| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC. |
- 2 - HARD ROCK CONSTRUCTION CO. |
- 3 - BOH BROS. CONSTRUCTION CO., LLC. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
100,000.00 |
100,000.00 |
100,000.00 |
100,000.00 |
175,000.00 |
175,000.00 |
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
1,017   |
SQYD |
10.00 |
10,170.00 |
12.00 |
12,204.00 |
10.00 |
10,170.00 |
|
|
| 202-02-D |
removal of concrete walks & drives
|
1,430   |
SQYD |
12.00 |
17,160.00 |
12.00 |
17,160.00 |
8.00 |
11,440.00 |
|
|
| 202-02-E |
removal of concrete curbs
|
3,260.6 |
LNFT |
4.00 |
13,042.40 |
0.00 |
0.00 |
2.00 |
6,521.20 |
|
|
| 202-02-I |
removal of asphalt pavement (10" thick)
|
3,670.9 |
SQYD |
10.00 |
36,709.00 |
12.00 |
44,050.80 |
3.00 |
11,012.70 |
|
|
| 202-02-J |
removal of brick walks
|
5.8 |
SQYD |
12.00 |
69.60 |
12.00 |
69.60 |
50.00 |
290.00 |
|
|
| 202-02-K |
removal of asphalt overlayed pcc pavement (2" asp. -
8" pcc) |
3,206.3 |
SQYD |
10.00 |
32,063.00 |
12.00 |
38,475.60 |
10.00 |
32,063.00 |
|
|
| 202-02-L |
removal of existing manholes
|
26   |
EACH |
550.00 |
14,300.00 |
500.00 |
13,000.00 |
400.00 |
10,400.00 |
|
|
| 203-06 |
excavation & embankment
|
lump |
LUMP |
100,000.00 |
100,000.00 |
200,000.00 |
200,000.00 |
65,000.00 |
65,000.00 |
|
|
| 302-02-E |
class ii base course (8" thick)
|
10,196.2 |
SQYD |
18.00 |
183,531.60 |
15.00 |
152,943.00 |
18.00 |
183,531.60 |
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
500.0 |
CUYD |
60.00 |
30,000.00 |
1.00 |
500.00 |
30.00 |
15,000.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
49.1 |
TON |
250.00 |
12,275.00 |
150.00 |
7,365.00 |
300.00 |
14,730.00 |
|
|
| 601-01-I |
portland cement concrete pavement (9" thick)
|
9,440.0 |
SQYD |
54.00 |
509,760.00 |
60.00 |
566,400.00 |
60.00 |
566,400.00 |
|
|
| 701-03-B |
storm drain pipe (6" pvc)
|
80   |
LNFT |
21.00 |
1,680.00 |
15.00 |
1,200.00 |
40.00 |
3,200.00 |
|
|
| 701-03-C |
storm drain pipe (8" pvc)
|
42   |
LNFT |
23.00 |
966.00 |
25.00 |
1,050.00 |
45.00 |
1,890.00 |
|
|
| 701-03-E |
storm drain pipe (12"rcp)
|
20   |
LNFT |
78.00 |
1,560.00 |
155.00 |
3,100.00 |
90.00 |
1,800.00 |
|
|
| 701-03-F |
storm drain pipe (15" rcp)
|
1,276   |
LNFT |
75.00 |
95,700.00 |
73.00 |
93,148.00 |
100.00 |
127,600.00 |
|
|
| 701-03-G |
storm drain pipe (18" rcp)
|
50   |
LNFT |
115.00 |
5,750.00 |
127.00 |
6,350.00 |
105.00 |
5,250.00 |
|
|
| 701-03-G-01 |
storm drain pipe (18")- class iv rcp
|
43   |
LNFT |
90.00 |
3,870.00 |
101.00 |
4,343.00 |
110.00 |
4,730.00 |
|
|
| 701-03-I |
storm drain pipe (24" rcp)
|
183   |
LNFT |
148.00 |
27,084.00 |
141.00 |
25,803.00 |
120.00 |
21,960.00 |
|
|
| 701-03-I-01 |
storm drain pipe (24")- class iv rcp
|
54   |
LNFT |
140.00 |
7,560.00 |
107.00 |
5,778.00 |
130.00 |
7,020.00 |
|
|
| 701-03-K |
storm drain pipe (30" rcp)
|
297   |
LNFT |
210.00 |
62,370.00 |
139.00 |
41,283.00 |
165.00 |
49,005.00 |
|
|
| 701-03-N |
storm drain pipe (42" rcp)
|
182   |
LNFT |
280.00 |
50,960.00 |
191.00 |
34,762.00 |
200.00 |
