-B-01 |
removal of 2 concrete box culverts (sta. 21+616.477;
2-900 mm x 900 mm) |
1   |
ea |
7,800.00 |
7,800.00 |
7,500.00 |
7,500.00 |
10,000.00 |
10,000.00 |
4,600.00 |
4,600.00 |
| 202-02-B-02 |
removal of concrete box culvert headwall (sta. 20+603)
|
1   |
ea |
4,500.00 |
4,500.00 |
3,500.00 |
3,500.00 |
4,000.00 |
4,000.00 |
2,300.00 |
2,300.00 |
| 202-02-C |
removal of portland cement concrete pavement
|
17,571   |
sq m |
4.00 |
70,284.00 |
15.00 |
263,565.00 |
9.00 |
158,139.00 |
5.00 |
87,855.00 |
| 202-02-D |
removal of concrete walks & drives
|
1,260   |
sq m |
4.00 |
5,040.00 |
14.00 |
17,640.00 |
20.00 |
25,200.00 |
3.00 |
3,780.00 |
| 202-02-G |
removal of surfacing & stabilized base
|
23,250.5 |
sq m |
3.50 |
81,376.75 |
7.00 |
162,753.50 |
3.35 |
77,889.18 |
3.00 |
69,751.50 |
| 202-02-H |
removal of guard rail
|
310   |
ln m |
11.00 |
3,410.00 |
10.00 |
3,100.00 |
115.00 |
35,650.00 |
8.00 |
2,480.00 |
| 202-02-01 |
removal of 10.4 m x 11.6 m wood frame residence (rt.
of sta. 22+133) (contains non-friable asbestos) |
1   |
each |
4,500.00 |
4,500.00 |
5,700.00 |
5,700.00 |
3,250.00 |
3,250.00 |
1,000.00 |
1,000.00 |
| 202-02-02 |
removal of 9.3 m x 12.3 m wood frame residence (lt. of
sta. 22+691) (contains transite asbestos siding) |
1   |
each |
4,500.00 |
4,500.00 |
5,100.00 |
5,100.00 |
3,250.00 |
3,250.00 |
1,000.00 |
1,000.00 |
| 202-02-03 |
removal of 17.8 m x 8.5 m wood frame residence (rt. of
sta. 22+950) (cont. friable & transite asbestos siding) |
1   |
each |
4,500.00 |
4,500.00 |
1,000.00 |
1,000.00 |
3,250.00 |
3,250.00 |
1,000.00 |
1,000.00 |
| 202-02-04 |
removal of 32.8 m x 12.2 m abandoned gas station (lt.
of sta. 23+412) (contains transite asbestos siding) |
1   |
each |
13,500.00 |
13,500.00 |
9,600.00 |
9,600.00 |
5,250.00 |
5,250.00 |
3,000.00 |
3,000.00 |
| 202-02-05 |
removal of 10.5 m x 8.5 m building (lt. of sta. 23+702)
(contains transite asbestos siding) |
1   |
each |
4,500.00 |
4,500.00 |
3,600.00 |
3,600.00 |
3,250.00 |
3,250.00 |
1,000.00 |
1,000.00 |
| 202-02-06 |
removal of 19.9 m x 14.6 m wood frame residence (rt.
of sta. 23+870) (contains non-friable asbestos) |
1   |
each |
4,500.00 |
4,500.00 |
6,400.00 |
6,400.00 |
3,250.00 |
3,250.00 |
1,000.00 |
1,000.00 |
| 202-02-07 |
removal of 8.1 m x 12.6 m building (lt. of sta. 23+930)
(contains non-friable asbestos) |
1   |
each |
4,500.00 |
4,500.00 |
1,000.00 |
1,000.00 |
2,750.00 |
2,750.00 |
1,000.00 |
1,000.00 |
| 202-02-08 |
removal of 8.6 m x 20.3 m wood frame residence with no
slab (lt. of sta. 24+185)(contains non-friable asbestos) |
1   |
each |
4,500.00 |
4,500.00 |
9,000.00 |
9,000.00 |
2,750.00 |
2,750.00 |
1,000.00 |
1,000.00 |
| 202-02-09 |
removal of 5.4 m x 5.7 m wood shed with no slab (lt.
of sta. 24+193) (contains non-friable asbestos) |
1   |
each |
2,850.00 |
2,850.00 |
1,300.00 |
1,300.00 |
1,250.00 |
1,250.00 |
500.00 |
500.00 |
| 202-02-10 |
removal of 15.4 m x 20.6 m wood frame residence with
no slab (lt. of sta. 27+986)(contains non-friable asbestos) |
1   |
each |
4,500.00 |
4,500.00 |
6,600.00 |
6,600.00 |
2,750.00 |
2,750.00 |
2,000.00 |
2,000.00 |
| 202-02-11 |
removal of 18.3 m x 11.7 m brick residence on slab
(lt. of sta. 31+000) (contains non-friable asbestos) |
1   |
each |
4,500.00 |
4,500.00 |
10,000.00 |
10,000.00 |
3,750.00 |
3,750.00 |
2,500.00 |
2,500.00 |
| 202-07 |
plugging existing water wells
|
18   |
each |
2,750.00 |
49,500.00 |
1,500.00 |
27,000.00 |
2,750.00 |
49,500.00 |
1,500.00 |
27,000.00 |
| 203-01 |
general excavation
|
380,276   |
cu m |
3.35 |
1,273,924.60 |
4.00 |
1,521,104.00 |
6.50 |
2,471,794.00 |
7.80 |
2,966,152.80 |
| 203-03 |
embankment
|
301,936   |
cu m |
4.00 |
1,207,744.00 |
8.00 |
2,415,488.00 |
7.50 |
2,264,520.00 |
11.70 |
3,532,651.20 |
| 203-04-A |
nonplastic embankment (stone)
|
1,923   |
cu m |
135.00 |
259,605.00 |
150.00 |
288,450.00 |
145.00 |
278,835.00 |
99.00 |
190,377.00 |
| 204-02 |
temporary hay or straw bales
|
217   |
ea |
10.00 |
2,170.00 |
7.00 |
1,519.00 |
34.00 |
7,378.00 |
16.00 |
3,472.00 |
| 204-05-A |
temporary sediment check dams (hay)
|
109   |
ea |
100.00 |
10,900.00 |
100.00 |
10,900.00 |
295.00 |
32,155.00 |
120.00 |
13,080.00 |
| 204-05-B |
temporary sediment check dams (stone)
|
106   |
ea |
385.00 |
40,810.00 |
500.00 |
53,000.00 |
680.00 |
72,080.00 |
300.00 |
31,800.00 |
| 204-06 |
temporary silt fencing
|
22,001   |
ln m |
4.55 |
100,104.55 |
5.00 |
110,005.00 |
7.75 |
170,507.75 |
7.20 |
158,407.20 |
| 204-07 |
temporary stone construction entrance
|
5   |
ea |
6,000.00 |
30,000.00 |
