The Louisiana Department of Transportation and Development, (DOTD), announces that weather permitting, clearing and grubbing operations will begin on the LA 392 bridge project on Monday, January 24, 2022 and will continue for approximately two (2) weeks. In order to facilitate utility relocations on the project, the contractor will clear and grub the site and demobilize until utility relocations are complete. A subsequent press release will be issued prior to the contractor resuming operations. This bridge replacement project is located on LA 392, beginning at the junction of LA 392 and Cecil Prewitt Rd and ending east of the junction of LA 392 and Erwin Rd. This 0.439-mile-long project will receive clearing and grubbing, removal of timber bridges, grading, drainage structures, pavement patching, class II base course, lime treatment, asphalt concrete overlay, precast concrete piles, concrete slab span bridges, and related work.

The project was awarded to the lowest bidder, WL Bass Construction Inc., in the amount of $5,131,701.93.

Permit/Detour section
The contractor will begin clearing and grubbing on Monday, January 24, 2022. The roadway will remain open to all local and through traffic with no restrictions. The roadway will be reduced to one lane during construction operations.

Safety reminder
DOTD appreciates your patience and reminds you to please drive with caution and be on the lookout for work crews and their equipment.

Additional Information
Motorists can access the latest updates on real-time traffic and road conditions using the 511 Traveler Information System by dialing 511 from their telephone and saying the route or region on which they are seeking information. Out-of-state travelers can call 1-888-ROAD-511 (1-888-762-3511). Travelers can also access this information by visiting the 511 Traveler Information Web site at www.511la.org. Additionally, you can follow the Traffic Management Center on Twitter: (@Alex Traffic). Motorists may also monitor the LA DOTD website @ www.dotd.la.gov and the DOTD Facebook page.

Project Contact
Mr. Randall Duffey, P.E.
Sabine and Vernon Parishes Project Engineer
Office: (337) 238-6406
Email: randall.duffey@la.gov

Media Contact
Mrs. Erin Buchanan Mills
Public Information Officer 3
District 08: Avoyelles, Grant, Natchitoches, Rapides, Sabine, Vernon, and Winn Parishes
Phone: (318) 549-8402
Email: erin.buchanan@la.gov