| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - GILCHRIST CONSTRUCTION CO. LLC |
- 2 - H & S CONSTRUCTION CO., INC. |
- 3 - PRAIRIE CONTRACTORS INC. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-H |
removal of guard rail
|
3,616   |
LNFT |
12.00 |
43,392.00 |
5.00 |
18,080.00 |
30.00 |
108,480.00 |
|
|
| 203-07 |
borrow (vehicular measurement)
|
9,816   |
CUYD |
18.00 |
176,688.00 |
14.00 |
137,424.00 |
50.00 |
490,800.00 |
|
|
| 502-01 |
superpave asphaltic concrete
|
17,417.0 |
TON |
110.00 |
1,915,870.00 |
85.00 |
1,480,445.00 |
125.00 |
2,177,125.00 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
2,100.6 |
TON |
150.00 |
315,090.00 |
120.00 |
252,072.00 |
200.00 |
420,120.00 |
|
|
| 507-01 |
asphaltic material (type c)
|
77,534   |
GAL |
2.40 |
186,081.60 |
1.87 |
144,988.58 |
4.00 |
310,136.00 |
|
|
| 507-02-B |
aggregate (s2)
|
189,107   |
SQYD |
1.30 |
245,839.10 |
1.16 |
219,364.12 |
2.00 |
378,214.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
158,335   |
SQYD |
1.50 |
237,502.50 |
1.65 |
261,252.75 |
3.00 |
475,005.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 6,597   |
CUYD |
0.01 |
- 65.97 |
0.01 |
- 65.97 |
0.01 |
- 65.97 |
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
682   |
SQYD |
198.00 |
135,036.00 |
150.00 |
102,300.00 |
200.00 |
136,400.00 |
|
|
| 602-02-A |
cleaning and resealing existing longitudinal pavement
joints |
81,878   |
LNFT |
1.50 |
122,817.00 |
1.50 |
122,817.00 |
2.00 |
163,756.00 |
|
|
| 602-02-B |
cleaning and resealing existing transverse pavement
joints |
60,485   |
LNFT |
1.80 |
108,873.00 |
1.70 |
102,824.50 |
2.00 |
120,970.00 |
|
|
| 602-03 |
cleaning and sealing random cracks
|
2,150   |
LNFT |
3.40 |
7,310.00 |
3.30 |
7,095.00 |
5.00 |
10,750.00 |
|
|
| 602-05-K-01 |
full depth patching of jointed conc pvmt (10" thick)
(16.0 sq yds & under) |
76.7 |
SQYD |
260.00 |
19,942.00 |
247.50 |
18,983.25 |
300.00 |
23,010.00 |
|
|
| 602-05-K-02 |
full depth patching of jointed conc pvmt (10" thick)
(16.1-48.0 sq yds) |
400.5 |
SQYD |
230.00 |
92,115.00 |
220.00 |
88,110.00 |
250.00 |
100,125.00 |
|
|
| 602-08 |
grinding concrete pavement
|
186.7 |
SQYD |
17.00 |
3,173.90 |
23.00 |
4,294.10 |
100.00 |
18,670.00 |
|
|
| 602-10 |
longitudinal shoulder joints
|
143,645   |
LNFT |
1.70 |
244,196.50 |
1.54 |
221,213.30 |
2.00 |
287,290.00 |
|
|
| 701-10-I |
reinforced concrete pipe (extension) (24")
|
4   |
LNFT |
350.00 |
1,400.00 |
380.00 |
1,520.00 |
1,000.00 |
4,000.00 |
|
|
| 701-15 |
concrete collar
|
1   |
EACH |
1,500.00 |
1,500.00 |
1,000.00 |
1,000.00 |
3,000.00 |
3,000.00 |
|
|
| 704-03 |
blocked out guard rail
|
5,500.0 |
LNFT |
20.00 |
110,000.00 |
18.70 |
102,850.00 |
30.00 |
165,000.00 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
550.0 |
LNFT |
63.00 |
34,650.00 |
64.00 |
35,200.00 |
100.00 |
55,000.00 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
22   |
EACH |
2,400.00 |
52,800.00 |
2,200.00 |
48,400.00 |
3,000.00 |
66,000.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
500,000.00 |
500,000.00 |
225,000.00 |
225,000.00 |
1,250,000.00 |
1,250,000.00 |
|
|
| 713-03-A |
temporary pavement markings (broken line) (4" width)
(4' length) |
10.514 |
MILE |
400.00 |
4,205.60 |
360.00 |
3,785.04 |
1,000.00 |
10,514.00 |
