| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BYRON E. TALBOT CONTRACTOR, INC. |
- 2 - RICHARD PRICE CONTRACTING CO, LLC |
- 3 - THREE C'S PROPERTIES INC |
- 4 - GERACE CONSTRUCTION LLC |
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
65,000.00 |
65,000.00 |
46,500.00 |
46,500.00 |
60,000.00 |
60,000.00 |
110,000.00 |
110,000.00 |
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
5,500.00 |
5,500.00 |
25,000.00 |
25,000.00 |
6,000.00 |
6,000.00 |
3,500.00 |
3,500.00 |
| 202-02-D |
removal of concrete walks & drives
|
181   |
SQYD |
3.75 |
678.75 |
6.00 |
1,086.00 |
7.50 |
1,357.50 |
10.00 |
1,810.00 |
| 202-02-E |
removal of concrete curbs
|
300.0 |
LNFT |
1.50 |
450.00 |
6.00 |
1,800.00 |
4.50 |
1,350.00 |
5.00 |
1,500.00 |
| 202-02-G |
removal of surfacing & stabilized base
|
1,122.4 |
SQYD |
11.75 |
13,188.20 |
4.00 |
4,489.60 |
3.00 |
3,367.20 |
5.00 |
5,612.00 |
| 202-02-01 |
removal of house (sta. 109+70; 3,300 sqft with brick
veneer) |
1   |
EACH |
10,000.00 |
10,000.00 |
6,000.00 |
6,000.00 |
9,000.00 |
9,000.00 |
12,000.00 |
12,000.00 |
| 202-02-02 |
removal of house (sta. 110+40; 2,500 sqft with brick
veneer) |
1   |
EACH |
10,000.00 |
10,000.00 |
6,000.00 |
6,000.00 |
8,000.00 |
8,000.00 |
12,000.00 |
12,000.00 |
| 202-02-03 |
removal of concrete drainage inlet structure (sta.
123+48) |
1   |
EACH |
1,100.00 |
1,100.00 |
2,500.00 |
2,500.00 |
1,500.00 |
1,500.00 |
3,000.00 |
3,000.00 |
| 203-02 |
drainage excavation
|
60   |
CUYD |
4.50 |
270.00 |
20.00 |
1,200.00 |
23.50 |
1,410.00 |
30.00 |
1,800.00 |
| 203-05 |
excavation and embankment
|
lump |
LUMP |
40,000.00 |
40,000.00 |
54,000.00 |
54,000.00 |
36,000.00 |
36,000.00 |
50,000.00 |
50,000.00 |
| 204-02 |
temporary hay or straw bales
|
350   |
EACH |
9.35 |
3,272.50 |
25.00 |
8,750.00 |
13.00 |
4,550.00 |
10.00 |
3,500.00 |
| 204-06 |
temporary silt fencing
|
6,300   |
LNFT |
2.25 |
14,175.00 |
3.00 |
18,900.00 |
0.75 |
4,725.00 |
1.50 |
9,450.00 |
| 302-02-E |
class ii base course (10" thick)
|
9,815.3 |
SQYD |
21.85 |
214,464.31 |
19.80 |
194,342.94 |
17.50 |
171,767.75 |
23.00 |
225,751.90 |
| 304-05 |
lime treatment (type e)
|
150.00 |
TON |
230.00 |
34,500.00 |
231.00 |
34,650.00 |
470.00 |
70,500.00 |
230.00 |
34,500.00 |
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
20   |
CUYD |
70.00 |
1,400.00 |
117.00 |
2,340.00 |
58.75 |
1,175.00 |
100.00 |
2,000.00 |
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
100.0 |
CUYD |
69.75 |
6,975.00 |
90.00 |
9,000.00 |
53.75 |
5,375.00 |
60.00 |
6,000.00 |
| 502-01 |
superpave asphaltic concrete
|
745.5 |
TON |
135.00 |
100,642.50 |
150.00 |
111,825.00 |
130.00 |
96,915.00 |
150.00 |
111,825.00 |
| 509-01 |
cold planing asphaltic pavement
|
369   |
SQYD |
8.80 |
3,247.20 |
27.00 |
9,963.00 |
23.50 |
8,671.50 |
25.00 |
9,225.00 |
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 21   |
CUYD |
5.00 |
- 105.00 |
5.75 |
- 120.75 |