36,400.00 |
|
|
| 702-03-A |
catch basins (cb-01)
|
10   |
EACH |
2,500.00 |
25,000.00 |
1,850.00 |
18,500.00 |
4,600.00 |
46,000.00 |
|
|
| 702-04-A |
adjusting manholes
|
1   |
EACH |
350.00 |
350.00 |
1,000.00 |
1,000.00 |
750.00 |
750.00 |
|
|
| 706-01-A |
concrete walk (4" thick)
|
1,061.9 |
SQYD |
48.00 |
50,971.20 |
70.00 |
74,333.00 |
48.00 |
50,971.20 |
|
|
| 706-02-C |
concrete drive (6" thick)
|
300.6 |
SQYD |
64.00 |
19,238.40 |
75.00 |
22,545.00 |
55.00 |
16,533.00 |
|
|
| 707-01 |
concrete curb
|
5,633.8 |
LNFT |
10.00 |
56,338.00 |
7.00 |
39,436.60 |
6.00 |
33,802.80 |
|
|
| 710-01 |
flowable fill
|
64   |
CUYD |
100.00 |
6,400.00 |
200.00 |
12,800.00 |
170.00 |
10,880.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
61,000.00 |
61,000.00 |
100,000.00 |
100,000.00 |
40,000.00 |
40,000.00 |
|
|
| 713-03-A |
temporary pavement markings (4" width)
|
2,400   |
LNFT |
1.00 |
2,400.00 |
1.00 |
2,400.00 |
1.00 |
2,400.00 |
|
|
| 714-01 |
slab sodding
|
5,334   |
SQYD |
6.50 |
34,671.00 |
6.00 |
32,004.00 |
4.00 |
21,336.00 |
|
|
| 715-01 |
topsoil
|
889   |
CUYD |
24.00 |
21,336.00 |
10.00 |
8,890.00 |
20.00 |
17,780.00 |
|
|
| 717-01 |
seeding
|
600   |
LB |
9.00 |
5,400.00 |
8.00 |
4,800.00 |
6.00 |
3,600.00 |
|
|
| 718-01 |
fertilizer
|
1,200   |
LB |
1.10 |
1,320.00 |
1.00 |
1,200.00 |
0.50 |
600.00 |
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
32,000.00 |
32,000.00 |
50,000.00 |
50,000.00 |
8,000.00 |
8,000.00 |
|
|
| 723-01 |
granular material (net section)
|
3,399   |
CUYD |
22.00 |
74,778.00 |
30.00 |
101,970.00 |
25.00 |
84,975.00 |
|
|
| 724-01 |
pavement patching
|
1,700   |
SQYD |
16.00 |
27,200.00 |
0.00 |
0.00 |
15.00 |
25,500.00 |
|
|
| 725-02 |
temporary detour roads
|
450.0 |
SQYD |
62.00 |
27,900.00 |
100.00 |
45,000.00 |
150.00 |
67,500.00 |
|
|
| 726-01 |
bedding material
|
9,055.2 |
CUYD |
10.00 |
90,552.00 |
0.00 |
0.00 |
0.10 |
905.52 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
100,000.00 |
100,000.00 |
370,000.00 |
370,000.00 |
390,000.00 |
390,000.00 |
|
|
| 729-01 |
sign (type a)
|
183.8 |
SQFT |
31.00 |
5,697.80 |
27.00 |
4,962.60 |
30.00 |
5,514.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
13   |
EACH |
6.50 |
84.50 |
6.00 |
78.00 |
7.00 |
91.00 |
|
|
| 732-01-B |
plastic pavement striping (6" width)
|
415   |
LNFT |
0.70 |
290.50 |
1.00 |
415.00 |
0.65 |
269.75 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
76   |
LNFT |
0.95 |
72.20 |
1.00 |
76.00 |
0.90 |
68.40 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
148   |
LNFT |
3.00 |
444.00 |
3.00 |
444.00 |
2.75 |
407.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
1.060 |
MILE |
2,600.00 |
2,756.00 |
2,300.00 |
2,438.00 |
2,400.00 |
2,544.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
0.500 |
MILE |
1,100.00 |
550.00 |
1,000.00 |
500.00 |
1,000.00 |
500.00 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
1   |
EACH |
170.00 |
170.00 |
155.00 |
155.00 |
160.00 |
160.00 |
|
|
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
1   |
