Letting of 4/30/2008 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 103-01-0025
Parish: CADDO
Routes: LA 523
Description: JCT. EXISTING 5-LANE TO JCT. LA 1
Type Const: grading, drain struc, class ii bc, lime trmt, superpave acp, pccp, traffic signals,
slab span bridges, and related work.
Estimated Construction Cost: $19,887,946.05
Maximum Number of Days Allowed for Construction: 1050
Calculated Daily User Cost: $1,000.00
 
RankLicenseBidderConstruction Bid Bidder's Proposed
Contract Time
Total Bid
1 12312 GILCHRIST CONSTRUCTION CO. LLC $23,348,707.83 650 $23,998,707.83
2 12135 BLOUNT BROS. CONSTRUCTION, INC. $24,289,359.43 750 $25,039,359.43
3 42076 AUSTIN BRIDGE & ROAD, LP $25,311,464.99 750 $26,061,464.99
4 39462 DENTON-JAMES LLC $25,647,379.90 1050 $26,697,379.90
5 34567 JAMES CONSTRUCTION GROUP LLC $26,654,966.20 850 $27,504,966.20
 
Item Number Item Description Quantity Unit of Measure - 1 -
GILCHRIST CONSTRUCTION CO. LLC
- 2 -
BLOUNT BROS. CONSTRUCTION, INC.
- 3 -
AUSTIN BRIDGE & ROAD, LP
- 4 -
DENTON-JAMES LLC
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 650,000.00 650,000.00 550,000.00 550,000.00 125,000.00 125,000.00 800,000.00 800,000.00
202-01 removal of structures & obstructions lump      LUMP 60,000.00 60,000.00 400,000.00 400,000.00 100,000.00 100,000.00 220,000.00 220,000.00
202-02-A-01 removal of bridge (32' x 190' concrete slab span) 1      EACH 25,000.00 25,000.00 75,000.00 75,000.00 50,000.00 50,000.00 20,000.00 20,000.00
202-02-A-02 removal of bridge (35' x 152' concrete slab span) 1      EACH 20,000.00 20,000.00 65,000.00 65,000.00 50,000.00 50,000.00 20,000.00 20,000.00
202-02-C removal of portland cement concrete pavement 5,757      SQYD 7.50 43,177.50 6.00 34,542.00 5.29 30,454.53 6.50 37,420.50
202-02-D removal of concrete walks & drives 4,645      SQYD 7.00 32,515.00 6.00 27,870.00 7.07 32,840.15 11.00 51,095.00
202-02-G removal of surfacing & stabilized base 36,384.2    SQYD 7.00 254,689.40 4.00 145,536.80 2.52 91,688.18 5.00 181,921.00
202-02-H removal of guard rail 1,830      LNFT 14.00 25,620.00 2.00 3,660.00 3.72 6,807.60 4.00 7,320.00
202-02-I removal of signal equipment/related items lump      LUMP 4,500.00 4,500.00 5,000.00 5,000.00 7,488.37 7,488.37 5,000.00 5,000.00
202-02-J removal of residential septic system 1      EACH 1,000.00 1,000.00 1.00 1.00 2,430.78 2,430.78 5,000.00 5,000.00
202-02-K-01 removal of sign (sta 128+50 lt, 5' x 2' metal) 1      EACH 200.00 200.00 1.00 1.00 665.36 665.36 1.00 1.00
202-02-K-02 removal of sign (sta 131+50 lt, 3' x 10' wood) 1      EACH 500.00 500.00 1.00 1.00 856.10 856.10 1.00 1.00
202-02-K-03 removal of sign (sta 131+50 rt, 4' x 8' wood) 1      EACH 500.00 500.00 1.00 1.00 816.15 816.15 1.00 1.00
202-02-K-04 removal of sign (sta 139+50 rt, 4' x 7' brick) 1      EACH 800.00 800.00 1.00 1.00 1,046.81 1,046.81 1.00 1.00
202-02-K-05 removal of sign (sta 232+90 rt, 12' x 16' brick) 1      EACH 2,500.00 2,500.00 1.00 1.00 1,508.14 1,508.14 1.00 1.00
202-02-K-06 removal of light pole(sta 232+90 rt, 12' metal pole
with camera)
1      EACH 250.00 250.00 1.00 1.00 2,502.12 2,502.12 1.00 1.00
202-02-K-07 removal of fence (sta 235+90 rt, brick fence) 260      LNFT 40.00 10,400.00 1.00 260.00 18.22 4,737.20 8.00 2,080.00
202-02-K-08 removal of sign (sta 236+05 lt, 3' x 15' brick) 1      EACH 400.00 400.00 1.00 1.00 1,428.23 1,428.23 1.00 1.00
202-02-K-09 removal of brick columns and entry gate (sta 236+05 lt) lump      LUMP 4,800.00 4,800.00 1.00 1.00 2,927.33 2,927.33 1.00 1.00
202-02-K-10 removal of brick walls (sta 236+05 lt, 2-3' high
subdivision entrance)
lump      LUMP 1,200.00 1,200.00 1.00 1.00 4,337.90 4,337.90 1.00 1.00
202-02-K-11 removal of light pole (sta 236+10 lt, 10' metal pole) 1      EACH 280.00 280.00 1.00 1.00 1,871.53 1,871.53 1.00 1.00
202-02-K-12 removal of sign (sta 266+20 lt, 6' x 8' brick) 1      EACH 1,600.00 1,600.00 1.00 1.00 1,508.14 1,508.14 1.00 1.00
202-02-K-13 removal of sign (sta 289+55 lt, 13' x 6' x 4' wood) 1      EACH 400.00 400.00 1.00 1.00 1,508.14 1,508.14 1.00 1.00
203-01 general excavation 59,706      CUYD 4.75 283,603.50 7.00 417,942.00 6.27 374,356.62 11.00 656,766.00
203-02 drainage excavation 2,940      CUYD 8.00 23,520.00 12.00 35,280.00 14.92 43,864.80 12.00 35,280.00
203-03 embankment 86,452      CUYD 10.00 864,520.00 12.00 1,037,424.00 17.00 1,469,684.00 16.00 1,383,232.00
204-02 temporary hay or straw bales 150      EACH 20.00 3,000.00 12.00 1,800.00 8.50 1,275.00 9.00 1,350.00
204-05-A temporary sediment check dams (hay) 135      EACH 300.00 40,500.00 100.00 13,500.00 100.00 13,500.00 100.00 13,500.00
204-05-B temporary sediment check dams (stone) 15      EACH 1,100.00 16,500.00 1,500.00 22,500.00 1,362.79 20,441.85 700.00 10,500.00
204-06 temporary silt fencing 24,000      LNFT 2.50 60,000.00 2.50 60,000.00 1.45 34,800.00 2.00 48,000.00