5.00 |
- 105.00 |
5.00 |
- 105.00 |
| 601-01-G |
portland cement concrete pavement (8" thick)
|
8,279.6 |
SQYD |
48.75 |
403,630.50 |
56.25 |
465,727.50 |
68.00 |
563,012.80 |
55.00 |
455,378.00 |
| 601-04 |
portland cement concrete pavement coring
|
10   |
EACH |
55.00 |
550.00 |
150.00 |
1,500.00 |
72.00 |
720.00 |
300.00 |
3,000.00 |
| 701-03-F |
storm drain pipe (15" rcp/pcp)
|
863   |
LNFT |
29.00 |
25,027.00 |
37.50 |
32,362.50 |
38.50 |
33,225.50 |
65.00 |
56,095.00 |
| 701-03-F/G-01 |
storm drain pipe (15" pcp or 18" cmp)(outfall)
|
11   |
LNFT |
30.00 |
330.00 |
70.00 |
770.00 |
47.00 |
517.00 |
100.00 |
1,100.00 |
| 701-03-G |
storm drain pipe (18" rcp/pcp)
|
421   |
LNFT |
32.00 |
13,472.00 |
44.75 |
18,839.75 |
45.50 |
19,155.50 |
65.00 |
27,365.00 |
| 701-03-I |
storm drain pipe (24" rcp/pcp)
|
744   |
LNFT |
52.00 |
38,688.00 |
60.25 |
44,826.00 |
57.00 |
42,408.00 |
75.00 |
55,800.00 |
| 701-04-A |
storm drain pipe arch (15" equiv. rcpa)
|
290   |
LNFT |
39.00 |
11,310.00 |
52.00 |
15,080.00 |
77.00 |
22,330.00 |
65.00 |
18,850.00 |
| 701-04-A-01 |
storm drain pipe arch (15" equiv. cmpa)(outfall)
|
138   |
LNFT |
37.25 |
5,140.50 |
46.00 |
6,348.00 |
76.00 |
10,488.00 |
60.00 |
8,280.00 |
| 701-04-J |
storm drain pipe arch (60" equiv. rcpa)
|
279   |
LNFT |
213.00 |
59,427.00 |
230.00 |
64,170.00 |
265.00 |
73,935.00 |
250.00 |
69,750.00 |
| 701-04-L |
storm drain pipe arch (72" equiv. rcpa)
|
102   |
LNFT |
305.00 |
31,110.00 |
320.00 |
32,640.00 |
320.00 |
32,640.00 |
325.00 |
33,150.00 |
| 701-05-G |
side drain pipe (18")
|
52   |
LNFT |
37.50 |
1,950.00 |
44.50 |
2,314.00 |
56.00 |
2,912.00 |
70.00 |
3,640.00 |
| 701-09 |
fabricating pipe fittings
|
1   |
EACH |
275.00 |
275.00 |
1,700.00 |
1,700.00 |
1,300.00 |
1,300.00 |
1,500.00 |
1,500.00 |
| 702-02 |
manholes (mh-12.5x9)
|
1   |
EACH |
16,000.00 |
16,000.00 |
17,700.00 |
17,700.00 |
14,000.00 |
14,000.00 |
10,000.00 |
10,000.00 |
| 702-03 |
catch basins (cb-sd08)
|
1   |
EACH |
9,000.00 |
9,000.00 |
23,200.00 |
23,200.00 |
18,000.00 |
18,000.00 |
11,000.00 |
11,000.00 |
| 702-03-A |
catch basins (cb-01)
|
2   |
EACH |
1,665.00 |
3,330.00 |
2,800.00 |
5,600.00 |
2,500.00 |
5,000.00 |
2,500.00 |
5,000.00 |
| 702-03-C |
catch basins (cb-06)
|
23   |
EACH |
2,400.00 |
55,200.00 |
3,200.00 |
73,600.00 |
2,800.00 |
64,400.00 |
4,000.00 |
92,000.00 |
| 702-03-F |
catch basins (cb-08)
|
6   |
EACH |
5,200.00 |
31,200.00 |
7,000.00 |
42,000.00 |
4,800.00 |
28,800.00 |
6,000.00 |
36,000.00 |
| 702-03-I |
catch basins (cb-04)
|
12   |
EACH |
1,000.00 |
12,000.00 |
1,850.00 |
22,200.00 |
1,800.00 |
21,600.00 |
1,300.00 |
15,600.00 |
| 702-04-B |
adjusting catch basins
|
3   |
EACH |
500.00 |
1,500.00 |
700.00 |
2,100.00 |
1,000.00 |
3,000.00 |
800.00 |
2,400.00 |
| 703-03 |
perforated pipe underdrains
|
2,938   |
LNFT |
9.00 |
26,442.00 |
7.00 |
20,566.00 |
7.00 |
20,566.00 |
14.00 |
41,132.00 |
| 706-02-C |
