I-20 Bridge over Ouachita River, Ouachita Parish
Wednesday, May 21, 2014 at 5:36:22 PM
Eastbound and Westbound I-20 on the Ouachita River Bridge will experience nightly lane closures beginning on Tuesday, May 27, 2014.  The lane closures will occur at the times shown below and will allow the contractor to overlay portions of the bridge deck with a surface treatment and perform other various rehab work.

 Eastbound Construction Phase: 
 7:00pm Monday to 7:00 am Tuesday
 7:00pm Tuesday to 7:00 am Wednesday
 7:00pm Wednesday to 7:00 am Thursday
 7:00pm Thursday to 7:00 am Friday
 8:00pm Friday to 10:00 am Saturday
 7:00pm Saturday to 12:00 Noon Sunday
 6:00pm Sunday to 7:00 am Monday

 Westbound Construction Phase: 
 7:00pm Monday to 7:00 am Tuesday
 7:00pm Tuesday to 7:00 am Wednesday
 7:00pm Wednesday to 7:00 am Thursday
 7:00pm Thursday to 7:00 am Friday
 9:00pm Friday to 9:00 am Saturday
 8:00pm Saturday to 12:00 Noon Sunday
 7:00pm Sunday to 7:00 am Monday

This work may also result in ramp closures during the above mentioned times.  Detour signing will be provided for ramp closures.

Intech Contracting, GEC Consulting, and LA DOTD appreciate your patience and remind you to please drive with caution through the construction site and be on the lookout for the work crews and their equipment.