|
|
| 713-03-B |
temporary pavement markings (broken line) (4" width)
(10' length) |
10.514 |
MILE |
800.00 |
8,411.20 |
396.00 |
4,163.54 |
500.00 |
5,257.00 |
|
|
| 713-04-A |
temporary pavement markings (solid line) (4" width)
|
20.962 |
MILE |
830.00 |
17,398.46 |
792.00 |
16,601.90 |
1,000.00 |
20,962.00 |
|
|
| 726-01 |
bedding material
|
0.9 |
CUYD |
160.00 |
144.00 |
125.00 |
112.50 |
2,000.00 |
1,800.00 |
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
720,000.00 |
720,000.00 |
425,000.00 |
425,000.00 |
1,250,000.00 |
1,250,000.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
22   |
EACH |
85.00 |
1,870.00 |
77.00 |
1,694.00 |
150.00 |
3,300.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
5,239   |
EACH |
5.90 |
30,910.10 |
5.61 |
29,390.79 |
7.00 |
36,673.00 |
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
15,434   |
LNFT |
1.10 |
16,977.40 |
1.00 |
15,434.00 |
3.00 |
46,302.00 |
|
|
| 732-01-D |
plastic pavement striping (12" width)
|
24   |
LNFT |
1.50 |
36.00 |
1.50 |
36.00 |
4.00 |
96.00 |
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
6,443   |
LNFT |
3.10 |
19,973.30 |
3.00 |
19,329.00 |
30.00 |
193,290.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
50.058 |
MILE |
3,900.00 |
195,226.20 |
2,695.00 |
134,906.31 |
4,000.00 |
200,232.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
22.060 |
MILE |
1,100.00 |
24,266.00 |
1,092.00 |
24,089.52 |
1,500.00 |
33,090.00 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
7   |
EACH |
175.00 |
1,225.00 |
171.00 |
1,197.00 |
200.00 |
1,400.00 |
|
|
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
5   |
EACH |
240.00 |
1,200.00 |
231.00 |
1,155.00 |
300.00 |
1,500.00 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
7   |
EACH |
190.00 |
1,330.00 |
190.00 |
1,330.00 |
300.00 |
2,100.00 |
|
|
| 732-04-F |
plastic pavement legends & symbols (ok)
|
1   |
EACH |
450.00 |
450.00 |
429.00 |
429.00 |
400.00 |
400.00 |
|
|
| 732-05 |
removal of existing markings
|
15.090 |
MILE |
5,700.00 |
86,013.00 |
5,445.00 |
82,165.05 |
8,000.00 |
120,720.00 |
|
|
| 739-01 |
hydro-seeding
|
10.52 |
ACRE |
2,100.00 |
22,092.00 |
1,155.00 |
12,150.60 |
2,000.00 |
21,040.00 |
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
125,000.00 |
125,000.00 |
100,000.00 |
100,000.00 |
100,000.00 |
100,000.00 |
|
|
| S-001 |
raising and/or undersealing approach slabs
|
40,700   |
LB |
4.60 |
187,220.00 |
4.40 |
179,080.00 |
6.00 |
244,200.00 |
|
|
| S-002 |
saw cutting
|
2,000   |
INFT |
0.80 |
1,600.00 |
1.10 |
2,200.00 |
5.00 |
10,000.00 |
|
|
| S-003 |
ultra-thin hmac wearing course system (0.75 inch thick)
|
158,335   |
SQYD |
7.30 |
1,155,845.50 |
7.60 |
1,203,346.00 |
11.00 |
1,741,685.00 |
|
|
| S-004 |
radar traffic sensor and recorder system
|
1   |
EACH |
26,000.00 |
26,000.00 |
28,000.00 |
28,000.00 |
40,000.00 |
40,000.00 |
|
|
| S-005 |
dynamic message sign unit
|
4   |
EACH |
15,000.00 |
60,000.00 |
20,900.00 |
83,600.00 |
50,000.00 |
200,000.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
7,261,604.39 |
|
5,964,362.88 |
|
11,048,346.03 |
|
|
| | NUMBER OF DAYS BID AT $15,000 PER DAY. |
|
|
|
2,475,000.00 |
|
3,900,000.00 |
|
5,250,000.00 |
|
|
| | TOTAL BID |
|
|
|
9,736,604.39 |
|
9,864,362.88 |
|
16,298,346.03 |
|
|
|