concrete drive (6" thick)
|
132.1 |
SQYD |
58.85 |
7,774.09 |
75.00 |
9,907.50 |
75.00 |
9,907.50 |
65.00 |
8,586.50 |
| 706-03-C |
incidental concrete paving (6" thick)
|
228.7 |
SQYD |
64.00 |
14,636.80 |
87.00 |
19,896.90 |
70.00 |
16,009.00 |
45.00 |
10,291.50 |
| 707-01 |
concrete curb
|
3,206.4 |
LNFT |
4.60 |
14,749.44 |
9.35 |
29,979.84 |
8.00 |
25,651.20 |
8.00 |
25,651.20 |
| 707-03 |
combination concrete curb & gutter
|
454.0 |
LNFT |
20.60 |
9,352.40 |
26.25 |
11,917.50 |
28.00 |
12,712.00 |
25.00 |
11,350.00 |
| 708-01 |
right-of-way monument
|
26   |
EACH |
7.50 |
195.00 |
250.00 |
6,500.00 |
110.00 |
2,860.00 |
150.00 |
3,900.00 |
| 708-02 |
right-of-way monument witness post
|
26   |
EACH |
18.75 |
487.50 |
220.00 |
5,720.00 |
60.00 |
1,560.00 |
65.00 |
1,690.00 |
| 710-01 |
flowable fill
|
2   |
CUYD |
110.00 |
220.00 |
400.00 |
800.00 |
250.00 |
500.00 |
150.00 |
300.00 |
| 711-01-C |
riprap (30 lb, 12" thick)
|
25   |
SQYD |
45.00 |
1,125.00 |
125.00 |
3,125.00 |
100.00 |
2,500.00 |
65.00 |
1,625.00 |
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
10,000.00 |
10,000.00 |
9,500.00 |
9,500.00 |
7,500.00 |
7,500.00 |
16,000.00 |
16,000.00 |
| 713-02-E |
temporary pavement markings (24" width)
|
50   |
LNFT |
1.35 |
67.50 |
1.20 |
60.00 |
1.25 |
62.50 |
1.50 |
75.00 |
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
0.750 |
MILE |
355.00 |
266.25 |
353.50 |
265.13 |
340.00 |
255.00 |
400.00 |
300.00 |
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
1.500 |
MILE |
836.00 |
1,254.00 |
353.50 |
530.25 |
780.00 |
1,170.00 |
900.00 |
1,350.00 |
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
1   |
EACH |
55.00 |
55.00 |
88.25 |
88.25 |
52.00 |
52.00 |
60.00 |
60.00 |
| 713-05-B |
temporary pavement legends and symbols (double arrow)
|
1   |
EACH |
88.00 |
88.00 |
117.75 |
117.75 |
84.00 |
84.00 |
100.00 |
100.00 |
| 727-01 |
mobilization
|
lump |
LUMP |
80,000.00 |
80,000.00 |
85,000.00 |
85,000.00 |
80,000.00 |
80,000.00 |
75,000.00 |
75,000.00 |
| 731-02 |
reflectorized raised pavement markers
|
485   |
EACH |
5.61 |
2,720.85 |
6.20 |
3,007.00 |
5.25 |
2,546.25 |
6.00 |
2,910.00 |
| 732-01-E |
plastic pavement striping (24" width)
|
460   |
LNFT |
4.35 |
2,001.00 |
5.30 |
2,438.00 |
4.00 |
1,840.00 |
5.00 |
2,300.00 |
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
2.988 |
MILE |
3,190.00 |
9,531.72 |
2,820.50 |
8,427.65 |
3,000.00 |
8,964.00 |
3,500.00 |
10,458.00 |
| 732-02-C |
plastic pavement striping (solid line) (8" width)
|
0.126 |
MILE |
6,400.00 |
806.40 |
7,051.50 |
888.49 |
6,000.00 |
756.00 |
7,000.00 |
882.00 |
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.121 |
MILE |
825.00 |
924.83 |
942.00 |
1,055.98 |
775.00 |
868.78 |
800.00 |
896.80 |
| 732-03-C |
plastic pavement striping (broken line)(8" width)
|
0.119 |
MILE |
5,230.00 |
622.37 |
1,425.00 |
169.58 |
5,000.00 |
595.00 |
6,000.00 |
714.00 |
