US 61, EAST AND WEST FELICIANA PARISHES, SP#H.013193
Friday, April 26, 2019 at 2:38:18 PM
On US 61, at the Thompson Creek Bridge, on the Northbound side of the road, the contractor will begin the pre-work needed in order to begin working on the the detour road required for this bridge work.

They have a tentative schedule as follows:

5/1 - 5/2 - Northbound Shoulder Closure - install signs

5/2 - 5/7 - Northbound Shoulder Closure - clear and grub mostly on the northbound bridge on the south side of the bridge/outside lane. Will also build crane pad.

5/3 -Northbound Shoulder Closure - remove guardrail on northbound outside and install temporary attenuator

5/6 - Northbound Outside Lane Closure - 4 truckloads of crane mats will be delivered and unloaded

5/8 - 5/10 - Northbound Outside Lane Closure - crane will be delivered and set up

There are no restrictions and no detour will be required.
Emergency vehicles will be allowed to pass through the project.

DOTD apprectiates your patience. Please drive with caution and be on the lookout through the construction site for work crews and their equipment.