I-10/I-12/I-59 (French Branch Bridge - West Pearl River Bridge) St. Tammany Parish
Monday, August 03, 2015 at 3:26:16 PM
SPN H.003107: I-10/I-12/I-59 (FRENCH BRANCH BRIDGE – WEST PEARL RIVER BRIDGE)
St. Tammany Parish
August 3, 2015
WEEKEND WORK

There will be closures of the inside (left) and outside (right) lanes of I-10/I-59 on Friday, August 7, 2015 through Monday, August 10, 2015 (weather permitting) while crews remove and replace the roadway at the following locations:
• I-10 Eastbound outside (Right) lane between the French Branch Bridge (Mile Post 267.14) (just north of the Gause Blvd. Overpass) and the West Pearl River Bridge (Mile Post 269.81) (near the I-10 Welcome Center) from 6:00 p.m. Friday, August 7, 2015 to 10:00 a.m. Monday, August 10, 2015. All lanes will be re-open Monday, August 10, 2015 at 10:00 a.m.
• I-10 Westbound inside (Left) lane between the West Pearl River Bridge (Mile Post 269.81) (near the I-10 Welcome Center) and the French Branch Bridge (Mile Post 267.14) (just north of the Gause Blvd. Overpass) from 6:00 p.m. Friday, August 7, 2015 to 2:00 p.m. Monday, August 10, 2015. All lanes will be re-open Monday, August 10, 2015 at 2:00 p.m.
• I-59 Southbound inside (Left) lane between the I-10/I-59 split (Mile Post 0) and just south of the I-59 Rest Area (Mile Post 1) from 7:00 p.m. Friday, August 7, 2015 to 5:00 a.m. Monday, August 10, 2015. All lanes will re-open Monday, August 10, 2015 at 5:00 a.m.

Permit/ Detour Section
One lane of traffic will remain open at all times. No oversized loads greater than 12’ wide will be allowed through the construction zone during lane closures.

Motorists wanting to utilize US 90 as a detour should be aware that there are load restrictions on the Pearl River Bridges which only allow for passenger vehicles. No larger truck traffic will be allowed.

DETOUR MAP (REVISED): http://bit.ly/1HPtBmS
DETOUR FLYER (REVISED): http://bit.ly/1Bk2zCM

Safety Reminder
DOTD appreciates your patience and reminds you to please drive with caution and be on the lookout for work crews and their equipment

Project Contact:
Stephen Heraty, P.E.
Project Engineer, Volkert, Inc.
985-265-6263
Stephen.Heraty@volkert.com

DOTD Website – WWW.DOTD.LA.GOV