US 167 Grant Parish to LA 472 Winn Parish; S.P. # H.010368.6; Control Section 023-03
Thursday, March 26, 2015 at 10:44:19 AM
US 167 Grant Parish to the intersection of LA 472 Winn Parish; S.P. #H.010368.6; Control Section 023-03

The Louisiana Department of Transportation and Development (DOTD), advises the public that on Wednesday, April 1, 2015 removal of the existing surfacing will begin on the northbound side of US 167 in Grant Parish. This work will begin at the intersection of US167 and LA 472 then proceed north approximately 9 miles ending at the Winn Parish line.


The intent of this project is to patch, cold plane to a depth of 2”, then overlay the existing northbound US 167 with 3.5” of Superpave Asphaltic Concrete. On Wednesday, April 1, 2015 the contractor will begin this process with patching and cold planing the existing surface. One lane will be closed at a time, allowing traffic through the project at all times.


The project was awarded to the low bidder, Gilchrist Construction Co. LLC, in the amount of $3,725,228.45 The work associated with this project should take approximately 170 calendar days to complete.

Permit/Detour section
Thru traffic will be maintained at all times.

Safety Reminder
DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.

Additional Information

Call (318) 561-5100 or (800) 542-3509 or 511 or visit www.511LA.org for additional information. Motorists may also monitor the LA DOTD website, www.dotd.la.gov, selecting MYDOTD, the LA DOTD Facebook page, or the LA DOTD Twitter page, @Alex_Traffic for further information.


Media Contact Information
Ms. LaDeidra Druilhet, Public Information Officer
Office # 1(337)262-6133
Email Address: Deidra.Druilhet@LA.GOV

Project Contact
Mr. David Pugh, Project Engineer
District 08, Gang 258
Office # 1(318)627-5522 or 1(318)627-5457
Email Address: David.Pugh@LA.GOV