Each project in the letting is listed with descriptive information. Click on a project to obtain a tabulation of item bids for each bidder. It includes the unit bid for each item as well as the total item bid. Also shown are the bidder totals and ranking for each project.
| Lead Project: 005-07-0068 | |
| Parish: LAFOURCHE | |
| Routes: US 90 | |
| Description: MAINTENANCE MOWING (MO) ROUTE US 90 | |
| Type Const: maintenance mowing and litter collection st. charles /lafourche p/l | |
| Low Bidder: ELLIOTT GROUNDS MAINTENANCE LLC | |
| Amount: $109,867.80 | |
| Estimated Construction Cost: $95,410.00 | |
| Federal Number: | |
| REBID | |
| Lead Project: 014-01-0009 | |
| Parish: CALCASIEU | |
| Routes: US 165, I-10 | |
| Description: US 165: US 90 - JEFFERSON DAVIS PARISH LINE (CM) | |
| Type Const: patching, cold planing, overlay, pavement markings, and rela ted work | |
| Low Bidder: R. E. HEIDT CONSTRUCTION CO., INC. | |
| Amount: $690,249.59 | |
| Estimated Construction Cost: $594,314.12 | |
| Federal Number: STP-1003(516) | |
| DBE GOAL FED | |
| Lead Project: 450-17-0028 | |
| Parish: ORLEANS, ST TAMMANY | |
| Routes: I-10 | |
| Description: I-10 BRIDGE OVER LAKE PONTCHARTRAIN | |
| Type Const:
construction layout, signs, treated timber piles,alt a-1 pre cast prestressed concrete girders(bt-78)alt a-2 segmentalbox c-i-p substructure alt a3 segmental box precast substructure | |
| Low Bidder: TRAYLOR/KIEWITSOUTH/MASSMAN JT VENT | |
| Amount: $166,698,939.00 | |
| Estimated Construction Cost: $174,512,285.30 | |
| Federal Number: ER-ERP1(019) | |
| REBID | |
| Lead Project: 450-34-0087 | |
| Parish: ORLEANS | |
| Routes: I-610, I-10 | |
| Description: MAINTENANCE MOWING (MO) | |
| Type Const: maintenance mowing and litter and trash collection in orleans parish | |
| Low Bidder: LEROY DANOS MAINT. SERVICES INC. | |
| Amount: $288,476.00 | |
| Estimated Construction Cost: $228,950.00 | |
| Federal Number: | |
| REBID | |
| Lead Project: 451-06-0130 | |
| Parish: OUACHITA | |
| Routes: | |
| Description: TWIN CITY GATEWAY PROJECT | |
| Type Const: landscaping, and related work. | |
| Low Bidder: QUALITY DESIGN & CONSTRUCTION, INC. | |
| Amount: $373,229.20 | |
| Estimated Construction Cost: $332,574.00 | |
| Federal Number: ENH-3704(509) | |
| DBE GOAL FED | |
| Lead Project: 454-01-0071 | |
| Parish: E BATON ROUGE | |
| Routes: I-12 | |
| Description: I-12 AT SHERWOOD FOREST BLVD. INTERSECTION IMPROVEMENTS | |
| Type Const:
grading, class ii bc, lime trmt, superpave acp, cold planing, high early strength pccp, drain struct, signing, traffic signals, video detection system, and related work | |
| Low Bidder: HARD ROCK CONSTRUCTION CO. | |
| Amount: $2,930,217.70 | |
| Estimated Construction Cost: $1,852,940.81 | |
| Federal Number: CMAQ-1702(503) | |
| DBE GOAL FED | |
| Lead Project: 713-09-0006 | |
| Parish: CADDO | |
| Routes: | |
| Description: CYPRESS BAYOU, CROSS BAYOU AND GLENLEAF DRIVE BRIDGES | |
| Type Const:
grading, class ii bc, drain struct, superpave acp, concrete slab span bridges and related work. | |
| Low Bidder: C W & W CONTRACTORS, INC. | |
| Amount: $979,636.20 | |
| Estimated Construction Cost: $760,996.85 | |
| Federal Number: BRO-002S(660) | |
| READV | |
| Lead Project: 713-53-0120 | |
| Parish: TANGIPAHOA | |
| Routes: | |
| Description: QUICK BOULEVARD BRIDGE REHABILITATION | |
| Type Const: precast concrete slab span bridge, and related work | |
| Low Bidder: CHAMBERS CONSTRUCTION CO., INC. | |
| Amount: $204,920.00 | |
| Estimated Construction Cost: $146,062.50 | |
| Federal Number: BDP-5305(509) | |
| REBID | |
| Lead Project: 737-98-0030 | |
| Parish: DISTRICT 08 | |
| Routes: | |
| Description: REPAIR, MAINT, & CONST OF GUARDRAIL & BRIDGE RAIL (DIST 08) | |
| Type Const: repair and/or replacement of damaged guardrail and relatated work | |
| Low Bidder: UNITED RENTALS HWY TECHNOLOGIES INC | |
| Amount: $500,935.00 | |
| Estimated Construction Cost: $378,345.00 | |
| Federal Number: | |
| READV | |
| DBE GOAL FED | |
| Lead Project: 742-36-0116 | |
| Parish: ORLEANS | |
| Routes: | |
| Description: FLEUR DE LIS DRIVE IMPROVEMENTS - PHASE I | |
| Type Const:
drainage structures,class ii base course,pvmt patching, portland cement concrete pavement,sanitary sewer work, water service, and related work. | |
| Low Bidder: BARRIERE CONSTRUCTION CO., LLC. | |
| Amount: $3,441,969.20 | |
| Estimated Construction Cost: $4,223,105.42 | |
| Federal Number: STP-3602(512) | |