I-20 West Bound From the Vicksburg Bridge to Mile post 182, Madison Parish – Lane Closure
Tuesday, September 01, 2015 at 9:04:32 AM
Tuesday 1 September 2015

UPDATE: I-20 West Bound Madison Parish - Vicksburg Bridge to Mound

Both inside and outside lanes will be open from Tuesday 1 September 2015 through Sunday 20 September 2015. The inside and outside shoulders will be periodically closed during this period.

The 1-20 West Bound from the Vicksburg Bridge to the LA602 – Interstate 20 interchange at Mound, mile post 182, Madison Parish will undergo single lane closures from 21 September 2015 through 19 December 2015. The lane closures are required to perform repairs to the shoulders and travel lanes.

Restrictions - from 21 September 2015 through 19 December 2015:
12 foot maximum width with the following exception,
18 foot maximum width Fridays 6 AM to 6 PM.

Friday, 14 August 2015

The I-20 West Bound Outside Lane from the Vicksburg Bridge to the LA602 – Interstate 20 interchange at Mound, mile post 182, Madison Parish is closed as of Friday, 14 August 2015 and will remain closed until Friday, 4 September 2015. This closure is required to perform repairs to the shoulders and travel lanes.

Restrictions:
12 foot maximum width with the following exception,
18 foot maximum width Fridays 6 AM to 6 PM.

Safety reminder:
D & J Construction Co., Inc. and DOTD appreciate your patience and remind you to please drive with caution around the construction site and be on the lookout for work crews and their equipment.

CONTACT FOR MORE INFORMATION

Douglas Fleming, P.E.
Project Engineer
LA DOTD - District 05
Office: (318) 342-0210
douglas.fleming@la.gov

OR

Jerry White
VP of Operations
D & J Construction Co., Inc.
Phone: 318-388-2764 Ext 222