2,000.00 |
10,000.00 |
4,400.00 |
22,000.00 |
2,000.00 |
10,000.00 |
| 302-02-B-01 |
class ii base course (150 mm thick)(soil cement)
|
219,466.3 |
sq m |
9.30 |
2,041,036.59 |
8.00 |
1,755,730.40 |
7.65 |
1,678,917.20 |
7.50 |
1,645,997.25 |
| 304-05 |
lime treatiment (type e)
|
1,657.64 |
Mg |
220.00 |
364,680.80 |
110.00 |
182,340.40 |
270.00 |
447,562.80 |
200.00 |
331,528.00 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
420   |
cu m |
80.00 |
33,600.00 |
125.00 |
52,500.00 |
40.00 |
16,800.00 |
70.00 |
29,400.00 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
4,000.0 |
cu m |
80.00 |
320,000.00 |
75.00 |
300,000.00 |
53.00 |
212,000.00 |
95.00 |
380,000.00 |
| 510-01-B |
pavement patching (300 mm thickness)
|
1,354   |
sq m |
185.00 |
250,490.00 |
110.00 |
148,940.00 |
110.00 |
148,940.00 |
220.00 |
297,880.00 |
| 701-01-F |
cross drain pipe (375 mm rcp/pcp)
|
649.1 |
ln m |
110.00 |
71,401.00 |
175.00 |
113,592.50 |
185.00 |
120,083.50 |
154.00 |
99,961.40 |
| 701-01-I |
cross drain pipe (600 mm rcp/pcp)
|
25.5 |
ln m |
150.00 |
3,825.00 |
225.00 |
5,737.50 |
260.00 |
6,630.00 |
230.00 |
5,865.00 |
| 701-01-K |
cross drain pipe (750 mm rcp/pcp)
|
201.7 |
ln m |
210.00 |
42,357.00 |
275.00 |
55,467.50 |
305.00 |
61,518.50 |
260.00 |
52,442.00 |
| 701-01-M |
cross drain pipe (900 mm rcp/pcp)
|
205.1 |
ln m |
255.00 |
52,300.50 |
350.00 |
71,785.00 |
365.00 |
74,861.50 |
372.00 |
76,297.20 |
| 701-01-N |
cross drain pipe (1050 mm rcp/pcp)
|
130.5 |
ln m |
315.00 |
41,107.50 |
450.00 |
58,725.00 |
495.00 |
64,597.50 |
490.00 |
63,945.00 |
| 701-01-O |
cross drain pipe (1200 mm rcp/pcp)
|
143.4 |
ln m |
390.00 |
55,926.00 |
575.00 |
82,455.00 |
560.00 |
80,304.00 |
560.00 |
80,304.00 |
| 701-02-F |
cross drain pipe arch (900 mm equiv. rcpa)
|
30.0 |
ln m |
300.00 |
9,000.00 |
375.00 |
11,250.00 |
400.00 |
12,000.00 |
380.00 |
11,400.00 |
| 701-02-G |
cross drain pipe arch (1050 mm equiv. rcpa)
|
806.5 |
ln m |
355.00 |
286,307.50 |
475.00 |
383,087.50 |
510.00 |
411,315.00 |
472.00 |
380,668.00 |
| 701-02-H |
cross drain pipe arch (1200 mm equiv. rcpa)
|
229.0 |
ln m |
425.00 |
97,325.00 |
625.00 |
143,125.00 |
660.00 |
151,140.00 |
570.00 |
130,530.00 |
| 701-02-I |
cross drain pipe arch (1350 mm equiv. rcpa)
|
121.0 |
ln m |
500.00 |
60,500.00 |
700.00 |
84,700.00 |
760.00 |
91,960.00 |
710.00 |
85,910.00 |
| 701-05-G |
side drain pipe (450 mm)
|
329.5 |
ln m |
115.00 |
37,892.50 |
125.00 |
41,187.50 |
160.00 |
52,720.00 |
152.00 |
50,084.00 |
| 701-05-G-01 |
side drain pipe (450 mm)(erosion)
|
35.0 |
ln m |
125.00 |
4,375.00 |
150.00 |
5,250.00 |
160.00 |
5,600.00 |
138.00 |
4,830.00 |
| 701-05-I |
side drain pipe (600 mm)
|
345.0 |
ln m |
155.00 |
53,475.00 |
175.00 |
60,375.00 |
200.00 |
69,000.00 |
180.00 |
62,100.00 |
| 701-05-K |
side drain pipe (750 mm)
|
75.5 |
ln m |
190.00 |
14,345.00 |
275.00 |
20,762.50 |
300.00 |
22,650.00 |
255.00 |
19,252.50 |
| 701-05-M |
side drain pipe (900 mm)
|
62.5 |
ln m |
255.00 |
15,937.50 |
350.00 |
21,875.00 |
310.00 |
19,375.00 |
355.00 |
22,187.50 |
| 701-05-N |
side drain pipe (1050 mm)
|
42.5 |
ln m |
320.00 |
13,600.00 |
450.00 |
19,125.00 |
410.00 |
17,425.00 |
525.00 |
22,312.50 |
| 701-05-P |
side drain pipe (1350 mm)
|
39.0 |
ln m |
435.00 |
16,965.00 |
650.00 |
25,350.00 |
510.00 |
19,890.00 |
665.00 |
25,935.00 |
| 701-15 |
concrete collars
|
4   |
ea |
700.00 |
2,800.00 |
1,000.00 |
4,000.00 |
850.00 |
3,400.00 |
850.00 |
3,400.00 |
| 702-03-A |
catch basins (cb-01m)
|
32   |
ea |
3,000.00 |
96,000.00 |
1,900.00 |
60,800.00 |
2,500.00 |
80,000.00 |
4,200.00 |
134,400.00 |
| 702-03-B |
catch basins (cb-02m)
|
6   |
ea |
4,575.00 |
27,450.00 |
4,500.00 |
27,000.00 |
4,800.00 |
28,800.00 |
5,700.00 |
34,200.00 |
| 702-07-A |
cross drain safety end (type 1)
|
5   |
each |
1,175.00 |
5,875.00 |
3,000.00 |
15,000.00 |
3,900.00 |
19,500.00 |
2,800.00 |
14,000.00 |
| 702-07-B |
cross drain safety end (type 2)
|
1   |
each |
4,000.00 |
4,000.00 |
6,000.00 |
6,000.00 |
8,200.00 |
8,200.00 |
4,200.00 |
4,200.00 |
| 702-08-A |
side drain safety end (type 1)
|
15   |
each |
1,175.00 |
17,625.00 |
3,000.00 |
45,000.00 |
2,200.00 |
33,000.00 |
1,800.00 |
27,000.00 |
| 704-01-A |
guard rail (single thrie beam)(950 mm post spacing)
|
25.25 |
ln m |
145.00 |
3,661.25 |
145.00 |
3,661.25 |
315.00 |
7,953.75 |
145.00 |
3,661.25 |
| 704-03 |
blocked out guard rail
|
218.82 |
ln m |
65.00 |
14,223.30 |
65.00 |
14,223.30 |
6.00 |
1,312.92 |
65.00 |
14,223.30 |
| 704-06-A |
guard rail anchor sections (trailing end)(single thrie
beam) |
3.82 |
ln m |
