Letting of 4/30/2008 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 193-06-0032
Parish: CALCASIEU
Routes: LA 14, I-210
Description: I-210 AT LA14 EB ON-RAMP MODIFICATION & RIGHT TURN LANES
Type Const: grading, drainage structures, lime treatment, class ii base course, portland cement
concrete pavement and related work.
Estimated Construction Cost: $837,233.50
 
RankLicenseBidderConstruction Bid
1 36384 JOHN BAILEY, INC. $1,268,254.96
2 12312 GILCHRIST CONSTRUCTION CO. LLC $1,312,795.55
 
Item Number Item Description Quantity Unit of Measure - 1 -
JOHN BAILEY, INC.
- 2 -
GILCHRIST CONSTRUCTION CO. LLC

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 50,000.00 50,000.00 65,000.00 65,000.00        
202-02-E removal of concrete curbs 554.9    LNFT 12.00 6,658.80 9.00 4,994.10        
202-02-F removal of concrete combination curb & gutter 478.0    LNFT 15.00 7,170.00 11.00 5,258.00        
202-02-I removal of signs and supports 2      EACH 250.00 500.00 2,400.00 4,800.00        
202-02-J removal of concrete headwall (sta.19+11.74 to
sta.19+63.25)
1      EACH 6,500.00 6,500.00 8,500.00 8,500.00        
202-03-A relocation of traffic control pedestal 1      EACH 35,280.00 35,280.00 35,000.00 35,000.00        
202-03-B relocation of gas valve 1      EACH 2,500.00 2,500.00 650.00 650.00        
203-05 excavation & embankment lump      LUMP 75,000.00 75,000.00 100,000.00 100,000.00        
204-05-A temporary sediment check dams (hay) 5      EACH 200.00 1,000.00 300.00 1,500.00        
204-06 temporary silt fencing 1,360      LNFT 4.50 6,120.00 2.00 2,720.00        
302-02-A class ii base course (4" thick crushed stone) 3,768.2    SQYD 15.00 56,523.00 14.00 52,754.80        
302-02-C class ii base course (8" thick soil cement) 3,768.2    SQYD 23.00 86,668.60 16.00 60,291.20        
304-01 lime 53.98   TON 200.00 10,796.00 180.00 9,716.40        
304-04-D lime treatment (type d) (12" thick) 3,808      SQYD 9.00 34,272.00 7.50 28,560.00        
601-01-K portland cement concrete pavement (10" thick) 3,611.4    SQYD 95.00 343,083.00 85.00 306,969.00        
601-04 portland cement concrete pavement coring 5      EACH 270.00 1,350.00 130.00 650.00        
701-03-G storm drain pipe (18" rcp/pcp) 64      LNFT 145.00 9,280.00 170.00 10,880.00        
701-04-L storm drain pipe arch (72" equiv. rcpa) 200      LNFT 455.00 91,000.00 575.00 115,000.00        
701-10-O reinforced concrete pipe (extension)(48") 20      LNFT 360.00 7,200.00 435.00 8,700.00        
701-10-Q reinforced concrete pipe (extension)(60") 20      LNFT 456.00 9,120.00 535.00 10,700.00        
702-02-A manholes (mh-06) 1      EACH 9,600.00 9,600.00 15,000.00 15,000.00        
702-02-C manholes (r-cb-11 mod) 2      EACH 9,600.00 19,200.00 15,000.00 30,000.00        
702-03-B catch basins (cb-02) 2      EACH 5,400.00 10,800.00 6,000.00 12,000.00        
702-03-C catch basins (cb-06) 3      EACH 4,800.00 14,400.00 5,000.00 15,000.00        
702-04-A adjusting manholes 1      EACH 2,160.00 2,160.00 2,300.00 2,300.00        
702-04-B adjusting catch basins 4      EACH 3,000.00 12,000.00 3,200.00 12,800.00        
704-03 blocked out guard rail 12.5    LNFT 100.00 1,250.00 50.00 625.00        
704-08-B guard rail transitions (double thrie beam) 25.0    LNFT 100.00 2,500.00 80.00 2,000.00        
704-11-A guard rail end treatment (flared) 1      EACH 150.00 150.00 3,200.00 3,200.00        
706-03-C incidental concrete paving (6" thick) 633.9    SQYD 85.00 53,881.50 58.00 36,766.20        
707-01 concrete curb 1,157.2    LNFT 15.00 17,358.00 2.75 3,182.30        
708-01 right-of-way monument 2      EACH 250.00 500.00 380.00 760.00        
711-01-C riprap (30 lb, 14in) 155      SQYD 80.00 12,400.00 78.00 12,090.00        
713-01 temporary signs & barricades lump      LUMP 50,000.00 50,000.00 65,000.00 65,000.00        
722-01 project site laboratory 1      EACH 25,000.00 25,000.00 23,000.00 23,000.00        
727-01 mobilization lump      LUMP 85,000.00 85,000.00 120,000.00 120,000.00        
730-15 relocate light poles (10" & wood) 2      EACH 3,500.00 7,000.00 4,500.00 9,000.00        
731-02 reflectorized raised pavement markers 56      EACH 7.32 409.92 8.00 448.00        
732-01-E plastic pavement striping (24" width) 9      LNFT 5.10 45.90 5.50 49.50        
732-02-A plastic pavement striping (solid line) (4" width) 0.519  MILE 3,540.00 1,837.26 3,900.00 2,024.10        
732-02-C plastic pavement striping (solid line) (8" width) 0.070  MILE 7,692.00 538.44 8,400.00 588.00        
732-03-A plastic pavement striping (broken line)(4" width) 0.068  MILE 955.00 64.94 1,000.00 68.00        
732-04-A plastic pavement legends & symbols (arrow) 2      EACH 210.00 420.00 230.00 460.00        
732-04-B plastic pavement legends & symbols (double arrow) 1      EACH 234.00 234.00 250.00 250.00        
732-04-C plastic pavement legends & symbols (only) 1      EACH 174.00 174.00 185.00 185.00        
733-01 concrete roadway barrier (single faced) 100.0    LNFT 630.00 63,000.00 335.00 33,500.00        
740-01 construction layout lump      LUMP 10,000.00 10,000.00 50,000.00 50,000.00        
741-08 relocating water meter 1      EACH 2,500.00 2,500.00 650.00 650.00        
805-01-A class a concrete (pipe headwalls) 14.30   CUYD 1,200.00 17,160.00 1,300.00 18,590.00        
806-01 deformed reinforcing steel 861      LB 3.60 3,099.60 3.95 3,400.95        
S-001 saw cutting porland cement concrete pavement (8" thick) 555      LNFT 10.00 5,550.00 13.00 7,215.00        
                       
 CONTRACTOR TOTAL       1,268,254.96   1,312,795.55        