EACH |
235.00 |
235.00 |
210.00 |
210.00 |
220.00 |
220.00 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
1   |
EACH |
180.00 |
180.00 |
165.00 |
165.00 |
175.00 |
175.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
100,000.00 |
100,000.00 |
100,000.00 |
100,000.00 |
75,000.00 |
75,000.00 |
|
|
| 744-01 |
traffic control management
|
lump |
LUMP |
45,000.00 |
45,000.00 |
50,000.00 |
50,000.00 |
5,000.00 |
5,000.00 |
|
|
| S-001 |
suction manhole removed and reconstructed including
12" diameter ductile iron pipe extension to new manhole |
21   |
VTFH |
2,500.00 |
52,500.00 |
5,000.00 |
105,000.00 |
10,000.00 |
210,000.00 |
|
|
| S-002 |
utility exploration
|
10   |
EACH |
1,200.00 |
12,000.00 |
700.00 |
7,000.00 |
700.00 |
7,000.00 |
|
|
| S-003 |
removal of existing sewer force main
|
1,232   |
LNFT |
28.00 |
34,496.00 |
30.00 |
36,960.00 |
16.00 |
19,712.00 |
|
|
| S-004 |
abandon catch basins or manholes (in place) including
backfilling w/ compacted river sand |
4   |
EACH |
425.00 |
1,700.00 |
500.00 |
2,000.00 |
400.00 |
1,600.00 |
|
|
| S-005 |
water main (8")
|
1,398   |
LNFT |
63.00 |
88,074.00 |
51.00 |
71,298.00 |
65.00 |
90,870.00 |
|
|
| S-006 |
water main (12")
|
1,207   |
LNFT |
82.00 |
98,974.00 |
58.00 |
70,006.00 |
85.00 |
102,595.00 |
|
|
| S-007 |
replace 3/4" water house connection (from main to
meter) + (from meter to property line) |
6   |
EACH |
450.00 |
2,700.00 |
600.00 |
3,600.00 |
900.00 |
5,400.00 |
|
|
| S-008 |
replace 1" water house connection (from main to meter)
+ (from meter to property line) |
18   |
EACH |
475.00 |
8,550.00 |
700.00 |
12,600.00 |
950.00 |
17,100.00 |
|
|
| S-009 |
remove & replace existing fire hydrants
|
8   |
EACH |
3,300.00 |
26,400.00 |
3,000.00 |
24,000.00 |
2,000.00 |
16,000.00 |
|
|
| S-010 |
adjust water valve box
|
5   |
EACH |
250.00 |
1,250.00 |
150.00 |
750.00 |
400.00 |
2,000.00 |
|
|
| S-011 |
remove mud and debris from inside of water meter box
(3/4") |
11   |
EACH |
50.00 |
550.00 |
50.00 |
550.00 |
200.00 |
2,200.00 |
|
|
| S-012 |
adjust complete water meter box to grade
|
6   |
EACH |
70.00 |
420.00 |
200.00 |
1,200.00 |
750.00 |
4,500.00 |
|
|
| S-013 |
replace broken water meter box (1")
|
5   |
EACH |
700.00 |
3,500.00 |
500.00 |
2,500.00 |
1,000.00 |
5,000.00 |
|
|
| S-014 |
water valves (8") with water valve manhole
|
7   |
EACH |
7,600.00 |
53,200.00 |
7,000.00 |
49,000.00 |
8,500.00 |
59,500.00 |
|
|
| S-015 |
water valves (12") with water valve manhole
|
3   |
EACH |
11,000.00 |
33,000.00 |
10,000.00 |
30,000.00 |
12,000.00 |
36,000.00 |
|
|
| S-016 |
sanitary sewer pipe (8") (0'-6.0')
|
130   |
LNFT |
70.00 |
9,100.00 |
80.00 |
10,400.00 |
95.00 |
12,350.00 |
|
|
| S-017 |
sanitary sewer pipe (8") (6.1' - 8.0')
|
1,339   |
LNFT |
80.00 |
107,120.00 |
96.00 |
128,544.00 |
140.00 |
187,460.00 |
|
|
| S-018 |
sanitary sewer pipe (8") (8.1' - 10.0')
|
954   |
LNFT |
120.00 |
114,480.00 |
118.00 |
112,572.00 |
190.00 |
181,260.00 |
|
|
| S-019 |
sanitary sewer manhole (0' - 6.0') (s&wb dwg. no.
