US 80 (Desiard St.) / Ouachita Parish
Friday, January 09, 2015 at 2:14:10 PM
US 80 (Desiard St.) In Ouachita Parish will be reduced to the outside lanes, allowing the interior lanes to be closed near Gilbert St... This lane reduction will begin Monday, January 12, 2015 and remain in effect until further notice. This lane reduction will allow contractors to construct the concrete island at this section of roadway.

DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.

Contact Persons:

Chad McMillan
Amethyst Construction
Phone: (318) 381-1541

Jamie Anderson
LA DOTD - District 05/Permits
P.O. Box 4068
Monroe, LA 71211
Phone: (318) 342-0120
Fax: (318) 342-0260