175.00 |
668.50 |
175.00 |
668.50 |
300.00 |
1,146.00 |
175.00 |
668.50 |
| 704-08-B |
guard rail transitions (double thrie beam)
|
15.24 |
ln m |
155.00 |
2,362.20 |
155.00 |
2,362.20 |
185.00 |
2,819.40 |
155.00 |
2,362.20 |
| 704-11-A |
guard rail end treatment (flared)
|
2   |
ea |
2,250.00 |
4,500.00 |
2,250.00 |
4,500.00 |
2,100.00 |
4,200.00 |
2,250.00 |
4,500.00 |
| 704-11-B |
guard rail end treatment (tangent)
|
2   |
ea |
2,750.00 |
5,500.00 |
2,750.00 |
5,500.00 |
2,500.00 |
5,000.00 |
2,750.00 |
5,500.00 |
| 705-01 |
barbed wire fence
|
2,053   |
ln m |
16.00 |
32,848.00 |
16.40 |
33,669.20 |
17.50 |
35,927.50 |
20.00 |
41,060.00 |
| 705-02 |
combination mesh & barbed wire fence
|
3,540   |
ln m |
19.00 |
67,260.00 |
17.40 |
61,596.00 |
18.50 |
65,490.00 |
23.00 |
81,420.00 |
| 705-04 |
single swinging driveway gates
|
15   |
ea |
500.00 |
7,500.00 |
500.00 |
7,500.00 |
550.00 |
8,250.00 |
500.00 |
7,500.00 |
| 705-05 |
double swinging driveway gates
|
2   |
dbgt |
1,000.00 |
2,000.00 |
750.00 |
1,500.00 |
800.00 |
1,600.00 |
1,000.00 |
2,000.00 |
| 705-06-A |
chain link fence (1200 mm height)
|
350   |
ln m |
55.00 |
19,250.00 |
20.00 |
7,000.00 |
21.00 |
7,350.00 |
50.53 |
17,685.50 |
| 706-02-C |
concrete drive (150 mm thick)
|
1,164.4 |
sq m |
63.00 |
73,357.20 |
70.00 |
81,508.00 |
75.00 |
87,330.00 |
52.00 |
60,548.80 |
| 706-03-C |
incidental concrete paving (150 mm thickness)
|
456.4 |
sq m |
79.00 |
36,055.60 |
125.00 |
57,050.00 |
70.00 |
31,948.00 |
110.00 |
50,204.00 |
| 708-01 |
right-of-way monument
|
175   |
ea |
140.00 |
24,500.00 |
210.00 |
36,750.00 |
140.00 |
24,500.00 |
100.00 |
17,500.00 |
| 708-02 |
right-of-way monument witness post
|
175   |
ea |
50.00 |
8,750.00 |
160.00 |
28,000.00 |
50.00 |
8,750.00 |
50.00 |
8,750.00 |
| 712-04 |
flexible revetment
|
2,909   |
sq m |
45.00 |
130,905.00 |
78.00 |
226,902.00 |
70.00 |
203,630.00 |
70.00 |
203,630.00 |
| 713-01 |
temporary signs & barricades
|
lump |
lump |
250,000.00 |
250,000.00 |
150,000.00 |
150,000.00 |
150,000.00 |
150,000.00 |
80,000.00 |
80,000.00 |
| 713-02-A |
temporary pavement markings (100 mm width)
|
1,210   |
ln m |
1.00 |
1,210.00 |
1.00 |
1,210.00 |
1.00 |
1,210.00 |
1.30 |
1,573.00 |
| 716-01-A |
mulch (vegetative)
|
58,240.0 |
kg |
1.10 |
64,064.00 |
0.93 |
54,163.20 |
1.75 |
101,920.00 |
1.10 |
64,064.00 |
| 717-01 |
seeding
|
2,670   |
kg |
16.50 |
44,055.00 |
8.00 |
21,360.00 |
16.00 |
42,720.00 |
16.50 |
44,055.00 |
| 718-01 |
fertilizer
|
62,800   |
kg |
0.33 |
20,724.00 |
0.40 |
25,120.00 |
0.65 |
40,820.00 |
0.33 |
20,724.00 |
| 720-01-A |
erosion control system, slope protection (type a)
|
88,808   |
sq m |
1.20 |
106,569.60 |
1.29 |
114,562.32 |
1.40 |
124,331.20 |
1.20 |
106,569.60 |
| 720-01-D |
erosion control system, flexible channel liner (type d)
|
174   |
sq m |
1.20 |
208.80 |
1.29 |
224.46 |
1.40 |
243.60 |
1.20 |
208.80 |
| 722-02 |
project site laboratory (equipped)
|
1   |
ea |
50,000.00 |
50,000.00 |
25,000.00 |
25,000.00 |
42,000.00 |
42,000.00 |
22,000.00 |
22,000.00 |
| 725-01 |
temporary detour roads
|
4,129.5 |
sq m |
80.00 |
330,360.00 |
60.00 |
247,770.00 |
66.00 |
272,547.00 |
70.00 |
289,065.00 |
| 726-01 |
bedding material
|
1,546.1 |
cu m |
100.00 |
154,610.00 |
75.00 |
115,957.50 |
110.00 |
170,071.00 |
72.00 |
111,319.20 |
| 727-01 |
mobilization
|
lump |
lump |
1,750,000.00 |
1,750,000.00 |
2,000,000.00 |
2,000,000.00 |
2,300,000.00 |
2,300,000.00 |
2,600,000.00 |
2,600,000.00 |
| 729-16-C |
object marker assembly (type 3)
|
6   |
ea |
75.00 |
450.00 |
75.00 |
450.00 |
75.00 |
450.00 |
75.00 |
450.00 |
| 731-01 |
nonreflectorized raised pavement markers
|
440   |
ea |
10.00 |
4,400.00 |
10.00 |
4,400.00 |
11.00 |
4,840.00 |
15.50 |
6,820.00 |
| 731-02 |
reflectorized raised pavement markers
|
4,310   |
ea |
5.00 |
21,550.00 |
5.00 |
21,550.00 |
5.50 |
23,705.00 |
5.25 |
22,627.50 |
| 732-01-C |
plastic pavement striping (200 mm width)
|
818   |
ln m |
3.30 |
2,699.40 |
3.30 |
2,699.40 |
3.50 |
2,863.00 |
2.95 |
2,413.10 |
| 732-01-E |
plastic pavement striping (600 mm width)
|
793   |
ln m |
9.90 |
7,850.70 |
10.00 |
7,930.00 |
11.00 |
8,723.00 |
9.10 |
7,216.30 |
| 732-02-A |
plastic pavement striping (solid line)(100 mm width)
|
65.105 |
km |
1,500.00 |
97,657.50 |
1,500.00 |
97,657.50 |
1,600.00 |
104,168.00 |
1,650.00 |
107,423.25 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
20   |
ea |
150.00 |
3,000.00 |
150.00 |
3,000.00 |
165.00 |
3,300.00 |
195.00 |
3,900.00 |
| 732-04-C |
plastic pavement legends & symbols (only)
|
20   |
ea |
