La. 73 Widening from I-10 to U.S. 61 (Airline Hwy) Project Update
Wednesday, August 07, 2013 at 11:17:54 AM

The project has run into some delays that have pushed the completion date back to Summer 2014. The contractor is working to fit drainage structures in a very limited space without disturbing utilities lines within the roadway space. At the same time, we are trying to protect and conserve the large Oak trees in the area. The contractor will continue working as safely and as timely as is permitted within the constraints of this space, but this adjustment has lengthened the timetable for this project.

We appreciate your patience and value your feedback. You may contact DOTD Customer Service at 1-877-4LADOTD (1-877-452-3683) if you have questions or concerns.