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
43   |
EACH |
220.00 |
9,460.00 |
235.50 |
10,126.50 |
210.00 |
9,030.00 |
250.00 |
10,750.00 |
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
4   |
EACH |
240.00 |
960.00 |
294.50 |
1,178.00 |
230.00 |
920.00 |
250.00 |
1,000.00 |
| 732-04-C |
plastic pavement legends & symbols (only)
|
18   |
EACH |
230.00 |
4,140.00 |
241.50 |
4,347.00 |
220.00 |
3,960.00 |
250.00 |
4,500.00 |
| 732-05 |
removal of existing markings
|
1.000 |
MILE |
5,885.00 |
5,885.00 |
5,900.00 |
5,900.00 |
5,500.00 |
5,500.00 |
6,500.00 |
6,500.00 |
| 739-01 |
hydro-seeding
|
1.75 |
ACRE |
1,800.00 |
3,150.00 |
1,300.00 |
2,275.00 |
4,300.00 |
7,525.00 |
3,000.00 |
5,250.00 |
| 740-01 |
construction layout
|
lump |
LUMP |
27,000.00 |
27,000.00 |
40,000.00 |
40,000.00 |
34,000.00 |
34,000.00 |
75,000.00 |
75,000.00 |
| 740-02 |
utility oversight and coordination
|
lump |
LUMP |
3,000.00 |
3,000.00 |
500.00 |
500.00 |
3,500.00 |
3,500.00 |
10,000.00 |
10,000.00 |
| 742-04 |
casing (8" diameter)(concrete)
|
5   |
LNFT |
50.00 |
250.00 |
100.00 |
500.00 |
300.00 |
1,500.00 |
150.00 |
750.00 |
| S-001 |
cleaning existing ditches
|
150   |
LNFT |
6.75 |
1,012.50 |
14.00 |
2,100.00 |
10.50 |
1,575.00 |
10.00 |
1,500.00 |
| S-002 |
saw cutting of portland cement concrete pavement
and/or asphaltic concrete pavement (full depth) |
2,400   |
INFT |
1.50 |
3,600.00 |
5.50 |
13,200.00 |
1.40 |
3,360.00 |
1.50 |
3,600.00 |
| S-003 |
dynamic message sign unit
|
4   |
EACH |
5,600.00 |
22,400.00 |
5,500.00 |
22,000.00 |
8,000.00 |
32,000.00 |
3,000.00 |
12,000.00 |
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,508,076.11 |
|
1,732,990.86 |
|
1,748,831.98 |
|
1,855,698.90 |
|
| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 5 - BOH BROS. CONSTRUCTION CO., LLC. |
- 6 - COMMAND CONSTRUCTION INDUSTRIES LLC |
- 7 - BARBER BROS. CONTRACTING CO., L.L.C |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
125,000.00 |
125,000.00 |
100,000.00 |
100,000.00 |
250,000.00 |
250,000.00 |
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
LUMP |
3,300.00 |
3,300.00 |
50,000.00 |
50,000.00 |
50,000.00 |
50,000.00 |
|
|
| 202-02-D |
removal of concrete walks & drives
|
181   |
SQYD |
7.00 |
1,267.00 |
10.00 |
1,810.00 |
35.00 |
6,335.00 |
|
|
| 202-02-E |
removal of concrete curbs
|
300.0 |
LNFT |
5.00 |
1,500.00 |
4.00 |
1,200.00 |
10.00 |
3,000.00 |
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
1,122.4 |
SQYD |
11.00 |
12,346.40 |
6.00 |
6,734.40 |
10.00 |
11,224.00 |
|
|
| 202-02-01 |
removal of house (sta. 109+70; 3,300 sqft with brick
veneer) |
1   |
EACH |
19,000.00 |
19,000.00 |
10,000.00 |
10,000.00 |
25,000.00 |
25,000.00 |
|
|
| 202-02-02 |
removal of house (sta. 110+40; 2,500 sqft with brick
veneer) |
1   |
EACH |
19,000.00 |
19,000.00 |
10,000.00 |
10,000.00 |
25,000.00 |
25,000.00 |
|
|
| 202-02-03 |
removal of concrete drainage inlet structure (sta.