150.00 |
3,000.00 |
150.00 |
3,000.00 |
165.00 |
3,300.00 |
235.00 |
4,700.00 |
| 732-05 |
removal of pavement markings
|
11.749 |
km |
3,700.00 |
43,471.30 |
3,700.00 |
43,471.30 |
4,000.00 |
46,996.00 |
3,550.00 |
41,708.95 |
| 735-01 |
mailboxes
|
20   |
ea |
25.00 |
500.00 |
1.00 |
20.00 |
1.00 |
20.00 |
10.00 |
200.00 |
| 735-02 |
mailbox supports (single)
|
20   |
ea |
140.00 |
2,800.00 |
180.00 |
3,600.00 |
180.00 |
3,600.00 |
180.00 |
3,600.00 |
| 740-01 |
construction layout
|
lump |
lump |
500,000.00 |
500,000.00 |
250,000.00 |
250,000.00 |
410,000.00 |
410,000.00 |
250,000.00 |
250,000.00 |
| 740-02 |
utility oversight and coordination
|
lump |
lump |
50,000.00 |
50,000.00 |
25,000.00 |
25,000.00 |
20,000.00 |
20,000.00 |
20,000.00 |
20,000.00 |
| 804-01-B |
precast concrete piles (350 mm)
|
80.0 |
ln m |
175.00 |
14,000.00 |
200.00 |
16,000.00 |
185.00 |
14,800.00 |
180.00 |
14,400.00 |
| 804-01-F |
precast concrete piles (600 mm)
|
1,040.0 |
ln m |
351.00 |
365,040.00 |
300.00 |
312,000.00 |
375.00 |
390,000.00 |
435.00 |
452,400.00 |
| 804-12 |
loading permanent piles
|
1   |
ea |
7,800.00 |
7,800.00 |
10,000.00 |
10,000.00 |
8,000.00 |
8,000.00 |
2,000.00 |
2,000.00 |
| 805-01-B |
class a concrete (box culvert headwalls)
|
67.20 |
cu m |
1,250.00 |
84,000.00 |
1,500.00 |
100,800.00 |
1,650.00 |
110,880.00 |
1,430.00 |
96,096.00 |
| 805-01-F |
class a concrete (bents)
|
149.00 |
cu m |
900.00 |
134,100.00 |
1,000.00 |
149,000.00 |
1,000.00 |
149,000.00 |
1,400.00 |
208,600.00 |
| 805-03 |
class aa concrete
|
428.08 |
cu m |
850.00 |
363,868.00 |
1,100.00 |
470,888.00 |
925.00 |
395,974.00 |
1,100.00 |
470,888.00 |
| 805-08-B |
precast-prestressed concrete girders (type ii)
|
742.50 |
ln m |
300.00 |
222,750.00 |
275.00 |
204,187.50 |
325.00 |
241,312.50 |
300.00 |
222,750.00 |
| 805-11 |
strip seal joints
|
60.00 |
ln m |
390.00 |
23,400.00 |
475.00 |
28,500.00 |
425.00 |
25,500.00 |
380.00 |
22,800.00 |
| 805-12-C |
reinforced concrete box culverts (1800 mm x 900 mm)
|
36.60 |
ln m |
810.00 |
29,646.00 |
1,200.00 |
43,920.00 |
1,400.00 |
51,240.00 |
1,000.00 |
36,600.00 |
| 805-12-F |
reinforced concrete box culverts (1500 mm x 1200 mm)
|
94.80 |
ln m |
727.00 |
68,919.60 |
1,100.00 |
104,280.00 |
1,300.00 |
123,240.00 |
700.00 |
66,360.00 |
| 805-12-G |
reinforced concrete box culverts (1800 mm x 1200 mm)
|
280.90 |
ln m |
925.00 |
259,832.50 |
1,600.00 |
449,440.00 |
1,400.00 |
393,260.00 |
820.00 |
230,338.00 |
| 805-12-H |
reinforced concrete box culverts (2100 mm x 1200 mm)
|
111.00 |
ln m |
1,080.00 |
119,880.00 |
1,800.00 |
199,800.00 |
1,500.00 |
166,500.00 |
925.00 |
102,675.00 |
| 806-01 |
deformed reinforcing steel
|
22,305   |
kg |
2.00 |
44,610.00 |
1.75 |
39,033.75 |
2.25 |
50,186.25 |
2.90 |
64,684.50 |
| 806-02 |
deformed reinforcing steel (epoxy coated)
|
59,586   |
kg |
3.00 |
178,758.00 |
2.25 |
134,068.50 |
3.40 |
202,592.40 |
3.40 |
202,592.40 |
| 807-08 |
structural metalwork
|
lump |
lump |
3,215.00 |
3,215.00 |
35,000.00 |
35,000.00 |
17.00 |
17.00 |
14,000.00 |
14,000.00 |
| 810-01 |
concrete railing (barrier)
|
322.00 |
ln m |
204.00 |
65,688.00 |
300.00 |
96,600.00 |
225.00 |
72,450.00 |
200.00 |
64,400.00 |
| 813-01 |
concrete approach slabs
|
288.00 |
sq m |
215.00 |
61,920.00 |
145.00 |
41,760.00 |
235.00 |
67,680.00 |
240.00 |
69,120.00 |
| S-001 |
rumble strips (ground-in)
|
49.7 |
km |
375.00 |
18,637.50 |
275.00 |
13,667.50 |
325.00 |
16,152.50 |
280.00 |
13,916.00 |
| | SUBTOTAL GENERAL |
|
|
|
14,226,301.74 |
|
16,095,466.68 |
|
17,111,407.95 |
|
18,473,207.20 |
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A |
pavement options
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A1 |
superpave asphaltic concrete pavement
|
|
|
|
|
|
|
|
|
|
|
| 302-02-A-01 |
class ii base course (125 mm thick)(stone or recycled
pccp) |
20,353.8 |
sq m |
14.00 |
284,953.20 |
12.50 |
254,422.50 |
16.35 |
332,784.63 |
0.00 |
0.00 |
| 302-02-C-01 |
class ii base course (200 mm thick)(stone or recycled
pccp) |
11,517.5 |
sq m |
21.50 |
247,626.25 |
20.00 |
230,350.00 |
23.00 |
264,902.50 |
0.00 |
0.00 |
| 302-02-D-01 |
class ii base course (225 mm thick)(stone or recycled
pccp) |
12,428.5 |
sq m |
24.00 |
298,284.00 |
22.00 |
273,427.00 |
28.00 |
347,998.00 |
0.00 |
0.00 |
| 302-02-G-01 |
class ii base course (100 mm thick)(stone or recycled
pccp) |
202,314.2 |
sq m |
11.00 |
2,225,456.20 |
9.50 |
1,921,984.90 |
11.25 |
2,276,034.75 |
0.00 |
0.00 |
| 302-02-H-01 |
class ii base course (40 mm thick)(stone or recycled
pccp) |
375.9 |
sq m |
10.00 |
3,759.00 |
