I-10/I-12/I-59 (French Branch Bridge - West Pearl River Bridge) St. Tammany Parish
Friday, May 20, 2016 at 9:24:24 AM
SPN H. 003107: I-10/I-12/I-59 (French Branch Bridge - West Pearl River Bridge)
St. Tammany Parish
May 17, 2016
Weekend Ramp/Lane Closure

**UPDATE**

There will be intermittent ramp closures of the I-59 Northbound to I-10 Westbound Exit Ramp (Exit 267B) Sunday, May 22, 2016 from 1:00 a.m. until 9:00 a.m. (weather permitting). All lanes will re-open Sunday, May 22, 2016 at 9:00 a.m.

There will be intermittent closures of the inside (left) and outside (right) lanes of I-10/I-12/I-59 on Friday, May 20, 2016 through Monday, May 23, 2016 (weather permitting) while crews perform final dressing activities.

• I-59 Northbound outside (right) lane between I-10/I-59 split (Mile Post 0) and just south of the I-59 Rest Area (Mile Post 1) from 7:00 p.m. Friday, May 20, 2016 to 12:00 p.m. Monday, May 23, 2016. All lanes will re-open Monday, May 23, 2016 at 12 noon.
• I-59 Southbound between I-10/I-59 split (Mile Post 0) and I-59 Rest Area (Mile Post 1) from 7:00 p.m. Friday, May 20, 2016 to 5:00 a.m. Monday, May 23, 2016. All lanes will re-open Monday, May 23, 2016 at 5:00 a.m.
• I-10 Eastbound between the French Branch Bridge (Mile Post 267.14) (just north of Gause Blvd.) and the West Pearl River Bridge (Mile Post 269.81) (near the I-10 Welcome Center) from 7:00 p.m. Friday, May 20, 2016 to 10:00 a.m. Monday, May 23, 2016. All lanes will be open between 10:00 a.m. and 7:00 p.m. daily.
• I-10 Westbound between the West Pearl River Bridge (Mile Post 269.81) (near the I-10 Welcome Center) and the French Branch Bridge (Mile Post 267.14) (just north of Gause Blvd.) from 5:00 a.m. Saturday, May 21, 2016 to 11:00 a.m. Sunday, May 22, 2016. All lanes will re-open Sunday, May 22, 2016 at 11:00 a.m.
• I-12 Eastbound between the I-59 southbound overpass (Mile Post 85) and the I-10 Eastbound merge (Mile Post 86) from 4:00 p.m. Friday, May 20, 2016 through 7:00 p.m. Saturday, May 21, 2016. All lanes will re-open Saturday, May 21, 2016 at 7:00 p.m.

Permit/ Detour Section

Motorists traveling I-59 Northbound to I-12 Westbound will need to continue north to LA 1090 (Exit 3), west on LA 1090 to I-59 Southbound, south on I-59 to I-12 Westbound (Exit 1A).

One lane of traffic will remain open at all times. No oversized loads greater than 12’ wide will be allowed through the construction zone during lane closures.

DETOUR MAP (REVISED): http://bit.ly/1HPtBmS
DETOUR FLYER (REVISED): http://bit.ly/1Bk2zCM

Safety Reminder
DOTD appreciates your patience and reminds you to please drive with caution and be on the lookout for work crews and their equipment

Project Contact:
Stephen Heraty, P.E.
Project Engineer, Volkert, Inc.
985-265-6263
Stephen.Heraty@volkert.com