204-07 temporary stone construction entrance 2      EACH 4,400.00 8,800.00 2,500.00 5,000.00 6,598.82 13,197.64 2,500.00 5,000.00
302-01 class ii base course 20,882.5    CUYD 80.00 1,670,600.00 70.00 1,461,775.00 79.80 1,666,423.50 110.00 2,297,075.00
304-01 lime 1,478.93   TON 155.00 229,234.15 145.00 214,444.85 155.98 230,683.50 130.00 192,260.90
304-04-D lime treatment (type d) (12" thick) 104,332      SQYD 1.50 156,498.00 3.50 365,162.00 4.09 426,717.88 1.50 156,498.00
402-01 traffic maintenance aggregate (vehicular measurement) 2,000.0    CUYD 115.00 230,000.00 50.00 100,000.00 46.45 92,900.00 80.00 160,000.00
502-01 superpave asphaltic concrete 12,762.9    TON 130.00 1,659,177.00 110.00 1,403,919.00 103.34 1,318,918.09 110.00 1,403,919.00
601-01-G portland cement concrete pavement (8" thick) 101,139.4    SQYD 44.00 4,450,133.60 57.00 5,764,945.80 63.00 6,371,782.20 50.00 5,056,970.00
601-01-K portland cement concrete pavement (10" thick) 3,565.2    SQYD 50.00 178,260.00 62.00 221,042.40 70.32 250,704.86 68.00 242,433.60
601-02-G portland cement concrete pavement (8" thick)
(crossovers & turnouts)
2,262.7    SQYD 55.00 124,448.50 60.00 135,762.00 67.62 153,003.77 65.00 147,075.50
601-03-C portland cement concrete shoulder (6" thick) 693.6    SQYD 55.00 38,148.00 55.00 38,148.00 63.77 44,230.87 92.00 63,811.20
701-01-I cross drain pipe (24" rcp/pcp) 168      LNFT 108.00 18,144.00 56.00 9,408.00 60.00 10,080.00 90.00 15,120.00
701-01-M cross drain pipe (36" rcp/pcp) 458      LNFT 210.00 96,180.00 75.00 34,350.00 100.00 45,800.00 130.00 59,540.00
701-01-N cross drain pipe (42" rcp/pcp) 908      LNFT 230.00 208,840.00 110.00 99,880.00 140.00 127,120.00 180.00 163,440.00
701-01-Q cross drain pipe (60" rcp/pcp) 46      LNFT 500.00 23,000.00 240.00 11,040.00 250.00 11,500.00 270.00 12,420.00
701-03-F storm drain pipe (15" rcp/pcp) 3,762      LNFT 50.00 188,100.00 37.00 139,194.00 52.00 195,624.00 55.00 206,910.00
701-03-G storm drain pipe (18" rcp/pcp) 1,595      LNFT 65.00 103,675.00 45.00 71,775.00 60.00 95,700.00 60.00 95,700.00
701-03-I storm drain pipe (24" rcp/pcp) 1,031      LNFT 90.00 92,790.00 56.00 57,736.00 70.00 72,170.00 75.00 77,325.00
701-05-G side drain pipe (18") 548      LNFT 50.00 27,400.00 45.00 24,660.00 60.00 32,880.00 55.00 30,140.00
701-05-I side drain pipe (24") 744      LNFT 65.00 48,360.00 56.00 41,664.00 70.00 52,080.00 65.00 48,360.00
701-05-I-01 side drain pipe (24")(erosion) 200      LNFT 75.00 15,000.00 56.00 11,200.00 70.00 14,000.00 65.00 13,000.00
701-05-K side drain pipe (30") 256      LNFT 80.00 20,480.00 67.00 17,152.00 76.00 19,456.00 80.00 20,480.00
701-05-M side drain pipe (36") 64      LNFT 120.00 7,680.00 75.00 4,800.00 105.00 6,720.00 100.00 6,400.00
701-05-M-01 side drain pipe (36")(erosion) 40      LNFT 125.00 5,000.00 75.00 3,000.00 105.00 4,200.00 100.00 4,000.00
701-05-N side drain pipe (42") 60      LNFT 130.00 7,800.00 110.00 6,600.00 140.00 8,400.00 140.00 8,400.00
702-02-A-01 manholes (mh-06)(type a grate) 1      EACH 8,000.00 8,000.00 5,000.00 5,000.00 5,500.00 5,500.00 5,000.00 5,000.00
702-02-B manholes (r-cb-11) 1      EACH 7,000.00 7,000.00 5,000.00 5,000.00 6,000.00 6,000.00 5,000.00 5,000.00
702-03-A catch basins (cb-01) 6      EACH 2,300.00 13,800.00 5,000.00 30,000.00 2,000.00 12,000.00 3,000.00 18,000.00
702-03-C catch basins (cb-06) 57      EACH 4,300.00 245,100.00 4,500.00 256,500.00 3,000.00 171,000.00 4,400.00 250,800.00
702-03-D catch basins (cb-07) 2      EACH 5,800.00 11,600.00 5,500.00 11,000.00 4,000.00 8,000.00 5,500.00 11,000.00
702-03-F catch basins (cb-08) 20      EACH 8,000.00 160,000.00 5,500.00 110,000.00 6,000.00 120,000.00 7,000.00 140,000.00
702-04-A adjusting manholes 5      EACH 1,500.00 7,500.00 1,500.00 7,500.00 1,500.00 7,500.00 1,400.00 7,000.00
703-02 shoulder outlet underdrains 2      EACH 1,700.00 3,400.00 500.00 1,000.00 785.53 1,571.06 700.00 1,400.00
703-03 perforated pipe underdrains (4" pvc) 23,810      LNFT 12.75 303,577.50 12.00 285,720.00 17.91 426,437.10 9.00 214,290.00
705-01 barbed wire fence 5,385      LNFT 6.40 34,464.00 5.50 29,617.50 5.98 32,202.30 6.00 32,310.00
705-02 combination mesh & barbed wire fence 183      LNFT 7.80 1,427.40 11.00 2,013.00 7.37 1,348.71 8.00 1,464.00
705-05 double swinging driveway gates 4      DBGT 800.00 3,200.00 880.00 3,520.00 747.77 2,991.08 700.00 2,800.00
705-06-A chain link fence (4-foot height) 130      LNFT 20.00 2,600.00 22.00 2,860.00 19.23 2,499.90 20.00 2,600.00
705-06-C chain link fence (6-foot height) 301      LNFT 30.00 9,030.00 22.00 6,622.00 27.77 8,358.77 28.00 8,428.00
705-06-D chain link fence (7-foot height) 1,864      LNFT 35.00 65,240.00 24.00 44,736.00 36.32 67,700.48 35.00 65,240.00
705-08-C 10-foot double gates for chain link fence (6-foot
height)
1      DBGT 1,600.00 1,600.00 880.00 880.00 1,548.95 1,548.95 1,500.00 1,500.00