6.00 |
2,255.40 |
18.25 |
6,860.18 |
0.00 |
0.00 |
| 502-01 |
superpave asphaltic concrete
|
56,969.8 |
Mg |
98.00 |
5,583,040.40 |
92.00 |
5,241,221.60 |
88.00 |
5,013,342.40 |
0.00 |
0.00 |
| 502-01-A |
superpave asphaltic concrete drives, turnouts and
miscellaneous |
10,353.7 |
Mg |
135.00 |
1,397,749.50 |
110.00 |
1,138,907.00 |
100.00 |
1,035,370.00 |
0.00 |
0.00 |
| 732-03-A |
plastic pavement striping (broken line)(100 mm width)
|
25.322 |
km |
450.00 |
11,394.90 |
450.00 |
11,394.90 |
500.00 |
12,661.00 |
0.00 |
0.00 |
| | SUBTOTAL ALT A1 |
|
|
|
10,052,263.45 |
|
9,073,963.30 |
|
9,289,953.46 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A2 |
portland cement concrete pavement
|
|
|
|
|
|
|
|
|
|
|
| 302-02-A-01 |
class ii base course (125 mm thick)(stone or recycled
pccp) |
34,767.2 |
sq m |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
17.25 |
599,734.20 |
| 302-02-C-01 |
class ii base course (200 mm thick)(stone or recycled
pccp) |
1,490.7 |
sq m |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
29.00 |
43,230.30 |
| 302-02-D-01 |
class ii base course (225 mm thick)(stone or recycled
pccp) |
20,720.5 |
sq m |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
28.50 |
590,534.25 |
| 302-02-G-01 |
class ii base course (100 mm thick)(stone or recycled
pccp) |
189,935.8 |
sq m |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
11.75 |
2,231,745.65 |
| 302-02-I-01 |
class ii base course (65 mm thick)(stone or recycled
pccp) |
375.9 |
sq m |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
9.00 |
3,383.10 |
| 502-01 |
superpave asphaltic concrete
|
36,926.5 |
Mg |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
115.00 |
4,246,547.50 |
| 502-01-A |
superpave asphaltic concrete drives, turnouts and
miscellaneous |
7,504.4 |
Mg |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
142.00 |
1,065,624.80 |
| 601-01-I |
portland cement concrete pavement (225 mm thick)
|
42,645.7 |
sq m |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
48.00 |
2,046,993.60 |
| 601-02-I |
portland cement concrete pavement (225 mm thick)
(crossovers & turnouts) |
6,063.7 |
sq m |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
75.00 |
454,777.50 |
| 601-04 |
portland cement concrete coring
|
80   |
each |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
100.00 |
8,000.00 |
| 732-03-A |
plastic pavement striping (broken line)(100 mm width)
|
20.048 |
km |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
430.00 |
8,620.64 |
| 732-03-A-01 |
plastic pavement striping (broken line)(100 mm width)
(preformed marking tape (type v) |
5.274 |
km |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
2,600.00 |
13,712.40 |
| | SUBTOTAL ALT A2 |
|
|
|
|
|
|
|
|
|
11,312,903.94 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
24,278,565.19 |
|
25,169,429.98 |
|
26,401,361.41 |
|
29,786,111.14 |
| | NUMBER OF DAYS BID AT $7,500 PER DAY. |
|
|
|
4,875,000.00 |
|
4,500,000.00 |
|
4,875,000.00 |
|
4,875,000.00 |
| | LIFE CYCLE COST |
|
|
|
1,006,700.00 |
|
1,006,700.00 |
|
1,006,700.00 |
|
317,500.00 |
| | TOTAL BID |
|
|
|
30,160,265.19 |
|
30,676,129.98 |
|
32,283,061.41 |
|
34,978,611.14 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - GILCHRIST CONSTRUCTION CO. LLC |
|
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing and grubbing
|
lump |
lump |
2,200,000.00 |
2,200,000.00 |
|
|
|
|
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
lump |
200,000.00 |
200,000.00 |
|
|
|
|
|
|
| 202-02-A-01 |
removal of 2-span timber bridge (sta. 27+128.0)
|
1   |
ea |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| 202-02-A-02 |
removal of 2-span timber bridge (sta. 29+958.6)
|
1   |
ea |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| 202-02-A-03 |
removal of 2-span timber bridge (sta. 33+922.8)
|
1   |
ea |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| 202-02-B-01 |
removal of 2 concrete box culverts (sta. 21+616.477;
2-900 mm x 900 mm) |
1   |
ea |
4,500.00 |
4,500.00 |
|
|
|
|
|
|
| 202-02-B-02 |
removal of concrete box culvert headwall (sta. 20+603)
|
1   |
ea |
2,500.00 |
2,500.00 |
|
|
|
|
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
17,571   |
sq m |
8.00 |
140,568.00 |
|
|
|
|
|
|
| 202-02-D |
removal of concrete walks & drives
|
1,260   |
sq m |
8.00 |
10,080.00 |
|
|
|
|
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
23,250.5 |
sq m |
6.00 |
139,503.00 |
|
|
|
|
|
|
| 202-02-H |
removal of guard rail
|
310   |
ln m |
35.00 |
10,850.00 |
|
|
|
|
|
|
| 202-02-01 |
removal of 10.4 m x 11.6 m wood frame residence (rt.
