Belle Chasse Bridge & Tunnel Project: Lane Closure Notice
Friday, April 26, 2024 at 1:41:02 PM
BELLE CHASSE, LA. - The Belle Chasse Bridge and Tunnel Replacement Project announces scheduled construction activities and anticipated traffic impacts. These anticipated impacts are weather-permitting and subject to potential changes.

Weekday Daytime Schedule (8:00 AM - 2:00 PM)
· Wednesday, 5/1 - LA 23 northbound left lane closure from Engineers Rd. to Barriere Rd.
· Thursday, 5/2 - LA 23 northbound left lane closure from Engineers Rd. to Barriere Rd.
· Friday, 5/3 - LA 23 northbound left lane closure from Engineers Rd. to Barriere Rd.

Weekend Daytime Schedule (7:00 AM - 5:00 PM)
· Saturday, 4/27 - LA 23 southbound left lane closure from Engineers Rd. to Barriere Rd.
· Sunday, 4/28 - LA 23 southbound left lane closure from Engineers Rd. to Barriere Rd.
· Saturday, 5/4 - LA 23 southbound left lane closure from Engineers Rd. to Barriere Rd.
· Sunday, 5/5 - LA 23 southbound left lane closure from Engineers Rd. to Barriere Rd.

Weekend and Weekday Evening Schedule (7:30 PM-5:30 AM)
· Thursday, 4/25 - LA 23 northbound left lane closure from Engineers Rd. to Barriere Rd.
· Friday, 4/26 - LA 23 southbound and northbound left lane closure from Engineers Rd. to Barriere Rd.
· Saturday, 4/27 - LA 23 northbound left lane closure from Engineers Rd. to Barriere Rd.
· Sunday, 4/28 - LA 23 northbound left lane closure from Engineers Rd. to Barriere Rd.
· Saturday, 5/4 - LA 23 northbound left lane closure from Engineers Rd. to Barriere Rd.
· Sunday, 5/5 - LA 23 northbound left lane closure from Engineers Rd. to Barriere Rd.

To sign up for project updates, please visit bellechassebridge.com and provide your email address for notifications to go directly to your inbox as the new bridge construction continues. Interested parties can submit questions to the project team via email at info@bellechassebridge.com. You can also follow the project on Facebook @BelleChasseBridge and Twitter @Bridge_BC.