I-10 EB & WB from Exit 103 (I-49) to Exit 109 (LA 328), Lafayette & St. Martin Parishes, Lane Closures
Monday, August 16, 2021 at 11:27:27 AM
I-10 eastbound & westbound from Exit 103 (I-49) to Exit 109 (LA 328) will have nightly lane closures between 8:00 p.m. and 6:00 a.m. beginning Sunday, August 15 until Tuesday, August 24, weather permitting.

These closures are necessary to allow crews to install bridge deck joint seals and stripe the roadway.

There will be no vehicle width restrictions associated with this lane closure.

Emergency vehicles will have access to the area but may encounter delays. No detour route is necessary.

The $124.7 million I-10 widening project will involve widening a 7.11-mile section from I-49 to Breaux Bridge (State Project Number H.003003). The project will include pavement replacement within the existing lanes and the construction of one additional lane in each direction along I-10 from I-49 to LA 328 (Breaux Bridge).

The project began in May 2017 and is estimated for completion in Summer 2021.