705-09 rebuilt fence 557      LNFT 174.00 96,918.00 113.00 62,941.00 84.39 47,005.23 120.00 66,840.00
706-02-C concrete drive (6" thick) 6,101.4    SQYD 44.00 268,461.60 50.00 305,070.00 58.68 358,030.15 48.00 292,867.20
706-03-A incidental concrete paving (4" thick) 4,979.7    SQYD 50.00 248,985.00 45.00 224,086.50 35.35 176,032.40 42.00 209,147.40
707-01 concrete curb 31,994.9    LNFT 2.25 71,988.53 6.00 191,969.40 2.36 75,507.96 9.00 287,954.10
708-01 right-of-way monument 131      EACH 340.00 44,540.00 300.00 39,300.00 139.34 18,253.54 120.00 15,720.00
708-02 right-of-way monument witness post 131      EACH 340.00 44,540.00 150.00 19,650.00 96.03 12,579.93 120.00 15,720.00
711-01-D riprap (55 lb, 24"thick) 237      SQYD 75.00 17,775.00 60.00 14,220.00 112.75 26,721.75 80.00 18,960.00
711-04 geotextile fabric 237      SQYD 4.00 948.00 3.00 711.00 4.16 985.92 1.00 237.00
712-04 flexible revetment 3,113      SQYD 65.00 202,345.00 65.00 202,345.00 83.30 259,312.90 48.00 149,424.00
713-01 temporary signs & barricades lump      LUMP 300,000.00 300,000.00 175,000.00 175,000.00 106,000.00 106,000.00 400,000.00 400,000.00
713-04-A-01 temporary pavement markings (solid line)(4" width)
(type i removable)
22.474  MILE 11,000.00 247,214.00 11,550.00 259,574.70 10,500.00 235,977.00 11,000.00 247,214.00
713-07 temporary precast concrete barrier (contractor
furnished)
28      EACH 1,000.00 28,000.00 1,000.00 28,000.00 1,172.18 32,821.04 600.00 16,800.00
716-01-B mulch (fiber) 31.96   TON 1,200.00 38,352.00 900.00 28,764.00 1,000.00 31,960.00 1,000.00 31,960.00
717-01 seeding 1,918      LB 9.00 17,262.00 12.00 23,016.00 8.00 15,344.00 8.00 15,344.00
718-01 fertilizer 31,960      LB 0.50 15,980.00 0.75 23,970.00 0.32 10,227.20 0.34 10,866.40
720-01-A erosion control system, slope protection (type a) 667      SQYD 1.50 1,000.50 2.50 1,667.50 1.40 933.80 1.50 1,000.50
720-01-D erosion control system, flexible channel liner (type d) 23,197      SQYD 2.15 49,873.55 3.00 69,591.00 1.90 44,074.30 2.00 46,394.00
722-02 project site laboratory (equipped) 1      EACH 100,000.00 100,000.00 65,000.00 65,000.00 200,000.00 200,000.00 30,000.00 30,000.00
725-01 temporary detour roads 3,700.0    SQYD 80.00 296,000.00 75.00 277,500.00 100.00 370,000.00 85.00 314,500.00
726-01 bedding material 1,122.8    CUYD 80.00 89,824.00 80.00 89,824.00 78.00 87,578.40 85.00 95,438.00
727-01 mobilization lump      LUMP 2,300,000.00 2,300,000.00 1,400,000.00 1,400,000.00 2,256,000.00 2,256,000.00 2,500,000.00 2,500,000.00
729-01 sign (type a) 416.9    SQFT 30.00 12,507.00 45.00 18,760.50 30.00 12,507.00 30.00 12,507.00
729-02 sign (type b) 173.6    SQFT 30.00 5,208.00 40.00 6,944.00 30.00 5,208.00 35.00 6,076.00
729-16-C object marker assembly (type 3) 4      EACH 90.00 360.00 110.00 440.00 125.00 500.00 80.00 320.00
731-02 reflectorized raised pavement markers 2,250      EACH 5.50 12,375.00 5.30 11,925.00 4.80 10,800.00 5.00 11,250.00
732-02-A plastic pavement striping (solid line) (4" width) 11.687  MILE 2,400.00 28,048.80 2,375.00 27,756.63 2,150.00 25,127.05 2,200.00 25,711.40
732-02-C plastic pavement striping (solid line) (8" width) 0.202  MILE 5,000.00 1,010.00 4,950.00 999.90 4,488.02 906.58 4,500.00 909.00
732-02-E plastic pavement striping (solid line) (24" width) 0.183  MILE 12,000.00 2,196.00 12,200.00 2,232.60 11,087.98 2,029.10 11,000.00 2,013.00
732-03-A plastic pavement striping (broken line)(4" width) 10.560  MILE 800.00 8,448.00 770.00 8,131.20 700.00 7,392.00 700.00 7,392.00
732-04-A plastic pavement legends & symbols (arrow) 89      EACH 150.00 13,350.00 145.00 12,905.00 130.00 11,570.00 150.00 13,350.00
732-04-B plastic pavement legends & symbols (double arrow) 2      EACH 170.00 340.00 165.00 330.00 150.00 300.00 170.00 340.00
732-04-C plastic pavement legends & symbols (only) 14      EACH 160.00 2,240.00 155.00 2,170.00 140.00 1,960.00 170.00 2,380.00
732-04-D plastic pavement legends & symbols (rr crossing) 2      EACH 400.00 800.00 385.00 770.00 350.00 700.00 400.00 800.00
732-05 removal of existing markings 0.250  MILE 6,000.00 1,500.00 5,800.00 1,450.00 5,280.00 1,320.00 6,000.00 1,500.00
736-01 trenching and backfilling 2,165      LNFT 2.20 4,763.00 2.20 4,763.00 6.07 13,141.55 6.00 12,990.00
736-03-A jacked or bored conduit (1" p.e.c.) 495      LNFT 15.00 7,425.00 14.50 7,177.50 17.09 8,459.55 16.00 7,920.00
736-03-B jacked or bored conduit (2" p.e.c.) 445      LNFT 23.00 10,235.00 22.00 9,790.00 21.36 9,505.20 20.00 8,900.00
736-03-C jacked or bored conduit (3" p.e.c.) 350      LNFT 25.00 8,750.00 24.00 8,400.00 30.35 10,622.50 30.00 10,500.00
736-04-A signal support (mast arm standard w/30' arm) 1      EACH 13,500.00 13,500.00 13,090.00 13,090.00 9,196.92 9,196.92 8,500.00 8,500.00
