US 90B, Jefferson Parish, H.009933
Friday, August 12, 2016 at 2:24:37 PM
Westbound elevated US90B (Westbank Expressway) in Harvey; nightly alternating closure: two right lanes closed then left lane closed from approx. Manhattan Blvd. to the Harvey Canal overpass on Sunday night (August 14, 2016) from 9:00pm – 6:00am. This closure will be in place while crews restripe expressway lanes.

Westbound US90B (Westbank Expressway) Manhattan Blvd. off-ramp in Harvey and Lafayette on-ramp in Gretna closed Sunday night (August 14, 2016) and Monday night (August 15, 2016) from 9:00 pm – 5:00 am. This closure will be in place while crews perform roadway work.

Westbound US90B (Westbank Expressway) ground-level from Manhattan Blvd. to Brown Ave. in Harvey; all lanes closed (including Manhattan Blvd. on-ramp) nightly Sunday night (August 14, 2016) thru Tuesday night (August 16, 2016) from 9:00pm – 5:00am. This closure will be in place while crews perform asphalt installations and striping.

US90B (Westbank Expressway) Manhattan crossover in Harvey, all lanes closed on Sunday night (August 14, 2016) and Monday night (August 15, 2016) from 9:00 pm – 5:00 am. This closure will be in place while crews perform striping and traffic signal work.

Vehicle restrictions for wide loads greater than 12’. General public and restricted load vehicles may detour using LA 18 (4th St) to LA 3018 (Destrehan Ave) to US90B (Westbank Expressway). Emergency vehicles will not have access during closures.

DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.

Chad Larkins, MSCE, EI
Construction - Assistant Project Engineer
Bridge City - District 02, Jefferson Parish
Office: 504-309-7842
Email: chad.larkins@la.gov