I-10/I-12/I-59 (French Branch Bridge - West Pearl River Bridge) St. Tammany Parish
Tuesday, December 01, 2015 at 7:50:19 AM
SPN H. 003107: I-10/I-12/I-59 (French Branch Bridge - West Pearl River Bridge)
St. Tammany Parish
November 30, 2015
Weekend Ramp/Lane Closure

**UPDATE**

There will be a complete ramp closure of the I-59 Southbound Exit Ramp (Exit 1B) to I-10 Eastbound beginning Saturday, December 5, 2015 at 4:00 a.m. until Sunday, December 6, 2015 at 6:00 a.m. (weather permitting) while crews perform roadway surface corrections.

There will be a complete ramp closure of the I-12 Eastbound Exit Ramp to I-59 Northbound (Exit 85B) beginning Sunday, December 6, 2015 at 6:00 a.m. until Monday, December 7, 2015 at 5:00 a.m. (weather permitting) while crews perform roadway surface corrections.

There will also be closures of the inside (left) and outside (right) lanes of I-10/I-12/I-59 on Friday, December 4, 2015 through Monday, December 7, 2015 (weather permitting) while crews remove and replace the roadway at the following locations:
• I-12 Eastbound outside (right) lane between the I-59 overpass (Mile Post 85.54) and I-10 merge (Mile Post 86.28) from 4:00 p.m. Friday, December 4, 2015 to 6:00 a.m. Monday, December 7, 2015. All lanes will re-open Monday, December 7, 2015 at 6:00 a.m.
* I-59 Southbound outside (right) lane between the I-59 Rest Area (Mile Post 1) to the I-10/I-59 split (Mile Post O) from
10:00 p.m. Friday, December 4, 2015 to 5:00 a.m. Monday, December 7, 2015. All lanes will re-open Monday, December 7, 2015 at 5:00 a.m.

Permit/ Detour Section
Motorists traveling I-12 Eastbound to I-59 Northbound will need to exit to I-10 West (Exit 85A) to US 190-B/Fremaux Ave (Exit 265), East on US 190-B to I-10 East, I-10 East to I-59 North.

Motorists traveling I-59 Southbound to I-10 Eastbound will need to continue to I-10 West (Exit 1C) to US 190-B/Fremaux Ave (Exit 265), East on US 190-B to I-10 East.

One lane of traffic will remain open at all times. No oversized loads greater than 12’ wide will be allowed through the construction zone during lane closures.

DETOUR MAP (REVISED): http://bit.ly/1HPtBmS
DETOUR FLYER (REVISED): http://bit.ly/1Bk2zCM

Safety Reminder
DOTD appreciates your patience and reminds you to please drive with caution and be on the lookout for work crews and their equipment

Project Contact:
Stephen Heraty, P.E.
Project Engineer, Volkert, Inc.
985-265-6263
Stephen.Heraty@volkert.com

DOTD Website – WWW.DOTD.LA.GOV