LA 42 Widening Project (Ascension Parish)
Monday, July 08, 2013 at 11:51:17 AM

Just a brief update on the progress of LA 42.

The clearing and utility project will be let in August and should be completed early next year. This will include building the parish’s $5M sewer system and moving utilities in anticipation for the roadway project which is scheduled to let March 2014.