6178-b6) |
1   |
EACH |
3,300.00 |
3,300.00 |
3,000.00 |
3,000.00 |
4,100.00 |
4,100.00 |
|
|
| S-020 |
sanitary sewer manhole (6.1' - 8.0') (s&wb dwg. no.
6178-b6) |
2   |
EACH |
3,700.00 |
7,400.00 |
3,500.00 |
7,000.00 |
4,500.00 |
9,000.00 |
|
|
| S-021 |
sanitary sewer manhole (8.1' - 10.0') (s&wb dwg. no.
6178-b6) |
3   |
EACH |
4,600.00 |
13,800.00 |
4,000.00 |
12,000.00 |
5,600.00 |
16,800.00 |
|
|
| S-022 |
sanitary sewer manhole (10.0' +) (s&wb dwg. no.
6178-b6) |
1   |
EACH |
4,700.00 |
4,700.00 |
6,000.00 |
6,000.00 |
8,000.00 |
8,000.00 |
|
|
| S-023 |
new sewer house connection main to back of curb
|
1   |
EACH |
1,500.00 |
1,500.00 |
1,000.00 |
1,000.00 |
1,000.00 |
1,000.00 |
|
|
| S-024 |
replace sewer house connection main to property line
|
22   |
EACH |
1,700.00 |
37,400.00 |
1,000.00 |
22,000.00 |
1,200.00 |
26,400.00 |
|
|
| S-025 |
new sewer force main (20")
|
1,247   |
LNFT |
150.00 |
187,050.00 |
200.00 |
249,400.00 |
155.00 |
193,285.00 |
|
|
| S-026 |
tie into existing sewer force main at service road
|
lump |
LUMP |
15,000.00 |
15,000.00 |
28,000.00 |
28,000.00 |
8,000.00 |
8,000.00 |
|
|
| S-027 |
tie into existing sewer force main at veterans
memorial hwy. |
lump |
LUMP |
16,000.00 |
16,000.00 |
28,000.00 |
28,000.00 |
10,000.00 |
10,000.00 |
|
|
| S-028 |
drain house connections (6") from new drain line to
back of curb |
1,055   |
LNFT |
10.00 |
10,550.00 |
9.00 |
9,495.00 |
20.00 |
21,100.00 |
|
|
| S-029 |
drain house connections beyond back of curb (6")
|
150   |
LNFT |
10.00 |
1,500.00 |
21.00 |
3,150.00 |
20.00 |
3,000.00 |
|
|
| S-030 |
collection line to c.b.'s for drain house connections
(6") |
150   |
LNFT |
10.00 |
1,500.00 |
10.00 |
1,500.00 |
20.00 |
3,000.00 |
|
|
| S-031 |
manholes (s&wb of new orleans) (dwg. d-870) type 1
|
7   |
EACH |
3,200.00 |
22,400.00 |
3,300.00 |
23,100.00 |
3,500.00 |
24,500.00 |
|
|
| S-032 |
manholes (s&wb of new orleans) (dwg. d-870) type 2
|
5   |
EACH |
3,800.00 |
19,000.00 |
3,600.00 |
18,000.00 |
3,900.00 |
19,500.00 |
|
|
| S-033 |
manholes (s&wb of new orleans) (dwg. d-870) type 3
|
1   |
EACH |
4,000.00 |
4,000.00 |
4,000.00 |
4,000.00 |
4,200.00 |
4,200.00 |
|
|
| S-034 |
manholes (s&wb of new orleans) (dwg. d-3340)
|
4   |
EACH |
5,600.00 |
22,400.00 |
4,000.00 |
16,000.00 |
5,700.00 |
22,800.00 |
|
|
| S-035 |
catch basins (s&wb of n.o. single driveover) (dwg.