736-04-B signal support (mast arm standard w/40' arm) 3      EACH 14,000.00 42,000.00 13,640.00 40,920.00 10,284.99 30,854.97 10,000.00 30,000.00
736-04-C signal support (mast arm standard w/45' arm) 1      EACH 15,000.00 15,000.00 14,740.00 14,740.00 10,944.80 10,944.80 11,000.00 11,000.00
736-04-D signal support (mast arm standard w/50' arm) 3      EACH 16,000.00 48,000.00 15,840.00 47,520.00 11,718.14 35,154.42 11,000.00 33,000.00
736-04-E signal support (mast arm standard w/35' & 40' arms) 1      EACH 18,000.00 18,000.00 17,875.00 17,875.00 12,776.99 12,776.99 12,000.00 12,000.00
736-05-A signal heads (3-section, r, y, g)(l.e.d) 15      EACH 1,200.00 18,000.00 1,210.00 18,150.00 1,203.85 18,057.75 1,100.00 16,500.00
736-05-B signal heads (3-section, r, lty, ltg)(l.e.d) 2      EACH 1,200.00 2,400.00 1,170.00 2,340.00 1,207.22 2,414.44 1,100.00 2,200.00
736-05-C signal heads (5-section, r, lty, y, ltg, g)(l.e.d) 3      EACH 1,900.00 5,700.00 1,810.00 5,430.00 1,824.32 5,472.96 1,700.00 5,100.00
736-05-D signal heads (programmable 3-section, r, y, g)(l.e.d) 1      EACH 3,600.00 3,600.00 3,465.00 3,465.00 2,461.65 2,461.65 2,200.00 2,200.00
736-05-E signal heads (programmable 5-section, r, lty, y, ltg,
g)(l.e.d)
2      EACH 5,700.00 11,400.00 5,500.00 11,000.00 2,787.63 5,575.26 2,800.00 5,600.00
736-05-F signal heads (programmable 5-section, r, rty, y, rtg,
g)(l.e.d)
1      EACH 5,700.00 5,700.00 5,500.00 5,500.00 2,787.63 2,787.63 2,800.00 2,800.00
736-06-A signal service 2      EACH 2,300.00 4,600.00 2,200.00 4,400.00 1,798.47 3,596.94 1,700.00 3,400.00
736-06-B signal service (pedestal mounted) 2      EACH 2,300.00 4,600.00 2,200.00 4,400.00 2,324.52 4,649.04 2,400.00 4,800.00
736-08 signal controller 2      EACH 23,000.00 46,000.00 21,670.00 43,340.00 25,852.98 51,705.96 25,000.00 50,000.00
736-09 loop detector 548      LNFT 20.00 10,960.00 20.00 10,960.00 14.05 7,699.40 14.00 7,672.00
736-10-A underground junction box (type "e") 8      EACH 400.00 3,200.00 385.00 3,080.00 492.33 3,938.64 500.00 4,000.00
736-10-B underground junction box (type "f") 12      EACH 520.00 6,240.00 495.00 5,940.00 620.47 7,445.64 600.00 7,200.00
736-10-C underground junction box (type "h") 2      EACH 1,200.00 2,400.00 1,210.00 2,420.00 1,195.98 2,391.96 1,100.00 2,200.00
736-11-A conduit (1/2" p.e.c. schedule 80) 100      LNFT 4.00 400.00 3.30 330.00 1.71 171.00 1.70 170.00
736-11-B conduit (1" p.e.c. schedule 80) 1,360      LNFT 4.00 5,440.00 3.30 4,488.00 2.47 3,359.20 2.40 3,264.00
736-11-C conduit (2" p.e.c. schedule 80) 120      LNFT 5.75 690.00 5.50 660.00 3.99 478.80 4.00 480.00
736-11-D conduit (3" p.e.c. schedule 80) 545      LNFT 7.50 4,087.50 7.25 3,951.25 4.09 2,229.05 4.00 2,180.00
736-12-A conductor (2c, loop lead-in) 2,980      LNFT 1.25 3,725.00 1.25 3,725.00 1.69 5,036.20 1.60 4,768.00
736-12-B conductor (6c, signal) 777      LNFT 2.90 2,253.30 2.75 2,136.75 2.02 1,569.54 2.00 1,554.00
736-12-C conductor (10c, signal) 4,065      LNFT 2.90 11,788.50 2.75 11,178.75 2.81 11,422.65 2.70 10,975.50
736-12-D conductor (railroad preemption cable) 340      LNFT 3.45 1,173.00 3.30 1,122.00 3.54 1,203.60 3.50 1,190.00
736-12-E conductor (3c, power) 20      LNFT 7.00 140.00 6.60 132.00 3.37 67.40 3.20 64.00
740-01 construction layout lump      LUMP 400,000.00 400,000.00 300,000.00 300,000.00 250,000.00 250,000.00 400,000.00 400,000.00
740-02 utility oversight and coordination lump      LUMP 90,000.00 90,000.00 100,000.00 100,000.00 130,000.00 130,000.00 40,000.00 40,000.00
742-01-A sanitary sewer pipe (6") 12      LNFT 45.00 540.00 44.00 528.00 40.00 480.00 45.00 540.00
742-01-B sanitary sewer pipe (8") 30      LNFT 50.00 1,500.00 49.50 1,485.00 45.00 1,350.00 50.00 1,500.00
742-01-C sanitary sewer pipe (10") 28      LNFT 55.00 1,540.00 55.00 1,540.00 50.00 1,400.00 60.00 1,680.00
742-01-D sanitary sewer pipe (12") 1,661      LNFT 200.00 332,200.00 200.00 332,200.00 179.00 297,319.00 190.00 315,590.00
742-01-E sanitary sewer pipe (15") 1,700      LNFT 375.00 637,500.00 380.00 646,000.00 343.00 583,100.00 370.00 629,000.00
742-01-F sanitary sewer pipe (24") 730      LNFT 400.00 292,000.00 405.00 295,650.00 369.00 269,370.00 400.00 292,000.00
742-01-G sanitary sewer pipe (36") 75      LNFT 480.00 36,000.00 470.00 35,250.00 428.00 32,100.00 470.00 35,250.00
742-05-A abandon manhole 9      EACH 600.00 5,400.00 550.00 4,950.00 500.00 4,500.00 550.00 4,950.00
742-05-B abandon 10" sanitary sewer (+/- 54 lnft) lump      LUMP 600.00 600.00 550.00 550.00 500.00 500.00 550.00 550.00
742-05-C abandon 12" sanitary sewer (+/- 1,655 lnft) lump      LUMP 9,500.00 9,500.00 9,100.00 9,100.00 8,275.00 8,275.00 9,000.00 9,000.00
742-05-D abandon 15" sanitary sewer (+/- 1,695 lnft) lump      LUMP 15,000.00 15,000.00 14,450.00 14,450.00 13,150.00 13,150.00 14,000.00 14,000.00