of sta. 22+133) (contains non-friable asbestos) |
1   |
each |
3,000.00 |
3,000.00 |
|
|
|
|
|
|
| 202-02-02 |
removal of 9.3 m x 12.3 m wood frame residence (lt. of
sta. 22+691) (contains transite asbestos siding) |
1   |
each |
3,000.00 |
3,000.00 |
|
|
|
|
|
|
| 202-02-03 |
removal of 17.8 m x 8.5 m wood frame residence (rt. of
sta. 22+950) (cont. friable & transite asbestos siding) |
1   |
each |
3,000.00 |
3,000.00 |
|
|
|
|
|
|
| 202-02-04 |
removal of 32.8 m x 12.2 m abandoned gas station (lt.
of sta. 23+412) (contains transite asbestos siding) |
1   |
each |
3,000.00 |
3,000.00 |
|
|
|
|
|
|
| 202-02-05 |
removal of 10.5 m x 8.5 m building (lt. of sta. 23+702)
(contains transite asbestos siding) |
1   |
each |
3,000.00 |
3,000.00 |
|
|
|
|
|
|
| 202-02-06 |
removal of 19.9 m x 14.6 m wood frame residence (rt.
of sta. 23+870) (contains non-friable asbestos) |
1   |
each |
3,000.00 |
3,000.00 |
|
|
|
|
|
|
| 202-02-07 |
removal of 8.1 m x 12.6 m building (lt. of sta. 23+930)
(contains non-friable asbestos) |
1   |
each |
3,000.00 |
3,000.00 |
|
|
|
|
|
|
| 202-02-08 |
removal of 8.6 m x 20.3 m wood frame residence with no
slab (lt. of sta. 24+185)(contains non-friable asbestos) |
1   |
each |
3,000.00 |
3,000.00 |
|
|
|
|
|
|
| 202-02-09 |
removal of 5.4 m x 5.7 m wood shed with no slab (lt.
of sta. 24+193) (contains non-friable asbestos) |
1   |
each |
3,000.00 |
3,000.00 |
|
|
|
|
|
|
| 202-02-10 |
removal of 15.4 m x 20.6 m wood frame residence with
no slab (lt. of sta. 27+986)(contains non-friable asbestos) |
1   |
each |
3,000.00 |
3,000.00 |
|
|
|
|
|
|
| 202-02-11 |
removal of 18.3 m x 11.7 m brick residence on slab
(lt. of sta. 31+000) (contains non-friable asbestos) |
1   |
each |
3,000.00 |
3,000.00 |
|
|
|
|
|
|
| 202-07 |
plugging existing water wells
|
18   |
each |
3,000.00 |
54,000.00 |
|
|
|
|
|
|
| 203-01 |
general excavation
|
380,276   |
cu m |
8.00 |
3,042,208.00 |
|
|
|
|
|
|
| 203-03 |
embankment
|
301,936   |
cu m |
17.00 |
5,132,912.00 |
|
|
|
|
|
|
| 203-04-A |
nonplastic embankment (stone)
|
1,923   |
cu m |
200.00 |
384,600.00 |
|
|
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
217   |
ea |
25.00 |
5,425.00 |
|
|
|
|
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
109   |
ea |
170.00 |
18,530.00 |
|
|
|
|
|
|
| 204-05-B |
temporary sediment check dams (stone)
|
106   |
ea |
650.00 |
68,900.00 |
|
|
|
|
|
|
| 204-06 |
temporary silt fencing
|
22,001   |
ln m |
3.50 |
77,003.50 |
|
|
|
|
|
|
| 204-07 |
temporary stone construction entrance
|
5   |
ea |
3,000.00 |
15,000.00 |
|
|
|
|
|
|
| 302-02-B-01 |
class ii base course (150 mm thick)(soil cement)
|
219,466.3 |
sq m |
13.00 |
2,853,061.90 |
|
|
|
|
|
|
| 304-05 |
lime treatiment (type e)
|
1,657.64 |
Mg |
350.00 |
580,174.00 |
|
|
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
420   |
cu m |
180.00 |
75,600.00 |
|
|
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
4,000.0 |
cu m |
75.00 |
300,000.00 |
|
|
|
|
|
|
| 510-01-B |
pavement patching (300 mm thickness)
|
1,354   |
sq m |
250.00 |
338,500.00 |
|
|
|
|
|
|
| 701-01-F |
cross drain pipe (375 mm rcp/pcp)
|
649.1 |
ln m |
200.00 |
129,820.00 |
|
|
|
|
|
|
| 701-01-I |
cross drain pipe (600 mm rcp/pcp)
|
25.5 |
ln m |
260.00 |
6,630.00 |
|
|
|
|
|
|
| 701-01-K |
cross drain pipe (750 mm rcp/pcp)
|
201.7 |
ln m |
300.00 |
60,510.00 |
|
|
|
|
|
|
| 701-01-M |
cross drain pipe (900 mm rcp/pcp)
|
205.1 |
ln m |
320.00 |
65,632.00 |
|
|
|
|
|
|
| 701-01-N |
cross drain pipe (1050 mm rcp/pcp)
|
130.5 |
ln m |
450.00 |
58,725.00 |
|
|
|
|
|
|
| 701-01-O |
cross drain pipe (1200 mm rcp/pcp)
|
143.4 |
ln m |
460.00 |
65,964.00 |
|
|
|
|
|
|
| 701-02-F |
cross drain pipe arch (900 mm equiv. rcpa)
|
30.0 |
ln m |
600.00 |
18,000.00 |
|
|
|
|
|
|
| 701-02-G |
cross drain pipe arch (1050 mm equiv. rcpa)
|
806.5 |
ln m |
500.00 |
403,250.00 |
|
|
|
|
|
|
| 701-02-H |
cross drain pipe arch (1200 mm equiv. rcpa)
|
229.0 |
ln m |
800.00 |
183,200.00 |
|
|
|
|
|
|
| 701-02-I |
cross drain pipe arch (1350 mm equiv. rcpa)
|
121.0 |
ln m |
810.00 |
98,010.00 |
|
|
|
|
|
|
| 701-05-G |
side drain pipe (450 mm)
|
329.5 |
ln m |
200.00 |
65,900.00 |
|
|
|
|
|
|
| 701-05-G-01 |
side drain pipe (450 mm)(erosion)
|
35.0 |
ln m |
300.00 |
10,500.00 |
|
|
|
|
|
|
| 701-05-I |
side drain pipe (600 mm)
|
345.0 |
ln m |
250.00 |
86,250.00 |
|
|
|
|
|
|
| 701-05-K |
side drain pipe (750 mm)
|
75.5 |
ln m |
320.00 |
24,160.00 |
|
|
|
|
|
|
| 701-05-M |
side drain pipe (900 mm)
|
62.5 |
ln m |
450.00 |
28,125.00 |
|
|
|
|
|
|
| 701-05-N |
side drain pipe (1050 mm)
