Letting of 7/25/2007 LA DOTD Headquarters


 
go back
Go Back
DBE GOAL FED
Lead Project: 033-03-0038
Parish: AVOYELLES
Routes: LA 115
Description: JUNCTION LA 107 - RAPIDES PARISH LINE
Type Const: grading, cement treated bc, lime tr, cold planing asphaltic concrete, asphaltic
surface treatment, pavement patching, superpave asphaltic concrete pavement, and related work.
Estimated Construction Cost: $1,759,352.14
 
RankLicenseBidderConstruction Bid
1 12487 DIAMOND B CONSTRUCTION CO., L.L.C. $1,982,133.20
2 12312 GILCHRIST CONSTRUCTION CO. LLC $1,989,954.73
3 05789 D & J CONSTRUCTION CO., INC. $2,077,989.72
 
Item Number Item Description Quantity Unit of Measure - 1 -
DIAMOND B CONSTRUCTION CO., L.L.C.
- 2 -
GILCHRIST CONSTRUCTION CO. LLC
- 3 -
D & J CONSTRUCTION CO., INC.

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-D removal of concrete walks & drives 3      SQYD 100.00 300.00 155.00 465.00 50.00 150.00    
203-07-A borrow (vehicular meas.) (selected soils) 100      CUYD 30.00 3,000.00 25.00 2,500.00 15.00 1,500.00    
304-01 lime 146.11   TON 150.00 21,916.50 140.00 20,455.40 152.00 22,208.72    
304-04-D lime treatment (type d) (12" thick) 9,277      SQYD 2.85 26,439.45 1.20 11,132.40 4.60 42,674.20    
308-01-A in-place cement treated base course (12" thick) 9,277      SQYD 9.25 85,812.25 7.80 72,360.60 7.50 69,577.50    
401-02 aggregate surface course (adjusted vehicular
measurement)
3,148      CUYD 87.00 273,876.00 75.00 236,100.00 50.00 157,400.00    
502-01 superpave asphaltic concrete 9,891.1    TON 78.00 771,505.80 80.00 791,288.00 82.00 811,070.20    
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
2,172.8    TON 120.00 260,736.00 135.00 293,328.00 82.00 178,169.60    
507-01-A asphaltic material (crs-2p cold applied emulsion) 41,838      GAL 2.50 104,595.00 2.80 117,146.40 2.15 89,951.70    
507-02-B aggregate (s2) 61,527      SQYD 1.25 76,908.75 1.35 83,061.45 1.85 113,824.95    
507-02-C aggregate (s3) 61,527      SQYD 1.00 61,527.00 1.10 67,679.70 1.85 113,824.95    
509-01 cold planing asphaltic pavement 8,873      SQYD 4.00 35,492.00 2.27 20,141.71 2.35 20,851.55    
509-02 contractor retained reclaimed asphaltic pavement - 742      CUYD 0.10 - 74.20 0.01 - 7.42 0.01 - 7.42    
510-01-B pavement patching (12" minimum thickness) 140      SQYD 155.00 21,700.00 199.00 27,860.00 200.00 28,000.00    
713-01 temporary signs & barricades lump      LUMP 12,000.00 12,000.00 1,500.00 1,500.00 75,000.00 75,000.00    
713-03-A temporary pavement markings (broken line) (4" width)
(4' length)
6.830  MILE 450.00 3,073.50 450.00 3,073.50 226.00 1,543.58    
713-03-B temporary pavement markings (broken line) (4" width)
(10' length)
11.199  MILE 300.00 3,359.70 1.00 11.20 300.00 3,359.70    
713-04-A temporary pavement markings (solid line) (4" width) 28.485  MILE 450.00 12,818.25 1.00 28.49 1.00 28.49    
713-06-A temporary reflectorized raised pavement markers (tabs) 2,520      EACH 1.00 2,520.00 1.68 4,233.60 1.50 3,780.00    
722-01 project site laboratory 1      EACH 3,500.00 3,500.00 10,000.00 10,000.00 10,000.00 10,000.00    
727-01 mobilization lump      LUMP 79,000.00 79,000.00 90,000.00 90,000.00 155,000.00 155,000.00    
731-02 reflectorized raised pavement markers 720      EACH 5.00 3,600.00 5.75 4,140.00 6.00 4,320.00    
732-01-E plastic pavement striping (24" width) 18      LNFT 3.50 63.00 4.50 81.00 22.00 396.00    
732-02-A plastic pavement striping (solid line) (4" width) 24.883  MILE 2,400.00 59,719.20 2,700.00 67,184.10 2,000.00 49,766.00    
732-03-A plastic pavement striping (broken line) (4" width) 9.824  MILE 750.00 7,368.00 900.00 8,841.60 1,000.00 9,824.00    
735-01 mailboxes 112      EACH 1.00 112.00 10.00 1,120.00 13.00 1,456.00    
735-02 mailbox supports (single) 93      EACH 125.00 11,625.00 130.00 12,090.00 140.00 13,020.00    
735-03 mailbox supports (double) 4      EACH 160.00 640.00 180.00 720.00 250.00 1,000.00    
735-04 mailbox supports (multiple) 4      EACH 250.00 1,000.00 255.00 1,020.00 325.00 1,300.00    
740-01 construction layout lump      LUMP 6,500.00 6,500.00 10,000.00 10,000.00 20,000.00 20,000.00    
S-001 saw cutting 2,000      inft 2.25 4,500.00 3.70 7,400.00 2.00 4,000.00    
S-002 surface preparation lump      LUMP 27,000.00 27,000.00 25,000.00 25,000.00 75,000.00 75,000.00    
                       
 CONTRACTOR TOTAL       1,982,133.20   1,989,954.73   2,077,989.72    