| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC. |
- 2 - DIAMOND B CONSTRUCTION CO., L.L.C. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 203-07 |
borrow (vehicular measurement)
|
731   |
CUYD |
18.00 |
13,158.00 |
22.00 |
16,082.00 |
|
|
|
|
| 203-07-A |
borrow (vehicular meas.)(selected soils)
|
3,434   |
CUYD |
18.00 |
61,812.00 |
17.00 |
58,378.00 |
|
|
|
|
| 204-02 |
temporary hay or straw bales
|
40   |
EACH |
15.00 |
600.00 |
30.00 |
1,200.00 |
|
|
|
|
| 204-06 |
temporary silt fencing
|
1,000   |
LNFT |
3.00 |
3,000.00 |
4.00 |
4,000.00 |
|
|
|
|
| 303-02 |
removal of existing patches
|
1,500   |
SQYD |
10.00 |
15,000.00 |
15.00 |
22,500.00 |
|
|
|
|
| 308-01-A |
in-place cement treated base course (12" thick)
|
64,386   |
SQYD |
5.60 |
360,561.60 |
5.00 |
321,930.00 |
|
|
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
100   |
CUYD |
70.00 |
7,000.00 |
76.00 |
7,600.00 |
|
|
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
200.0 |
CUYD |
50.00 |
10,000.00 |
47.00 |
9,400.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
11,898.6 |
TON |
62.00 |
737,713.20 |
59.00 |
702,017.40 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
565.0 |
TON |
62.00 |
35,030.00 |
120.00 |
67,800.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
23,000.00 |
23,000.00 |
12,500.00 |
12,500.00 |
|
|
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
62   |
LNFT |
1.00 |
62.00 |
1.00 |
62.00 |
|
|
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
8.780 |
MILE |
170.00 |
1,492.60 |
150.00 |
1,317.00 |
|
|
|
|
| 713-03-B |
temporary pavement markings (broken line)(4" width)
(10' length) |
2.920 |
MILE |
230.00 |
671.60 |
330.00 |
963.60 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
31.440 |
MILE |
430.00 |
13,519.20 |
550.00 |
17,292.00 |
|
|
|
|
| 717-01 |
seeding
|
190   |
LB |
11.00 |
2,090.00 |
10.00 |
1,900.00 |
|
|
|
|
| 718-01 |
fertilizer
|
6,400   |
LB |
0.40 |
2,560.00 |
0.35 |
2,240.00 |
|
|
|
|
| 722-01 |
project site laboratory
|
1   |
EACH |
500.00 |
500.00 |
6,000.00 |
6,000.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
35,000.00 |
35,000.00 |
81,000.00 |
81,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
579   |
EACH |
6.00 |
3,474.00 |
5.00 |
2,895.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
31   |
LNFT |
8.00 |
248.00 |
3.50 |
108.50 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
15.720 |
MILE |
2,700.00 |
42,444.00 |
2,200.00 |
34,584.00 |
|
|
|
|
| 732-03-A |
plastic pavement striping (broken line)(4" width)
|
1.460 |
MILE |
800.00 |
1,168.00 |
800.00 |
1,168.00 |
|
|
|
|
| 735-01 |
mailboxes
|
25   |
EACH |
5.00 |
125.00 |
1.00 |
25.00 |
|
|
|
|
| 735-02 |
mailbox supports (single)
|
25   |
EACH |
150.00 |
3,750.00 |
125.00 |
3,125.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
20,000.00 |
20,000.00 |
25,000.00 |
25,000.00 |
|
|
|
|
| S-001 |
saw cutting of concrete/asphalt driveways and turnouts
(full depth) |
225   |
LNFT |
10.00 |
2,250.00 |
7.00 |
1,575.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
1,396,229.20 |
|
1,402,662.50 |
|
|
|
|
|