|
42.5 |
ln m |
500.00 |
21,250.00 |
|
|
|
|
|
|
| 701-05-P |
side drain pipe (1350 mm)
|
39.0 |
ln m |
900.00 |
35,100.00 |
|
|
|
|
|
|
| 701-15 |
concrete collars
|
4   |
ea |
1,000.00 |
4,000.00 |
|
|
|
|
|
|
| 702-03-A |
catch basins (cb-01m)
|
32   |
ea |
3,000.00 |
96,000.00 |
|
|
|
|
|
|
| 702-03-B |
catch basins (cb-02m)
|
6   |
ea |
4,000.00 |
24,000.00 |
|
|
|
|
|
|
| 702-07-A |
cross drain safety end (type 1)
|
5   |
each |
4,500.00 |
22,500.00 |
|
|
|
|
|
|
| 702-07-B |
cross drain safety end (type 2)
|
1   |
each |
4,500.00 |
4,500.00 |
|
|
|
|
|
|
| 702-08-A |
side drain safety end (type 1)
|
15   |
each |
4,000.00 |
60,000.00 |
|
|
|
|
|
|
| 704-01-A |
guard rail (single thrie beam)(950 mm post spacing)
|
25.25 |
ln m |
400.00 |
10,100.00 |
|
|
|
|
|
|
| 704-03 |
blocked out guard rail
|
218.82 |
ln m |
75.00 |
16,411.50 |
|
|
|
|
|
|
| 704-06-A |
guard rail anchor sections (trailing end)(single thrie
beam) |
3.82 |
ln m |
350.00 |
1,337.00 |
|
|
|
|
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
15.24 |
ln m |
200.00 |
3,048.00 |
|
|
|
|
|
|
| 704-11-A |
guard rail end treatment (flared)
|
2   |
ea |
2,800.00 |
5,600.00 |
|
|
|
|
|
|
| 704-11-B |
guard rail end treatment (tangent)
|
2   |
ea |
3,500.00 |
7,000.00 |
|
|
|
|
|
|
| 705-01 |
barbed wire fence
|
2,053   |
ln m |
20.00 |
41,060.00 |
|
|
|
|
|
|
| 705-02 |
combination mesh & barbed wire fence
|
3,540   |
ln m |
21.00 |
74,340.00 |
|
|
|
|
|
|
| 705-04 |
single swinging driveway gates
|
15   |
ea |
700.00 |
10,500.00 |
|
|
|
|
|
|
| 705-05 |
double swinging driveway gates
|
2   |
dbgt |
1,000.00 |
2,000.00 |
|
|
|
|
|
|
| 705-06-A |
chain link fence (1200 mm height)
|
350   |
ln m |
25.00 |
8,750.00 |
|
|
|
|
|
|
| 706-02-C |
concrete drive (150 mm thick)
|
1,164.4 |
sq m |
75.00 |
87,330.00 |
|
|
|
|
|
|
| 706-03-C |
incidental concrete paving (150 mm thickness)
|
456.4 |
sq m |
100.00 |
45,640.00 |
|
|
|
|
|
|
| 708-01 |
right-of-way monument
|
175   |
ea |
350.00 |
61,250.00 |
|
|
|
|
|
|
| 708-02 |
right-of-way monument witness post
|
175   |
ea |
350.00 |
61,250.00 |
|
|
|
|
|
|
| 712-04 |
flexible revetment
|
2,909   |
sq m |
65.00 |
189,085.00 |
|
|
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
lump |
1,000,000.00 |
1,000,000.00 |
|
|
|
|
|
|
| 713-02-A |
temporary pavement markings (100 mm width)
|
1,210   |
ln m |
1.80 |
2,178.00 |
|
|
|
|
|
|
| 716-01-A |
mulch (vegetative)
|
58,240.0 |
kg |
2.20 |
128,128.00 |
|
|
|
|
|
|
| 717-01 |
seeding
|
2,670   |
kg |
20.00 |
53,400.00 |
|
|
|
|
|
|
| 718-01 |
fertilizer
|
62,800   |
kg |
0.75 |
47,100.00 |
|
|
|
|
|
|
| 720-01-A |
erosion control system, slope protection (type a)
|
88,808   |
sq m |
1.50 |
133,212.00 |
|
|
|
|
|
|
| 720-01-D |
erosion control system, flexible channel liner (type d)
|
174   |
sq m |
1.50 |
261.00 |
|
|
|
|
|
|
| 722-02 |
project site laboratory (equipped)
|
1   |
ea |
100,000.00 |
100,000.00 |
|
|
|
|
|
|
| 725-01 |
temporary detour roads
|
4,129.5 |
sq m |
70.00 |
289,065.00 |
|
|
|
|
|
|
| 726-01 |
bedding material
|
1,546.1 |
cu m |
150.00 |
231,915.00 |
|
|
|
|
|
|
| 727-01 |
mobilization
|
lump |
lump |
3,900,000.00 |
3,900,000.00 |
|
|
|
|
|
|
| 729-16-C |
object marker assembly (type 3)
|
6   |
ea |
90.00 |
540.00 |
|
|
|
|
|
|
| 731-01 |
nonreflectorized raised pavement markers
|
440   |
ea |
20.00 |
8,800.00 |
|
|
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
4,310   |
ea |
6.00 |
25,860.00 |
|
|
|
|
|
|
| 732-01-C |
plastic pavement striping (200 mm width)
|
818   |
ln m |
4.00 |
3,272.00 |
|
|
|
|
|
|
| 732-01-E |
plastic pavement striping (600 mm width)
|
793   |
ln m |
12.00 |
9,516.00 |
|
|
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line)(100 mm width)
|
65.105 |
km |
2,100.00 |
136,720.50 |
|
|
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
20   |
ea |
250.00 |
5,000.00 |
|
|
|
|
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
20   |
ea |
330.00 |
6,600.00 |
|
|
|
|
|
|
| 732-05 |
removal of pavement markings
|
11.749 |
km |
4,500.00 |
52,870.50 |
|
|
|
|
|
|
| 735-01 |
mailboxes
|
20   |
ea |
5.00 |
100.00 |
|
|
|
|
|
|
| 735-02 |
mailbox supports (single)
|
20   |
ea |
200.00 |
4,000.00 |
|
|
|
|
|
|
| 740-01 |
construction layout
|
lump |
lump |
800,000.00 |
800,000.00 |
|
|
|
|
|
|
| 740-02 |
utility oversight and coordination
|
lump |
lump |
20,000.00 |
20,000.00 |
|
|
|
|
|
|
| 804-01-B |
precast concrete piles (350 mm)
|
80.0 |
ln m |
180.00 |
14,400.00 |
|
|
|
|
|
|
| 804-01-F |
precast concrete piles (600 mm)
|
1,040.0 |
ln m |
280.00 |
291,200.00 |
|
|
|
|
