Letting of 7/25/2007 LA DOTD Headquarters


REBID
go back
Go Back
DBE GOAL FED
Lead Project: 455-01-0049
Parish: LAFAYETTE
Routes: I-49
Description: I-10 - ST. LANDRY PARISH LINE
Type Const: grading, drainage struct., portland cement concrete pavement patching, cold planing
asphaltic concrete, asphaltic surface trmt., superpave asphaltic concrete overlay, & related work.
Estimated Construction Cost: $5,573,413.99
Maximum Number of Days Allowed for Construction: 400
Calculated Daily User Cost: $15,000.00
 
RankLicenseBidderConstruction Bid Bidder's Proposed
Contract Time
Total Bid
1 12312 GILCHRIST CONSTRUCTION CO. LLC $7,261,604.39 165 $9,736,604.39
2 04089 H & S CONSTRUCTION CO., INC. $5,964,362.88 260 $9,864,362.88
3 34356 PRAIRIE CONTRACTORS INC. $11,048,346.03 350 $16,298,346.03
 
Item Number Item Description Quantity Unit of Measure - 1 -
GILCHRIST CONSTRUCTION CO. LLC
- 2 -
H & S CONSTRUCTION CO., INC.
- 3 -
PRAIRIE CONTRACTORS INC.

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-H removal of guard rail 3,616      LNFT 12.00 43,392.00 5.00 18,080.00 30.00 108,480.00    
203-07 borrow (vehicular measurement) 9,816      CUYD 18.00 176,688.00 14.00 137,424.00 50.00 490,800.00    
502-01 superpave asphaltic concrete 17,417.0    TON 110.00 1,915,870.00 85.00 1,480,445.00 125.00 2,177,125.00    
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
2,100.6    TON 150.00 315,090.00 120.00 252,072.00 200.00 420,120.00    
507-01 asphaltic material (type c) 77,534      GAL 2.40 186,081.60 1.87 144,988.58 4.00 310,136.00    
507-02-B aggregate (s2) 189,107      SQYD 1.30 245,839.10 1.16 219,364.12 2.00 378,214.00    
509-01 cold planing asphaltic pavement 158,335      SQYD 1.50 237,502.50 1.65 261,252.75 3.00 475,005.00    
509-02 contractor retained reclaimed asphaltic pavement - 6,597      CUYD 0.01 - 65.97 0.01 - 65.97 0.01 - 65.97    
510-01-B pavement patching (12" minimum thickness) 682      SQYD 198.00 135,036.00 150.00 102,300.00 200.00 136,400.00    
602-02-A cleaning and resealing existing longitudinal pavement
joints
81,878      LNFT 1.50 122,817.00 1.50 122,817.00 2.00 163,756.00    
602-02-B cleaning and resealing existing transverse pavement
joints
60,485      LNFT 1.80 108,873.00 1.70 102,824.50 2.00 120,970.00    
602-03 cleaning and sealing random cracks 2,150      LNFT 3.40 7,310.00 3.30 7,095.00 5.00 10,750.00    
602-05-K-01 full depth patching of jointed conc pvmt (10" thick)
(16.0 sq yds & under)
76.7    SQYD 260.00 19,942.00 247.50 18,983.25 300.00 23,010.00    
602-05-K-02 full depth patching of jointed conc pvmt (10" thick)
(16.1-48.0 sq yds)
400.5    SQYD 230.00 92,115.00 220.00 88,110.00 250.00 100,125.00    
602-08 grinding concrete pavement 186.7    SQYD 17.00 3,173.90 23.00 4,294.10 100.00 18,670.00    
602-10 longitudinal shoulder joints 143,645      LNFT 1.70 244,196.50 1.54 221,213.30 2.00 287,290.00    
701-10-I reinforced concrete pipe (extension) (24") 4      LNFT 350.00 1,400.00 380.00 1,520.00 1,000.00 4,000.00    
701-15 concrete collar 1      EACH 1,500.00 1,500.00 1,000.00 1,000.00 3,000.00 3,000.00    
704-03 blocked out guard rail 5,500.0    LNFT 20.00 110,000.00 18.70 102,850.00 30.00 165,000.00    
704-08-B guard rail transitions (double thrie beam) 550.0    LNFT 63.00 34,650.00 64.00 35,200.00 100.00 55,000.00    