742-05-E abandon 24" sanitary sewer (+/- 732 lnft) lump      LUMP 16,000.00 16,000.00 15,700.00 15,700.00 14,275.00 14,275.00 15,000.00 15,000.00
742-06-A sanitary sewer manhole (10' - 15' depth) 3      EACH 5,200.00 15,600.00 4,950.00 14,850.00 4,500.00 13,500.00 5,000.00 15,000.00
742-06-B sanitary sewer manhole (15' - 20' depth) 4      EACH 7,500.00 30,000.00 7,150.00 28,600.00 6,500.00 26,000.00 7,000.00 28,000.00
742-06-C sanitary sewer manhole (20' - 25' depth) 3      EACH 9,800.00 29,400.00 9,350.00 28,050.00 8,500.00 25,500.00 9,500.00 28,500.00
742-06-D sanitary sewer manhole (25' - 30' depth) 3      EACH 11,500.00 34,500.00 11,000.00 33,000.00 10,000.00 30,000.00 11,000.00 33,000.00
742-07 de-watering lump      LUMP 500,000.00 500,000.00 522,750.00 522,750.00 475,215.00 475,215.00 600,000.00 600,000.00
742-08 sanitary sewer force main (8") 30      LNFT 60.00 1,800.00 55.00 1,650.00 50.00 1,500.00 55.00 1,650.00
804-01-D precast concrete piles (18") 3,240      LNFT 65.00 210,600.00 140.00 453,600.00 127.67 413,650.80 95.00 307,800.00
804-01-F precast concrete piles (24") 4,290      LNFT 92.00 394,680.00 200.00 858,000.00 186.58 800,428.20 140.00 600,600.00
804-05 precast concrete test piles 1      EACH 20,000.00 20,000.00 17,500.00 17,500.00 13,487.99 13,487.99 25,000.00 25,000.00
804-09 loading test piles 1      EACH 25,000.00 25,000.00 15,000.00 15,000.00 22,945.92 22,945.92 15,000.00 15,000.00
804-10 reloading test piles 1      EACH 1,000.00 1,000.00 3,000.00 3,000.00 16,438.51 16,438.51 1,000.00 1,000.00
804-11 redriving test piles 1      EACH 1,000.00 1,000.00 1,800.00 1,800.00 990.40 990.40 1,000.00 1,000.00
804-12 loading permanent piles 1      EACH 1,000.00 1,000.00 6,000.00 6,000.00 22,945.92 22,945.92 1,000.00 1,000.00
804-17 dynamic monitoring 3      EACH 6,500.00 19,500.00 10,000.00 30,000.00 5,186.39 15,559.17 1,200.00 3,600.00
805-01-A class a concrete (pipe headwalls) 31.40   CUYD 1,500.00 47,100.00 1,000.00 31,400.00 1,350.00 42,390.00 1,500.00 47,100.00
805-01-F class a concrete (bents) 522.02   CUYD 650.00 339,313.00 800.00 417,616.00 931.12 486,063.26 840.00 438,496.80
805-03 class aa concrete 1,217.52   CUYD 700.00 852,264.00 800.00 974,016.00 702.59 855,417.38 540.00 657,460.80
806-01 deformed reinforcing steel 335,899      LB 1.10 369,488.90 1.50 503,848.50 1.11 372,847.89 1.10 369,488.90
810-01 concrete railing (32" barrier) 1,060.66   LNFT 75.00 79,549.50 60.00 63,639.60 80.72 85,616.48 70.00 74,246.20
813-01 concrete approach slabs 1,854.04   SQYD 240.00 444,969.60 220.00 407,888.80 175.59 325,550.88 200.00 370,808.00
S-001 video detection camera device and connection 7      EACH 7,000.00 49,000.00 6,600.00 46,200.00 7,061.23 49,428.61 7,000.00 49,000.00
S-002 video detection camera system 2      EACH 5,000.00 10,000.00 4,840.00 9,680.00 5,018.85 10,037.70 5,000.00 10,000.00
S-003 blank out sign (no left turn) 1      EACH 5,200.00 5,200.00 5,025.00 5,025.00 3,936.40 3,936.40 4,000.00 4,000.00
S-004 blank out sign (no right turn) 1      EACH 5,200.00 5,200.00 5,025.00 5,025.00 3,936.40 3,936.40 4,000.00 4,000.00
S-005 chain link fence (12' height)(1" black mesh) 164      LNFT 160.00 26,240.00 91.00 14,924.00 147.42 24,176.88 80.00 13,120.00
S-006 paved gutter drain (4' wide) 79      EACH 1,800.00 142,200.00 1,500.00 118,500.00 1,866.72 147,470.88 3,000.00 237,000.00
S-007 paved gutter drain (8' wide) 12      EACH 3,000.00 36,000.00 3,000.00 36,000.00 3,202.10 38,425.20 3,600.00 43,200.00
S-102 dynamic analysis 3      EACH 2,500.00 7,500.00 5,000.00 15,000.00 2,326.19 6,978.57 1,200.00 3,600.00
S-103 vibration monitoring lump      LUMP 5,000.00 5,000.00 20,000.00 20,000.00 25,855.00 25,855.00 30,000.00 30,000.00
                       
 ITEM TOTAL (CONSTRUCTION BID)       23,348,707.83   24,289,359.43   25,311,464.99   25,647,379.90
 NUMBER OF DAYS BID AT $1,000 PER DAY.       650,000.00   750,000.00   750,000.00 1050 1,050,000.00
 TOTAL BID       23,998,707.83   25,039,359.43   26,061,464.99   26,697,379.90
 
Item Number Item Description Quantity Unit of Measure - 5 -
JAMES CONSTRUCTION GROUP LLC

 

 

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 1,200,000.00 1,200,000.00            
202-01 removal of structures & obstructions lump      LUMP 120,000.00 120,000.00            
202-02-A-01 removal of bridge (32' x 190' concrete slab span) 1      EACH 125,000.00 125,000.00            
202-02-A-02 removal of bridge (35' x 152' concrete slab span) 1      EACH 120,000.00 120,000.00            
202-02-C removal of portland cement concrete pavement 5,757      SQYD 5.00 28,785.00            
202-02-D removal of concrete walks & drives 4,645      SQYD 6.00 27,870.00            
202-02-G removal of surfacing & stabilized base 36,384.2    SQYD 7.40 269,243.08            
202-02-H removal of guard rail 1,830      LNFT 4.00 7,320.00            
202-02-I removal of signal equipment/related items lump      LUMP 4,000.00 4,000.00            
