UPDATE: I-310 Southbound, St. Charles Parish, S.P. H.012617
Tuesday, March 22, 2022 at 10:15:26 AM
Work is progressing on the southbound lanes of the I-310 Hale Boggs Bridge.

Concrete work is underway between Exit 6 (LA 48) in Destrehan/ St. Rose and Exit 7 (LA 48) in Luling. The southbound left lane work is now expected to be complete by Saturday, April 2, 2022, weather permitting. On Sunday, April 3, 2022, work will shift to the northbound lanes.

During construction, I-310 southbound will allow vehicles 12 feet wide or smaller to pass through the construction zone.

Safety Reminder:
DOTD appreciates your patience and reminds you to please drive with caution through the site and be on the lookout for work crews and their equipment.

Additional Information:
Call 511 or visit www.511la.org for additional information. Out-of-state travelers may call 1-888-ROAD-511 (1-888-762-3511).
Motorists may also monitor the LA DOTD website at www.dotd.la.gov, by selecting MYDOTD, or by visiting the DOTD Facebook and Twitter pages.