LA 20 ThruTraffic Lane Shifts - Lafourche Parish
Tuesday, December 29, 2015 at 11:26:43 AM
Contractors working for DOTD will begin construction of the LA 20 (North Canal Blvd.) Widening project on January 4, 2016. This $9.9 million dollar project will widen LA 20 to 4 lanes from LA 308 to St. Patrick Street. The project also includes drainage work, complete asphalt overlay, and installation of new traffic signals, and is scheduled to be completed in mid-September, 2016.

Motorists can expect travel lane shifts for the duration of the project. Through and local traffic will be maintained in both directions.

Safety Reminder - DOTD appreciates your patience and reminds you to please drive with caution and be on the lookout for work crews and their equipment.

Christopher Rogers, P.E.
LA DOTD Project Engineer
985-447-0943
DOTD Website – WWW.DOTD.LA.GOV
Statewide 511 Traffic Information – WWW.511LA.ORG