123+48) |
1   |
EACH |
1,750.00 |
1,750.00 |
250.00 |
250.00 |
10,000.00 |
10,000.00 |
|
|
| 203-02 |
drainage excavation
|
60   |
CUYD |
22.00 |
1,320.00 |
20.00 |
1,200.00 |
100.00 |
6,000.00 |
|
|
| 203-05 |
excavation and embankment
|
lump |
LUMP |
53,000.00 |
53,000.00 |
50,000.00 |
50,000.00 |
150,000.00 |
150,000.00 |
|
|
| 204-02 |
temporary hay or straw bales
|
350   |
EACH |
16.00 |
5,600.00 |
10.00 |
3,500.00 |
20.00 |
7,000.00 |
|
|
| 204-06 |
temporary silt fencing
|
6,300   |
LNFT |
2.00 |
12,600.00 |
2.00 |
12,600.00 |
1.50 |
9,450.00 |
|
|
| 302-02-E |
class ii base course (10" thick)
|
9,815.3 |
SQYD |
26.00 |
255,197.80 |
25.00 |
245,382.50 |
40.00 |
392,612.00 |
|
|
| 304-05 |
lime treatment (type e)
|
150.00 |
TON |
1.00 |
150.00 |
350.00 |
52,500.00 |
300.00 |
45,000.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
20   |
CUYD |
110.00 |
2,200.00 |
200.00 |
4,000.00 |
120.00 |
2,400.00 |
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
100.0 |
CUYD |
90.00 |
9,000.00 |
50.00 |
5,000.00 |
60.00 |
6,000.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
745.5 |
TON |
150.00 |
111,825.00 |
175.00 |
130,462.50 |
120.00 |
89,460.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
369   |
SQYD |
25.00 |
9,225.00 |
25.00 |
9,225.00 |
15.00 |
5,535.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 21   |
CUYD |
1.00 |
- 21.00 |
5.00 |
- 105.00 |
0.00 |
0.00 |
|
|
| 601-01-G |
portland cement concrete pavement (8" thick)
|
8,279.6 |
SQYD |
45.00 |
372,582.00 |
58.00 |
480,216.80 |
60.00 |
496,776.00 |
|
|
| 601-04 |
portland cement concrete pavement coring
|
10   |
EACH |
115.00 |
1,150.00 |
200.00 |
2,000.00 |
300.00 |
3,000.00 |
|
|
| 701-03-F |
storm drain pipe (15" rcp/pcp)
|
863   |
LNFT |
47.00 |
40,561.00 |
60.00 |
51,780.00 |
50.00 |
43,150.00 |
|
|
| 701-03-F/G-01 |
storm drain pipe (15" pcp or 18" cmp)(outfall)
|
11   |
LNFT |
72.00 |
792.00 |
70.00 |
770.00 |
100.00 |
1,100.00 |
|
|
| 701-03-G |
storm drain pipe (18" rcp/pcp)
|
421   |
LNFT |
44.00 |
18,524.00 |
70.00 |
29,470.00 |
55.00 |
23,155.00 |
|
|
| 701-03-I |
storm drain pipe (24" rcp/pcp)
|
744   |
LNFT |
66.00 |
49,104.00 |
75.00 |
55,800.00 |
70.00 |
52,080.00 |
|
|
| 701-04-A |
storm drain pipe arch (15" equiv. rcpa)
|
290   |
LNFT |
67.00 |
19,430.00 |
75.00 |
21,750.00 |
65.00 |
18,850.00 |
|
|
| 701-04-A-01 |
storm drain pipe arch (15" equiv. cmpa)(outfall)
|
138   |
LNFT |
57.00 |
7,866.00 |
80.00 |
11,040.00 |
75.00 |
10,350.00 |
|
|
| 701-04-J |
storm drain pipe arch (60" equiv. rcpa)
|
279   |
LNFT |
275.00 |
76,725.00 |
250.00 |
69,750.00 |
300.00 |
83,700.00 |
|
|
| 701-04-L |
storm drain pipe arch (72" equiv. rcpa)
|
102   |
