LA 22 & LA 73 Ascension Parish Construction Zone
Thursday, October 13, 2022 at 12:47:57 PM
Construction for State Project H.014131:LA 22 & LA 73: PCC AT I-10 INTERCHANGES is anticipated to begin Tuesday, October 18, 2022. This project is 0.456 miles in Ascension Parish. The type of work includes concrete pavement patching, plastic pavement striping, loop detectors, and related work at cost of $1,909,617.75.

The Louisiana Department of Transportation and Development advises motorists of the active construction zone on LA 22 and LA 73 at I-10. Motorists will have access to travel the roadways, but should anticipate delays due to work zone conditions. No permit or oversized loads greater than 16’ feet wide will be able to pass while construction takes place.

DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.

Scott Lobell, P.E., P.L.S.
Project Engineer ~ District 61
Office (225) 675-5320