I-12, Livingston Parish, Lane Closure
Monday, May 13, 2013 at 7:58:00 AM

I-12 Westbound, from Satsuma Rd  to LA 447 (between Satsuma Rd and Walker), will have single lane closures alternating between the inside and outside lanes beginning Monday, May 13, 2013 through Sunday, May 19, 2013 from 8:30 pm - 5:30 am, nightly (weather permitting).  One lane will remain open at all times.  These lane closures will allow crews to perform repairs on the approach slabs of the Middle Colyell Creek Bridge near mile marker 18.

 

This closure will allow vehicles up to 11 feet wide to pass through the construction zone.  The road is open for regular traffic but oversize vehicles and loads will be under permit restrictions.

 

Motorists may take US 190 as an alternate route to avoid nightly lane closures during construction.

 

DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.