LNFT |
350.00 |
35,700.00 |
300.00 |
30,600.00 |
450.00 |
45,900.00 |
|
|
| 701-05-G |
side drain pipe (18")
|
52   |
LNFT |
57.00 |
2,964.00 |
60.00 |
3,120.00 |
120.00 |
6,240.00 |
|
|
| 701-09 |
fabricating pipe fittings
|
1   |
EACH |
1,800.00 |
1,800.00 |
2,500.00 |
2,500.00 |
2,000.00 |
2,000.00 |
|
|
| 702-02 |
manholes (mh-12.5x9)
|
1   |
EACH |
14,000.00 |
14,000.00 |
4,000.00 |
4,000.00 |
25,000.00 |
25,000.00 |
|
|
| 702-03 |
catch basins (cb-sd08)
|
1   |
EACH |
16,500.00 |
16,500.00 |
7,500.00 |
7,500.00 |
25,000.00 |
25,000.00 |
|
|
| 702-03-A |
catch basins (cb-01)
|
2   |
EACH |
3,600.00 |
7,200.00 |
2,500.00 |
5,000.00 |
3,500.00 |
7,000.00 |
|
|
| 702-03-C |
catch basins (cb-06)
|
23   |
EACH |
3,800.00 |
87,400.00 |
3,500.00 |
80,500.00 |
4,000.00 |
92,000.00 |
|
|
| 702-03-F |
catch basins (cb-08)
|
6   |
EACH |
4,400.00 |
26,400.00 |
6,000.00 |
36,000.00 |
8,000.00 |
48,000.00 |
|
|
| 702-03-I |
catch basins (cb-04)
|
12   |
EACH |
3,300.00 |
39,600.00 |
1,750.00 |
21,000.00 |
2,000.00 |
24,000.00 |
|
|
| 702-04-B |
adjusting catch basins
|
3   |
EACH |
1,200.00 |
3,600.00 |
500.00 |
1,500.00 |
2,500.00 |
7,500.00 |
|
|
| 703-03 |
perforated pipe underdrains
|
2,938   |
LNFT |
15.00 |
44,070.00 |
10.00 |
29,380.00 |
10.00 |
29,380.00 |
|
|
| 706-02-C |
concrete drive (6" thick)
|
132.1 |
SQYD |
75.00 |
9,907.50 |
45.00 |
5,944.50 |
65.00 |
8,586.50 |
|
|
| 706-03-C |
incidental concrete paving (6" thick)
|
228.7 |
SQYD |
80.00 |
18,296.00 |
45.00 |
10,291.50 |
150.00 |
34,305.00 |
|
|
| 707-01 |
concrete curb
|
3,206.4 |
LNFT |
8.50 |
27,254.40 |
6.00 |
19,238.40 |
8.00 |
25,651.20 |
|
|
| 707-03 |
combination concrete curb & gutter
|
454.0 |
LNFT |
40.00 |
18,160.00 |
20.00 |
9,080.00 |
35.00 |
15,890.00 |
|
|
| 708-01 |
right-of-way monument
|
26   |
EACH |
165.00 |
4,290.00 |
200.00 |
5,200.00 |
350.00 |
9,100.00 |
|
|
| 708-02 |
right-of-way monument witness post
|
26   |
EACH |
11.00 |
286.00 |
200.00 |
5,200.00 |
400.00 |
10,400.00 |
|
|
| 710-01 |
flowable fill
|
2   |
CUYD |
150.00 |
300.00 |
400.00 |
800.00 |
500.00 |
1,000.00 |
|
|
| 711-01-C |
riprap (30 lb, 12" thick)
|
25   |
SQYD |
117.00 |
2,925.00 |
150.00 |
3,750.00 |
120.00 |
3,000.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
65,000.00 |
65,000.00 |
50,000.00 |
50,000.00 |
100,000.00 |
100,000.00 |
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
50   |
LNFT |
1.00 |
50.00 |
1.00 |
50.00 |
4.00 |
200.00 |
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
0.750 |
MILE |
330.00 |
247.50 |
300.00 |
225.00 |
400.00 |
300.00 |
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
1.500 |
MILE |
330.00 |
495.00 |
300.00 |
450.00 |
350.00 |