202-02-J removal of residential septic system 1      EACH 5,000.00 5,000.00            
202-02-K-01 removal of sign (sta 128+50 lt, 5' x 2' metal) 1      EACH 300.00 300.00            
202-02-K-02 removal of sign (sta 131+50 lt, 3' x 10' wood) 1      EACH 300.00 300.00            
202-02-K-03 removal of sign (sta 131+50 rt, 4' x 8' wood) 1      EACH 300.00 300.00            
202-02-K-04 removal of sign (sta 139+50 rt, 4' x 7' brick) 1      EACH 1,600.00 1,600.00            
202-02-K-05 removal of sign (sta 232+90 rt, 12' x 16' brick) 1      EACH 2,500.00 2,500.00            
202-02-K-06 removal of light pole(sta 232+90 rt, 12' metal pole
with camera)
1      EACH 2,600.00 2,600.00            
202-02-K-07 removal of fence (sta 235+90 rt, brick fence) 260      LNFT 11.00 2,860.00            
202-02-K-08 removal of sign (sta 236+05 lt, 3' x 15' brick) 1      EACH 1,000.00 1,000.00            
202-02-K-09 removal of brick columns and entry gate (sta 236+05 lt) lump      LUMP 3,800.00 3,800.00            
202-02-K-10 removal of brick walls (sta 236+05 lt, 2-3' high
subdivision entrance)
lump      LUMP 2,600.00 2,600.00            
202-02-K-11 removal of light pole (sta 236+10 lt, 10' metal pole) 1      EACH 3,650.00 3,650.00            
202-02-K-12 removal of sign (sta 266+20 lt, 6' x 8' brick) 1      EACH 300.00 300.00            
202-02-K-13 removal of sign (sta 289+55 lt, 13' x 6' x 4' wood) 1      EACH 300.00 300.00            
203-01 general excavation 59,706      CUYD 4.25 253,750.50            
203-02 drainage excavation 2,940      CUYD 17.00 49,980.00            
203-03 embankment 86,452      CUYD 11.00 950,972.00            
204-02 temporary hay or straw bales 150      EACH 14.45 2,167.50            
204-05-A temporary sediment check dams (hay) 135      EACH 120.00 16,200.00            
204-05-B temporary sediment check dams (stone) 15      EACH 370.00 5,550.00            
204-06 temporary silt fencing 24,000      LNFT 2.40 57,600.00            
204-07 temporary stone construction entrance 2      EACH 5,300.00 10,600.00            
302-01 class ii base course 20,882.5    CUYD 110.00 2,297,075.00            
304-01 lime 1,478.93   TON 138.00 204,092.34            
304-04-D lime treatment (type d) (12" thick) 104,332      SQYD 0.01 1,043.32            
402-01 traffic maintenance aggregate (vehicular measurement) 2,000.0    CUYD 58.00 116,000.00            
502-01 superpave asphaltic concrete 12,762.9    TON 105.00 1,340,104.50            
601-01-G portland cement concrete pavement (8" thick) 101,139.4    SQYD 58.00 5,866,085.20            
601-01-K portland cement concrete pavement (10" thick) 3,565.2    SQYD 73.00 260,259.60            
601-02-G portland cement concrete pavement (8" thick)
(crossovers & turnouts)
2,262.7    SQYD 88.00 199,117.60            
601-03-C portland cement concrete shoulder (6" thick) 693.6    SQYD 74.00 51,326.40            
701-01-I cross drain pipe (24" rcp/pcp) 168      LNFT 80.00 13,440.00            
701-01-M cross drain pipe (36" rcp/pcp) 458      LNFT 145.00 66,410.00            
701-01-N cross drain pipe (42" rcp/pcp) 908      LNFT 186.00 168,888.00            
701-01-Q cross drain pipe (60" rcp/pcp) 46      LNFT 385.00 17,710.00            
701-03-F storm drain pipe (15" rcp/pcp) 3,762      LNFT 89.00 334,818.00            
701-03-G storm drain pipe (18" rcp/pcp) 1,595      LNFT 102.00 162,690.00            
701-03-I storm drain pipe (24" rcp/pcp) 1,031      LNFT 118.00 121,658.00            
701-05-G side drain pipe (18") 548      LNFT 55.00 30,140.00            
701-05-I side drain pipe (24") 744      LNFT 66.00 49,104.00            
701-05-I-01 side drain pipe (24")(erosion) 200      LNFT 66.00 13,200.00            
701-05-K side drain pipe (30") 256      LNFT 82.00 20,992.00            
701-05-M side drain pipe (36") 64      LNFT 121.00 7,744.00            
701-05-M-01 side drain pipe (36")(erosion) 40      LNFT 121.00 4,840.00            
701-05-N side drain pipe (42") 60      LNFT 160.00 9,600.00            
702-02-A-01 manholes (mh-06)(type a grate) 1      EACH 5,040.00 5,040.00            
702-02-B manholes (r-cb-11) 1      EACH 5,055.00 5,055.00            
702-03-A catch basins (cb-01) 6      EACH 4,800.00 28,800.00            
702-03-C catch basins (cb-06) 57      EACH 4,960.00 282,720.00            
702-03-D catch basins (cb-07) 2      EACH 4,925.00 9,850.00            
702-03-F catch basins (cb-08) 20      EACH 7,770.00 155,400.00            
702-04-A adjusting manholes 5      EACH 2,000.00 10,000.00            
703-02 shoulder outlet underdrains 2      EACH 1,750.00 3,500.00            
703-03 perforated pipe underdrains (4" pvc) 23,810      LNFT 12.25 291,672.50            
705-01 barbed wire fence 5,385      LNFT 5.60 30,156.00            