704-11-A guard rail end treatment (flared) 22      EACH 2,400.00 52,800.00 2,200.00 48,400.00 3,000.00 66,000.00    
713-01 temporary signs & barricades lump      LUMP 500,000.00 500,000.00 225,000.00 225,000.00 1,250,000.00 1,250,000.00    
713-03-A temporary pavement markings (broken line) (4" width)
(4' length)
10.514  MILE 400.00 4,205.60 360.00 3,785.04 1,000.00 10,514.00    
713-03-B temporary pavement markings (broken line) (4" width)
(10' length)
10.514  MILE 800.00 8,411.20 396.00 4,163.54 500.00 5,257.00    
713-04-A temporary pavement markings (solid line) (4" width) 20.962  MILE 830.00 17,398.46 792.00 16,601.90 1,000.00 20,962.00    
726-01 bedding material 0.9    CUYD 160.00 144.00 125.00 112.50 2,000.00 1,800.00    
727-01 mobilization lump      LUMP 720,000.00 720,000.00 425,000.00 425,000.00 1,250,000.00 1,250,000.00    
729-16-C object marker assembly (type 3) 22      EACH 85.00 1,870.00 77.00 1,694.00 150.00 3,300.00    
731-02 reflectorized raised pavement markers 5,239      EACH 5.90 30,910.10 5.61 29,390.79 7.00 36,673.00    
732-01-C plastic pavement striping (8" width) 15,434      LNFT 1.10 16,977.40 1.00 15,434.00 3.00 46,302.00    
732-01-D plastic pavement striping (12" width) 24      LNFT 1.50 36.00 1.50 36.00 4.00 96.00    
732-01-E plastic pavement striping (24" width) 6,443      LNFT 3.10 19,973.30 3.00 19,329.00 30.00 193,290.00    
732-02-A plastic pavement striping (solid line) (4" width) 50.058  MILE 3,900.00 195,226.20 2,695.00 134,906.31 4,000.00 200,232.00    
732-03-A plastic pavement striping (broken line)(4" width) 22.060  MILE 1,100.00 24,266.00 1,092.00 24,089.52 1,500.00 33,090.00    
732-04-A plastic pavement legends & symbols (arrow) 7      EACH 175.00 1,225.00 171.00 1,197.00 200.00 1,400.00    
732-04-B plastic pavement legends & symbols (double arrow) 5      EACH 240.00 1,200.00 231.00 1,155.00 300.00 1,500.00    
732-04-C plastic pavement legends & symbols (only) 7      EACH 190.00 1,330.00 190.00 1,330.00 300.00 2,100.00    
732-04-F plastic pavement legends & symbols (ok) 1      EACH 450.00 450.00 429.00 429.00 400.00 400.00    
732-05 removal of existing markings 15.090  MILE 5,700.00 86,013.00 5,445.00 82,165.05 8,000.00 120,720.00    
739-01 hydro-seeding 10.52   ACRE 2,100.00 22,092.00 1,155.00 12,150.60 2,000.00 21,040.00    
740-01 construction layout lump      LUMP 125,000.00 125,000.00 100,000.00 100,000.00 100,000.00 100,000.00    
S-001 raising and/or undersealing approach slabs 40,700      LB 4.60 187,220.00 4.40 179,080.00 6.00 244,200.00    
S-002 saw cutting 2,000      INFT 0.80 1,600.00 1.10 2,200.00 5.00 10,000.00    
S-003 ultra-thin hmac wearing course system (0.75 inch thick) 158,335      SQYD 7.30 1,155,845.50 7.60 1,203,346.00 11.00 1,741,685.00    
S-004 radar traffic sensor and recorder system 1      EACH 26,000.00 26,000.00 28,000.00 28,000.00 40,000.00 40,000.00    
S-005 dynamic message sign unit 4      EACH 15,000.00 60,000.00 20,900.00 83,600.00 50,000.00 200,000.00    
                       
 ITEM TOTAL (CONSTRUCTION BID)       7,261,604.39   5,964,362.88   11,048,346.03    
 NUMBER OF DAYS BID AT $15,000 PER DAY.       2,475,000.00   3,900,000.00   5,250,000.00    
 TOTAL BID       9,736,604.39   9,864,362.88   16,298,346.03    