| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - T. L. WALLACE CONSTRUCTION, INC. |
- 2 - KEY CONSTRUCTORS, INC. |
- 3 - GUINN BROTHERS, LLC. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing & grubbing
|
lump |
LUMP |
10,000.00 |
10,000.00 |
35,000.00 |
35,000.00 |
32,500.00 |
32,500.00 |
|
|
| 202-02-A-01 |
removal of bridge (sta. 100+00; 55' x 20' conc. bridge
w/timber piling) |
1   |
EACH |
5,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
25,000.00 |
25,000.00 |
|
|
| 202-02-A-02 |
removal of bridge (sta. 100+00; 58' x 23' timber
bridge) |
1   |
EACH |
5,000.00 |
5,000.00 |
10,000.00 |
10,000.00 |
20,000.00 |
20,000.00 |
|
|
| 203-04 |
nonplastic embankment
|
66   |
CUYD |
100.00 |
6,600.00 |
105.00 |
6,930.00 |
120.00 |
7,920.00 |
|
|
| 203-05 |
excavation and embankment
|
lump |
LUMP |
50,000.00 |
50,000.00 |
37,000.00 |
37,000.00 |
48,000.00 |
48,000.00 |
|
|
| 204-02 |
temporary hay or straw bales
|
20   |
EACH |
14.00 |
280.00 |
15.00 |
300.00 |
100.00 |
2,000.00 |
|
|
| 204-03 |
temporary slope drains
|
104   |
LNFT |
14.00 |
1,456.00 |
10.00 |
1,040.00 |
10.00 |
1,040.00 |
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
14   |
EACH |
200.00 |
2,800.00 |
120.00 |
1,680.00 |
200.00 |
2,800.00 |
|
|
| 204-06 |
temporary silt fencing
|
1,450   |
LNFT |
2.80 |
4,060.00 |
5.00 |
7,250.00 |
5.00 |
7,250.00 |
|
|
| 302-01 |
class ii base course
|
344.1 |
CUYD |
150.00 |
51,615.00 |
95.00 |
32,689.50 |
100.00 |
34,410.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
4   |
CUYD |
150.00 |
600.00 |
155.00 |
620.00 |
500.00 |
2,000.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
269.2 |
TON |
200.00 |
53,840.00 |
250.00 |
67,300.00 |
300.00 |
80,760.00 |
|
|
| 704-03 |
blocked out guard rail
|
50.0 |
LNFT |
22.00 |
1,100.00 |
20.00 |
1,000.00 |
30.00 |
1,500.00 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
200.0 |
LNFT |
65.00 |
13,000.00 |
55.00 |
11,000.00 |
70.00 |
14,000.00 |
|
|
| 704-09 |
guard rail anchor sections (turndown)
|
100.0 |
LNFT |
60.00 |
6,000.00 |
30.00 |
3,000.00 |
40.00 |
4,000.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
4   |
EACH |
2,400.00 |
9,600.00 |
2,150.00 |
8,600.00 |
2,750.00 |
11,000.00 |
|
|
| 705-01 |
barbed wire fence
|
323   |
LNFT |
15.00 |
4,845.00 |
10.00 |
3,230.00 |
10.00 |
3,230.00 |
|
|
| 711-01-D |
riprap (55 lb,18" thick )
|
559   |
SQYD |
61.00 |
34,099.00 |
60.00 |
33,540.00 |
90.00 |
50,310.00 |
|
|
| 711-02-A |
riprap (2 lb)
|
7   |
CUYD |
200.00 |
1,400.00 |
330.00 |
2,310.00 |
200.00 |
1,400.00 |
|
|
| 711-02-C |
riprap (30 lb)
|
8   |
CUYD |
200.00 |
1,600.00 |
335.00 |
2,680.00 |
300.00 |
2,400.00 |
|
|
| 711-02-D |
riprap (55 lb)
|
19   |
CUYD |
200.00 |
3,800.00 |
195.00 |
3,705.00 |
300.00 |
5,700.00 |
|
|
| 711-04 |
geotextile fabric
|
628   |
SQYD |
3.00 |
1,884.00 |
3.75 |
2,355.00 |
5.00 |
3,140.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
20,830.00 |
20,830.00 |
40,000.00 |
40,000.00 |
26,000.00 |
26,000.00 |
|
|
| 716-01-A |
mulch (vegetative)
|
1.6 |
TON |
700.00 |
1,120.00 |
895.00 |
1,432.00 |
2,000.00 |
3,200.00 |
|
|
| 717-01 |
seeding
|
34   |
LB |
10.00 |
340.00 |
9.00 |
306.00 |
20.00 |
680.00 |
|
|
| 718-01 |
fertilizer
|
760   |
LB |
0.65 |
494.00 |
0.95 |
722.00 |
3.00 |
2,280.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
50,000.00 |
50,000.00 |
200,000.00 |
200,000.00 |
115,000.00 |
115,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
12   |
EACH |
75.00 |
900.00 |
75.00 |
900.00 |
100.00 |
1,200.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
5,000.00 |
5,000.00 |
45,000.00 |
45,000.00 |
20,000.00 |
20,000.00 |
|
|
| 803-03 |
steel sheet pile wall
|
2,319   |
SQFT |
50.00 |
115,950.00 |
60.00 |
139,140.00 |
60.00 |
139,140.00 |
|
|
| 804-01-B |
precast concrete piles (14")
|
1,665   |
LNFT |
45.00 |
74,925.00 |
65.00 |
108,225.00 |
52.00 |
86,580.00 |
|
|
| 804-12 |
loading permanent piles
|
2   |
EACH |
3,500.00 |
7,000.00 |
5,000.00 |
10,000.00 |
1.00 |
2.00 |
|
|
| 805-10-A |
bridge superstructure & substructure (24' clr. rdwy.
90deg x-ing) |
4   |
SPAN |
42,000.00 |
168,000.00 |
32,000.00 |
128,000.00 |
46,000.00 |
184,000.00 |
|
|
| 805-10-B |
bridge superstructure & substructure (28' clr. rdwy.
90deg x-ing , precast only) |
4   |
SPAN |
45,000.00 |
180,000.00 |
37,000.00 |
148,000.00 |
48,000.00 |
192,000.00 |
|
|
| S-101 |
concrete approach slabs(24'clr. roadway;90 degree
x-ing;without asphalt) |
2   |
EACH |
25,000.00 |
50,000.00 |
13,500.00 |
27,000.00 |
11,500.00 |
23,000.00 |
|
|
| S-102 |
concrete approach slabs(28'clr. roadway;90 degree
x-ing;without asphalt) |
2   |
EACH |
25,000.00 |
50,000.00 |
14,000.00 |
28,000.00 |
12,500.00 |
25,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
993,138.00 |
|
1,157,954.50 |
|
1,178,442.00 |
|
|
|