705-02 combination mesh & barbed wire fence 183      LNFT 6.90 1,262.70            
705-05 double swinging driveway gates 4      DBGT 700.00 2,800.00            
705-06-A chain link fence (4-foot height) 130      LNFT 18.00 2,340.00            
705-06-C chain link fence (6-foot height) 301      LNFT 26.00 7,826.00            
705-06-D chain link fence (7-foot height) 1,864      LNFT 34.00 63,376.00            
705-08-C 10-foot double gates for chain link fence (6-foot
height)
1      DBGT 1,450.00 1,450.00            
705-09 rebuilt fence 557      LNFT 155.00 86,335.00            
706-02-C concrete drive (6" thick) 6,101.4    SQYD 58.00 353,881.20            
706-03-A incidental concrete paving (4" thick) 4,979.7    SQYD 30.00 149,391.00            
707-01 concrete curb 31,994.9    LNFT 10.00 319,949.00            
708-01 right-of-way monument 131      EACH 120.00 15,720.00            
708-02 right-of-way monument witness post 131      EACH 80.00 10,480.00            
711-01-D riprap (55 lb, 24"thick) 237      SQYD 112.00 26,544.00            
711-04 geotextile fabric 237      SQYD 3.00 711.00            
712-04 flexible revetment 3,113      SQYD 57.00 177,441.00            
713-01 temporary signs & barricades lump      LUMP 145,700.00 145,700.00            
713-04-A-01 temporary pavement markings (solid line)(4" width)
(type i removable)
22.474  MILE 10,500.00 235,977.00            
713-07 temporary precast concrete barrier (contractor
furnished)
28      EACH 1,150.00 32,200.00            
716-01-B mulch (fiber) 31.96   TON 1,000.00 31,960.00            
717-01 seeding 1,918      LB 8.00 15,344.00            
718-01 fertilizer 31,960      LB 0.32 10,227.20            
720-01-A erosion control system, slope protection (type a) 667      SQYD 1.40 933.80            
720-01-D erosion control system, flexible channel liner (type d) 23,197      SQYD 1.90 44,074.30            
722-02 project site laboratory (equipped) 1      EACH 30,000.00 30,000.00            
725-01 temporary detour roads 3,700.0    SQYD 80.00 296,000.00            
726-01 bedding material 1,122.8    CUYD 60.00 67,368.00            
727-01 mobilization lump      LUMP 2,600,000.00 2,600,000.00            
729-01 sign (type a) 416.9    SQFT 34.00 14,174.60            
729-02 sign (type b) 173.6    SQFT 35.00 6,076.00            
729-16-C object marker assembly (type 3) 4      EACH 85.00 340.00            
731-02 reflectorized raised pavement markers 2,250      EACH 4.80 10,800.00            
732-02-A plastic pavement striping (solid line) (4" width) 11.687  MILE 2,150.00 25,127.05            
732-02-C plastic pavement striping (solid line) (8" width) 0.202  MILE 4,444.00 897.69            
732-02-E plastic pavement striping (solid line) (24" width) 0.183  MILE 10,907.00 1,995.98            
732-03-A plastic pavement striping (broken line)(4" width) 10.560  MILE 700.00 7,392.00            
732-04-A plastic pavement legends & symbols (arrow) 89      EACH 130.00 11,570.00            
732-04-B plastic pavement legends & symbols (double arrow) 2      EACH 150.00 300.00            
732-04-C plastic pavement legends & symbols (only) 14      EACH 140.00 1,960.00            
732-04-D plastic pavement legends & symbols (rr crossing) 2      EACH 350.00 700.00            
732-05 removal of existing markings 0.250  MILE 5,280.00 1,320.00            
736-01 trenching and backfilling 2,165      LNFT 2.00 4,330.00            
736-03-A jacked or bored conduit (1" p.e.c.) 495      LNFT 13.00 6,435.00            
736-03-B jacked or bored conduit (2" p.e.c.) 445      LNFT 20.00 8,900.00            
736-03-C jacked or bored conduit (3" p.e.c.) 350      LNFT 22.00 7,700.00            
736-04-A signal support (mast arm standard w/30' arm) 1      EACH 11,900.00 11,900.00            
736-04-B signal support (mast arm standard w/40' arm) 3      EACH 12,400.00 37,200.00            
736-04-C signal support (mast arm standard w/45' arm) 1      EACH 13,400.00 13,400.00            
736-04-D signal support (mast arm standard w/50' arm) 3      EACH 14,400.00 43,200.00            
736-04-E signal support (mast arm standard w/35' & 40' arms) 1      EACH 16,250.00 16,250.00            
736-05-A signal heads (3-section, r, y, g)(l.e.d) 15      EACH 1,100.00 16,500.00            
736-05-B signal heads (3-section, r, lty, ltg)(l.e.d) 2      EACH 1,065.00 2,130.00            
736-05-C signal heads (5-section, r, lty, y, ltg, g)(l.e.d) 3      EACH 1,645.00 4,935.00            
736-05-D signal heads (programmable 3-section, r, y, g)(l.e.d) 1      EACH 3,150.00 3,150.00            
736-05-E signal heads (programmable 5-section, r, lty, y, ltg,
g)(l.e.d)
2      EACH 5,000.00 10,000.00            
736-05-F signal heads (programmable 5-section, r, rty, y, rtg,
g)(l.e.d)
1      EACH 5,000.00 5,000.00            
736-06-A signal service 2      EACH 2,000.00 4,000.00            
