LA 6, between US 171 and LA 476; Sabine Parish; H000792; Structure Maintenance
Tuesday, March 22, 2016 at 12:04:06 PM
**03-22-2016**
**Bridge Super and Substructure Repair and Painting**

Sabine Parish
LA 6, between US 171 and LA 476
Edmonson Creek crossing and San Jose crossing
Project #: H.000792


The Louisiana Department of Transportation and Development (DOTD), advises the public that beginning on Monday March 28, 2016 at 7:00 AM, construction work will continue on the bridge location listed below. The work will consist of bridge repair. The Construction work is expected to be completed in January 2017. Updates to the Permit/Detour Section are listed below.

LOCATION:
Route: LA 6, between US 171 and LA 476 in Sabine Parish (Structure No. 08430340211581), the crossing over Edmonson Creek, and (Structure No. 08430340214661), the crossing over San Jose Creek.

DATE:

March 28, 2016 – April 15, 2016

Permit/Detour Section:
Road will remain open.
Restrictions: There will be a width restriction of 12 feet

Safety Reminder
DOTD appreciates your patience and reminds you to please drive with caution through the construction site and be on the lookout for work crews and their equipment.

Additional Information
Call (318) 561-5100 or (800) 542-3509 or 511 or visit www.511LA.org for additional information. Motorists may also monitor the LA DOTD website @ www.dotd.la.gov , by selecting MYDOTD, the Way to Geaux Application for iPhone or Android devices, the DOTD Facebook page or the LA DOTD Twitter page, @Alex_Traffic for further information and details.

Project Contacts:
Steve Buskie
DOTD Project Coordinator
Office # (318) 561-5213
steve.buskie@la.gov

William Dean
Project Engineer
Office (318) 473-2100
bdean@paealex.com

Media Contact:
Ms. Cindy Dorfner, Public Information Officer
Grant, Natchitoches, Sabine, and Winn Parishes
Phone # 318-549-8402