I-10 & I-12 St. Tammany Parish Approach Slab Repairs, St. Tammany Parish
Friday, January 06, 2017 at 10:25:30 AM
LANE CLOSURE
SPN H.009596: I-10 & I-12 St. Tammany Parish Approach Slab Repairs
St. Tammany Parish
January 6, 2017

There will be a right lane closure on I-10 Eastbound at the Middle Pearl River Bridge (Milepost 272.84 to Milepost 273.20) beginning at 8:00 p.m. Friday, January 13, 2017 and continuing until 6:00 a.m. on Monday, January 16, 2017 while crews work on the roadway.

Permit/Detour Section

To avoid construction delays, Eastbound motorists may take US 190 B (Exit #265 – Fremaux Ave.), to US 90 (Chef Menteur Hwy.), east on US 90 to MS 607, north on MS 607 to I-10.

Motorists wanting to utilize US 90 as a detour should be aware that there are load restrictions on the Pearl River Bridges.

One lane of traffic will be open at all times. Emergency vehicles will have access. By law, oversize loads are not allowed to travel at night.

Safety Reminder
DOTD appreciates your patience and reminds you to please drive with caution and be on the lookout for work crews and their equipment.

Project Contact
Seth deArmas, P.E.
DOTD Project Engineer
Covington Construction Office
985-893-6367
Seth.deArmas@LA.gov
DOTD Website – www.dotd.la.gov
Statewide 511 Traffic Information – www.511la.org