3431-a) |
4   |
EACH |
2,300.00 |
9,200.00 |
2,000.00 |
8,000.00 |
3,400.00 |
13,600.00 |
|
|
| S-036 |
catch basins (d #3431-r)
|
20   |
EACH |
2,700.00 |
54,000.00 |
2,000.00 |
40,000.00 |
3,300.00 |
66,000.00 |
|
|
| S-037 |
catch basins (dwg-873)
|
2   |
EACH |
2,500.00 |
5,000.00 |
2,400.00 |
4,800.00 |
3,500.00 |
7,000.00 |
|
|
| S-038 |
gravel bed and filter cloth over tree roots
|
lump |
LUMP |
2,800.00 |
2,800.00 |
1,000.00 |
1,000.00 |
6,000.00 |
6,000.00 |
|
|
| S-039 |
landscaping
|
lump |
LUMP |
2,200.00 |
2,200.00 |
1,000.00 |
1,000.00 |
2,000.00 |
2,000.00 |
|
|
| S-040 |
tree trimming
|
lump |
LUMP |
3,300.00 |
3,300.00 |
2,000.00 |
2,000.00 |
20,000.00 |
20,000.00 |
|
|
| S-041 |
root pruning
|
lump |
LUMP |
8,100.00 |
8,100.00 |
3,000.00 |
3,000.00 |
20,000.00 |
20,000.00 |
|
|
| S-042 |
new headwalls
|
lump |
LUMP |
18,000.00 |
18,000.00 |
8,000.00 |
8,000.00 |
5,700.00 |
5,700.00 |
|
|
| S-043 |
vibration monitoring
|
lump |
LUMP |
75,000.00 |
75,000.00 |
10,000.00 |
10,000.00 |
15,000.00 |
15,000.00 |
|
|
| S-044 |
replacement of ornamental brick walks
|
150   |
SQFT |
30.00 |
4,500.00 |
20.00 |
3,000.00 |
15.00 |
2,250.00 |
|
|
| S-045 |
saw cutting pcc pavement (2" thick)
|
250   |
INFT |
1.20 |
300.00 |
5.00 |
1,250.00 |
4.00 |
1,000.00 |
|
|
| S-046 |
project signs
|
1   |
EACH |
1,100.00 |
1,100.00 |
1,000.00 |
1,000.00 |
1,000.00 |
1,000.00 |
|
|
| S-047 |
42" x 42" x 15" concrete wye
|
3   |
EACH |
1,900.00 |
5,700.00 |
1,635.00 |
4,905.00 |
2,000.00 |
6,000.00 |
|
|
| S-048 |
30" x 30" x 15" concrete wye
|
4   |
EACH |
1,200.00 |
4,800.00 |
981.00 |
3,924.00 |
1,200.00 |
4,800.00 |
|
|
| S-049 |
24" x 24" x 15" concrete wye
|
2   |
EACH |
800.00 |
1,600.00 |
654.00 |
1,308.00 |
800.00 |
1,600.00 |
|
|
| S-050 |
30" x 30" x 12" concrete wye
|
1   |
EACH |
1,200.00 |
1,200.00 |
981.00 |
981.00 |
1,200.00 |
1,200.00 |
|
|
| S-051 |
video and photographic survey
|
lump |
LUMP |
20,000.00 |
20,000.00 |
25,000.00 |
25,000.00 |
18,000.00 |
18,000.00 |
|
|
| S-052 |
street name sign on new post
|
18   |
EACH |
180.00 |
3,240.00 |
155.00 |
2,790.00 |
170.00 |
3,060.00 |
|
|
| S-053 |
well point system setup/removal
|
lump |
LUMP |
50,000.00 |
50,000.00 |
100,000.00 |
100,000.00 |
50,000.00 |
50,000.00 |
|
|
| S-054 |
operate and maintain well point system
|
1,000   |
HOUR |
40.00 |
40,000.00 |
20.00 |
20,000.00 |
75.00 |
75,000.00 |
|
|
| S-055 |
concrete handicap ramp
|
50   |
SQYD |
150.00 |
7,500.00 |
250.00 |
12,500.00 |
200.00 |
10,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
3,441,969.20 |
|
3,767,390.20 |
|
3,936,338.17 |
|
|
|