|
|
| 804-12 |
loading permanent piles
|
1   |
ea |
10,000.00 |
10,000.00 |
|
|
|
|
|
|
| 805-01-B |
class a concrete (box culvert headwalls)
|
67.20 |
cu m |
1,600.00 |
107,520.00 |
|
|
|
|
|
|
| 805-01-F |
class a concrete (bents)
|
149.00 |
cu m |
2,000.00 |
298,000.00 |
|
|
|
|
|
|
| 805-03 |
class aa concrete
|
428.08 |
cu m |
2,000.00 |
856,160.00 |
|
|
|
|
|
|
| 805-08-B |
precast-prestressed concrete girders (type ii)
|
742.50 |
ln m |
920.00 |
683,100.00 |
|
|
|
|
|
|
| 805-11 |
strip seal joints
|
60.00 |
ln m |
500.00 |
30,000.00 |
|
|
|
|
|
|
| 805-12-C |
reinforced concrete box culverts (1800 mm x 900 mm)
|
36.60 |
ln m |
1,700.00 |
62,220.00 |
|
|
|
|
|
|
| 805-12-F |
reinforced concrete box culverts (1500 mm x 1200 mm)
|
94.80 |
ln m |
1,400.00 |
132,720.00 |
|
|
|
|
|
|
| 805-12-G |
reinforced concrete box culverts (1800 mm x 1200 mm)
|
280.90 |
ln m |
1,450.00 |
407,305.00 |
|
|
|
|
|
|
| 805-12-H |
reinforced concrete box culverts (2100 mm x 1200 mm)
|
111.00 |
ln m |
1,900.00 |
210,900.00 |
|
|
|
|
|
|
| 806-01 |
deformed reinforcing steel
|
22,305   |
kg |
2.50 |
55,762.50 |
|
|
|
|
|
|
| 806-02 |
deformed reinforcing steel (epoxy coated)
|
59,586   |
kg |
3.00 |
178,758.00 |
|
|
|
|
|
|
| 807-08 |
structural metalwork
|
lump |
lump |
25,000.00 |
25,000.00 |
|
|
|
|
|
|
| 810-01 |
concrete railing (barrier)
|
322.00 |
ln m |
250.00 |
80,500.00 |
|
|
|
|
|
|
| 813-01 |
concrete approach slabs
|
288.00 |
sq m |
200.00 |
57,600.00 |
|
|
|
|
|
|
| S-001 |
rumble strips (ground-in)
|
49.7 |
km |
700.00 |
34,790.00 |
|
|
|
|
|
|
| | SUBTOTAL GENERAL |
|
|
|
28,408,116.40 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A |
pavement options
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A1 |
superpave asphaltic concrete pavement
|
|
|
|
|
|
|
|
|
|
|
| 302-02-A-01 |
class ii base course (125 mm thick)(stone or recycled
pccp) |
20,353.8 |
sq m |
20.00 |
407,076.00 |
|
|
|
|
|
|
| 302-02-C-01 |
class ii base course (200 mm thick)(stone or recycled
pccp) |
11,517.5 |
sq m |
25.00 |
287,937.50 |
|
|
|
|
|
|
| 302-02-D-01 |
class ii base course (225 mm thick)(stone or recycled
pccp) |
12,428.5 |
sq m |
35.00 |
434,997.50 |
|
|
|
|
|
|
| 302-02-G-01 |
class ii base course (100 mm thick)(stone or recycled
pccp) |
202,314.2 |
sq m |
15.00 |
3,034,713.00 |
|
|
|
|
|
|
| 302-02-H-01 |
class ii base course (40 mm thick)(stone or recycled
pccp) |
375.9 |
sq m |
14.00 |
5,262.60 |
|
|
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
56,969.8 |
Mg |
99.00 |
5,640,010.20 |
|
|
|
|
|
|
| 502-01-A |
superpave asphaltic concrete drives, turnouts and
miscellaneous |
10,353.7 |
Mg |
150.00 |
1,553,055.00 |
|
|
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(100 mm width)
|
25.322 |
km |
500.00 |
12,661.00 |
|
|
|
|
|
|
| | SUBTOTAL ALT A1 |
|
|
|
11,375,712.80 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A2 |
portland cement concrete pavement
|
|
|
|
|
|
|
|
|
|
|
| 302-02-A-01 |
class ii base course (125 mm thick)(stone or recycled
pccp) |
34,767.2 |
sq m |
0.00 |
0.00 |
|
|
|
|
|
|
| 302-02-C-01 |
class ii base course (200 mm thick)(stone or recycled
pccp) |
1,490.7 |
sq m |
0.00 |
0.00 |
|
|
|
|
|
|
| 302-02-D-01 |
class ii base course (225 mm thick)(stone or recycled
pccp) |
20,720.5 |
sq m |
0.00 |
0.00 |
|
|
|
|
|
|
| 302-02-G-01 |
class ii base course (100 mm thick)(stone or recycled
pccp) |
189,935.8 |
sq m |
0.00 |
0.00 |
|
|
|
|
|
|
| 302-02-I-01 |
class ii base course (65 mm thick)(stone or recycled
pccp) |
375.9 |
sq m |
0.00 |
0.00 |
|
|
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
36,926.5 |
Mg |
0.00 |
0.00 |
|
|
|
|
|
|
| 502-01-A |
superpave asphaltic concrete drives, turnouts and
miscellaneous |
7,504.4 |
Mg |
0.00 |
0.00 |
|
|
|
|
|
|
| 601-01-I |
portland cement concrete pavement (225 mm thick)
|
42,645.7 |
sq m |
0.00 |
0.00 |
|
|
|
|
|
|
| 601-02-I |
portland cement concrete pavement (225 mm thick)
(crossovers & turnouts) |
6,063.7 |
sq m |
0.00 |
0.00 |
|
|
|
|
|
|
| 601-04 |
portland cement concrete coring
|
80   |
each |
0.00 |
0.00 |
|
|
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(100 mm width)
|
20.048 |
km |
0.00 |
0.00 |
|
|
|
|
|
|
| 732-03-A-01 |
plastic pavement striping (broken line)(100 mm width)
(preformed marking tape (type v) |
5.274 |
km |
0.00 |
0.00 |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
39,783,829.20 |
|
|
|
|
|
|
| | NUMBER OF DAYS BID AT $7,500 PER DAY. |
|
|
|
4,875,000.00 |
|
|
|
|
|
|
| | LIFE CYCLE COST |
|
|
|
1,006,700.00 |
|
|
|
|
|
|
| | TOTAL BID |
|
|
|
45,665,529.20 |
|
|
|
|
|
|
|