736-06-B signal service (pedestal mounted) 2      EACH 2,000.00 4,000.00            
736-08 signal controller 2      EACH 19,700.00 39,400.00            
736-09 loop detector 548      LNFT 18.00 9,864.00            
736-10-A underground junction box (type "e") 8      EACH 350.00 2,800.00            
736-10-B underground junction box (type "f") 12      EACH 450.00 5,400.00            
736-10-C underground junction box (type "h") 2      EACH 1,100.00 2,200.00            
736-11-A conduit (1/2" p.e.c. schedule 80) 100      LNFT 3.00 300.00            
736-11-B conduit (1" p.e.c. schedule 80) 1,360      LNFT 3.00 4,080.00            
736-11-C conduit (2" p.e.c. schedule 80) 120      LNFT 5.00 600.00            
736-11-D conduit (3" p.e.c. schedule 80) 545      LNFT 6.50 3,542.50            
736-12-A conductor (2c, loop lead-in) 2,980      LNFT 1.10 3,278.00            
736-12-B conductor (6c, signal) 777      LNFT 2.50 1,942.50            
736-12-C conductor (10c, signal) 4,065      LNFT 2.50 10,162.50            
736-12-D conductor (railroad preemption cable) 340      LNFT 3.00 1,020.00            
736-12-E conductor (3c, power) 20      LNFT 6.00 120.00            
740-01 construction layout lump      LUMP 300,000.00 300,000.00            
740-02 utility oversight and coordination lump      LUMP 88,000.00 88,000.00            
742-01-A sanitary sewer pipe (6") 12      LNFT 40.00 480.00            
742-01-B sanitary sewer pipe (8") 30      LNFT 45.00 1,350.00            
742-01-C sanitary sewer pipe (10") 28      LNFT 50.00 1,400.00            
742-01-D sanitary sewer pipe (12") 1,661      LNFT 179.00 297,319.00            
742-01-E sanitary sewer pipe (15") 1,700      LNFT 343.00 583,100.00            
742-01-F sanitary sewer pipe (24") 730      LNFT 369.00 269,370.00            
742-01-G sanitary sewer pipe (36") 75      LNFT 428.00 32,100.00            
742-05-A abandon manhole 9      EACH 500.00 4,500.00            
742-05-B abandon 10" sanitary sewer (+/- 54 lnft) lump      LUMP 500.00 500.00            
742-05-C abandon 12" sanitary sewer (+/- 1,655 lnft) lump      LUMP 8,275.00 8,275.00            
742-05-D abandon 15" sanitary sewer (+/- 1,695 lnft) lump      LUMP 13,150.00 13,150.00            
742-05-E abandon 24" sanitary sewer (+/- 732 lnft) lump      LUMP 14,275.00 14,275.00            
742-06-A sanitary sewer manhole (10' - 15' depth) 3      EACH 4,500.00 13,500.00            
742-06-B sanitary sewer manhole (15' - 20' depth) 4      EACH 6,500.00 26,000.00            
742-06-C sanitary sewer manhole (20' - 25' depth) 3      EACH 8,500.00 25,500.00            
742-06-D sanitary sewer manhole (25' - 30' depth) 3      EACH 10,000.00 30,000.00            
742-07 de-watering lump      LUMP 475,215.00 475,215.00            
742-08 sanitary sewer force main (8") 30      LNFT 50.00 1,500.00            
804-01-D precast concrete piles (18") 3,240      LNFT 90.00 291,600.00            
804-01-F precast concrete piles (24") 4,290      LNFT 200.00 858,000.00            
804-05 precast concrete test piles 1      EACH 80,000.00 80,000.00            
804-09 loading test piles 1      EACH 5,000.00 5,000.00            
804-10 reloading test piles 1      EACH 2,000.00 2,000.00            
804-11 redriving test piles 1      EACH 2,000.00 2,000.00            
804-12 loading permanent piles 1      EACH 2,000.00 2,000.00            
804-17 dynamic monitoring 3      EACH 1,500.00 4,500.00            
805-01-A class a concrete (pipe headwalls) 31.40   CUYD 1,360.00 42,704.00            
805-01-F class a concrete (bents) 522.02   CUYD 1,070.00 558,561.40            
805-03 class aa concrete 1,217.52   CUYD 790.00 961,840.80            
806-01 deformed reinforcing steel 335,899      LB 1.16 389,642.84            
810-01 concrete railing (32" barrier) 1,060.66   LNFT 60.00 63,639.60            
813-01 concrete approach slabs 1,854.04   SQYD 200.00 370,808.00            
S-001 video detection camera device and connection 7      EACH 6,000.00 42,000.00            
S-002 video detection camera system 2      EACH 4,400.00 8,800.00            
S-003 blank out sign (no left turn) 1      EACH 4,570.00 4,570.00            
S-004 blank out sign (no right turn) 1      EACH 4,570.00 4,570.00            
S-005 chain link fence (12' height)(1" black mesh) 164      LNFT 138.00 22,632.00            
S-006 paved gutter drain (4' wide) 79      EACH 1,700.00 134,300.00            
S-007 paved gutter drain (8' wide) 12      EACH 4,200.00 50,400.00            
S-102 dynamic analysis 3      EACH 1,500.00 4,500.00            
S-103 vibration monitoring lump      LUMP 15,000.00 15,000.00            
                       
 ITEM TOTAL (CONSTRUCTION BID)       26,654,966.20            
 NUMBER OF DAYS BID AT $1,000 PER DAY.       850,000.00            
 TOTAL BID       27,504,966.20            