Southbound and Northbound, LA Hwy 23 (Port Sulphur) from north of St. Jude Road to south of Grand Bayou Road/Fosters Road
Northbound lane closure starting 8/12/16 at 6:00 pm until 8/26/16 at 6:00 pm for construction of drainage pipe cross drains and raising and reconstruction of LA Hwy 23 roadway section near St. Jude Road

Northbound and southbound LA Hwy 23 traffic will utilize the southbound lanes through the work zone

This northbound lane closure will allow vehicles 11 feet wide or smaller to pass through the construction zone. No detour is available.

DOTD appreciates your patience and reminds you to please drive with caution through the construction/maintenance site and be on the lookout for work crews and their equipment.