Leesville Roundabout Project Update
Wednesday, June 08, 2011 at 3:56:57 PM

Current work:
The contractor is in the process of removing and replacing sections of the roadway on US 171 south bound lanes.

Completed work:
The soil cement and stone base courses for the La. 8/La. 28 west bound lanes and the US 171 south bound lanes are complete.

For questions or comments, contact DOTD’s Customer Service Center at 1-877-4LA-DOTD (1-877-452-3683) or e-mail cs@dotd.la.gov. The center is open 7:30 a.m. – 5 p.m., Monday through Friday. You can also visit the project’s Web page by going to www.dotd.la.gov and clicking on "Projects" from the Programs & Projects section of the main menu on the left-hand side of the page and selecting the “Roundabout Projects/Information,” or “US 171/LA 8/28 Roundabout in Leesville” project links.

Again, we thank you for your feedback and patience during this construction. Additionally, at your convenience, please let us know how we are doing by filling out our Customer Service Survey.

State Project Number: 373-01-0020
Parish: Vernon
Start Date: October 2010
Finish Date: Spring 2011
Cost: $2.1 million
Contractor: Diamond B Construction