525.00 |
|
|
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
1   |
EACH |
82.00 |
82.00 |
100.00 |
100.00 |
85.00 |
85.00 |
|
|
| 713-05-B |
temporary pavement legends and symbols (double arrow)
|
1   |
EACH |
110.00 |
110.00 |
100.00 |
100.00 |
125.00 |
125.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
197,000.00 |
197,000.00 |
250,000.00 |
250,000.00 |
275,000.00 |
275,000.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
485   |
EACH |
5.50 |
2,667.50 |
6.00 |
2,910.00 |
6.00 |
2,910.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
460   |
LNFT |
5.50 |
2,530.00 |
5.00 |
2,300.00 |
6.00 |
2,760.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
2.988 |
MILE |
2,600.00 |
7,768.80 |
2,700.00 |
8,067.60 |
3,000.00 |
8,964.00 |
|
|
| 732-02-C |
plastic pavement striping (solid line) (8" width)
|
0.126 |
MILE |
6,300.00 |
793.80 |
6,700.00 |
844.20 |
6,500.00 |
819.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.121 |
MILE |
880.00 |
986.48 |
800.00 |
896.80 |
1,000.00 |
1,121.00 |
|
|
| 732-03-C |
plastic pavement striping (broken line)(8" width)
|
0.119 |
MILE |
1,320.00 |
157.08 |
1,200.00 |
142.80 |
2,000.00 |
238.00 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
43   |
EACH |
220.00 |
9,460.00 |
200.00 |
8,600.00 |
250.00 |
10,750.00 |
|
|
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
4   |
EACH |
275.00 |
1,100.00 |
250.00 |
1,000.00 |
300.00 |
1,200.00 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
18   |
EACH |
225.00 |
4,050.00 |
200.00 |
3,600.00 |
250.00 |
4,500.00 |
|
|
| 732-05 |
removal of existing markings
|
1.000 |
MILE |
5,500.00 |
5,500.00 |
5,000.00 |
5,000.00 |
6,000.00 |
6,000.00 |
|
|
| 739-01 |
hydro-seeding
|
1.75 |
ACRE |
2,400.00 |
4,200.00 |
1,200.00 |
2,100.00 |
2,000.00 |
3,500.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
55,000.00 |
55,000.00 |
50,000.00 |
50,000.00 |
50,000.00 |
50,000.00 |
|
|
| 740-02 |
utility oversight and coordination
|
lump |
LUMP |
5,000.00 |
5,000.00 |
24,246.00 |
24,246.00 |
15,000.00 |
15,000.00 |
|
|
| 742-04 |
casing (8" diameter)(concrete)
|
5   |
LNFT |
150.00 |
750.00 |
250.00 |
1,250.00 |
200.00 |
1,000.00 |
|
|
| S-001 |
cleaning existing ditches
|
150   |
LNFT |
17.00 |
2,550.00 |
10.00 |
1,500.00 |
20.00 |
3,000.00 |
|
|
| S-002 |
saw cutting of portland cement concrete pavement
and/or asphaltic concrete pavement (full depth) |
2,400   |
INFT |
2.00 |
4,800.00 |
2.00 |
4,800.00 |
2.00 |
4,800.00 |
|
|
| S-003 |
dynamic message sign unit
|
4   |
EACH |
6,000.00 |
24,000.00 |
2,000.00 |
8,000.00 |
5,000.00 |
20,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,984,945.26 |
|
2,123,123.00 |
|
2,758,926.70 |
|
|
|