I-10 westbound from Exit 109 – LA 328 (Breaux Bridge) to the Bayou Teche Bridge, Lafayette Parish, Lane Closure, SPN H.003003
Friday, June 15, 2018 at 3:50:16 PM

The left lane of I-10 westbound from Exit 109 – LA 328 (Breaux Bridge) to the Bayou Teche Bridge will be closed the night of Tuesday, June 19, to allow crews to erect span girders.


This closure is estimated to take place from 8 p.m. to 6 a.m., weather permitting.


DOTD appreciates your patience and reminds you to please drive with caution and be on the lookout for work crews and their equipment.


The $124.7 million I-10 widening project will involve widening a 7.11-mile section from I-49 to Breaux Bridge (State Project Number H.003003). The project will include pavement replacement within the existing lanes and the construction of one additional lane in each direction along I-10 from I-49 to La 328 (Breaux Bridge).


The project began in May 2017 and is estimated for completion in fall 2019.