Lafayette and St. Martin Parishes – Interstate 10 – Lane and ramp closures
Thursday, May 18, 2017 at 3:24:53 PM
All lane closures scheduled from Thursday, May 18 until Sunday, May 21 have been CANCELLED. Work will resume on Monday, May 22.

The Louisiana Department of Transportation and Development (DOTD) announces that the following work is scheduled to take place along I-10:

On Monday, May 8, the westbound left lane of I-10, between I-49 to LA 328 (Breaux Bridge), will be closed for the removal of reflectors.

On Tuesday, May 9, the westbound right lane of I-10, between LA 328 (Breaux Bridge) to Sawmill Overpass, will be closed to traffic for striping operations. Additionally, the I-10 westbound on and off ramps at LA 328 will have intermittent lane closures for striping operations.

On Wednesday, May 10, the westbound right lane of I-10, between Sawmill Overpass to I-49, will be closed to traffic for striping operations. Additionally, the I-10 westbound on and off ramps at Louisiana Avenue will have intermittent lane closures for striping operations.

Beginning Thursday, May 11, until Friday, May 12, the westbound left lane of I-10, between LA 328 (Breaux Bridge) to I-49, will be closed for striping operations.

On Friday, May 12, the eastbound right lane of I-10, from I-49 to Sawmill Overpass will be closed to traffic for striping operations. Additionally, the I-10 eastbound on and off ramps at Louisiana Avenue will have intermittent lane closures for striping operations.

Beginning Friday, May 12 until Sunday, May 21, the westbound left lane of I-10, from LA 328 (Breaux Bridge) to Vermilion River Bridge (east of Louisiana Avenue Overpass), will be closed for installation of concrete barrier rails.

On Saturday, May 13, the eastbound right lane of I-10, from Sawmill Overpass to LA 328 (Breaux Bridge), will be closed to traffic for striping operations. Additionally, the I-10 eastbound on and off ramps at LA 328 (Breaux Bridge) will have intermittent lane closures for striping operations.

Beginning Sunday, May 14, until Monday, May 15, there will be alternating lane closures in the westbound and eastbound directions of I-10, from I-49 to LA 328 (Breaux Bridge), will be closed for striping operations.

Beginning Sunday, May 21 until Thursday, June 1, the eastbound left lane of I-10, from LA 328 (Breaux Bridge) to Vermilion River Bridge (east of Louisiana Avenue Overpass), will be closed for installation of concrete barrier rails.

All closures are estimated to take place nightly from 8:00 p.m. to 6:00 a.m., weather permitting.

There are no restrictions for permit loads.

DOTD apologizes for any inconvenience to the traveling public and encourages motorists to lookout for crews and their equipment.

This work is related to the FASTLANE I-10 widening project. The $124.7 million I-10 widening project will involve widening a 7.11-mile section from I-49 to Breaux Bridge. The project will include pavement replacement within the existing lanes and the construction of one additional lane in each direction along I-10 from I-49 to La 328 (Breaux Bridge).

With the help of the FASTLANE grant, this is the first of three projects to reconstruct and widen the I-10 corridor from I-49 to the Atchafalaya Basin Bridge.

Awarded to James Construction, this project will begin in May 2017 and is estimated for completion in fall 2019.