| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - BARRIERE CONSTRUCTION CO., LLC |
- 2 - HUEY STOCKSTILL, INC. |
|
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 202-02-D |
removal of concrete walks and drives
|
550.0 |
SQYD |
10.00 |
5,500.00 |
17.00 |
9,350.00 |
|
|
|
|
| 202-02-F |
removal of concrete combination curb & gutter
|
1,076.0 |
LNFT |
5.00 |
5,380.00 |
15.00 |
16,140.00 |
|
|
|
|
| 203-07 |
borrow (vehicular measurement)
|
500   |
CUYD |
10.00 |
5,000.00 |
15.00 |
7,500.00 |
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
3,233.3 |
TON |
82.00 |
265,130.60 |
87.00 |
281,297.10 |
|
|
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
500.0 |
TON |
82.00 |
41,000.00 |
170.00 |
85,000.00 |
|
|
|
|
| 509-01 |
cold planing asphaltic pavement
|
34,618   |
SQYD |
2.00 |
69,236.00 |
4.00 |
138,472.00 |
|
|
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 1,082   |
CUYD |
10.00 |
- 10,820.00 |
1.00 |
- 1,082.00 |
|
|
|
|
| 510-01-B |
pavement patching (12" minimum thickness)
|
1,100   |
SQYD |
20.00 |
22,000.00 |
95.00 |
104,500.00 |
|
|
|
|
| 510-03 |
pavement joint repair
|
200.0 |
TON |
50.00 |
10,000.00 |
140.00 |
28,000.00 |
|
|
|
|
| 702-04-A |
adjusting manholes
|
48   |
EACH |
100.00 |
4,800.00 |
400.00 |
19,200.00 |
|
|
|
|
| 702-04-B |
adjusting catch basins
|
5   |
EACH |
500.00 |
2,500.00 |
1,600.00 |
8,000.00 |
|
|
|
|
| 706-01-A |
concrete walk (4" thick)
|
550.0 |
SQYD |
35.00 |
19,250.00 |
50.00 |
27,500.00 |
|
|
|
|
| 707-03 |
combination concrete curb & gutter
|
500.0 |
LNFT |
25.00 |
12,500.00 |
35.00 |
17,500.00 |
|
|
|
|
| 713-01 |
temporary signs & barricades
|
lump |
LUMP |
76,000.00 |
76,000.00 |
309,000.00 |
309,000.00 |
|
|
|
|
| 713-02-C |
temporary pavement markings (8" width)
|
3,600   |
LNFT |
0.10 |
360.00 |
0.30 |
1,080.00 |
|
|
|
|
| 713-02-E |
temporary pavement markings (24" width)
|
2,212   |
LNFT |
0.10 |
221.20 |
1.80 |
3,981.60 |
|
|
|
|
| 713-03-A |
temporary pavement markings (broken line)(4" width)(4'
length) |
5.680 |
MILE |
500.00 |
2,840.00 |
200.00 |
1,136.00 |
|
|
|
|
| 713-04-A |
temporary pavement markings (solid line)(4" width)
|
9.920 |
MILE |
10.00 |
99.20 |
500.00 |
4,960.00 |
|
|
|
|
| 713-05-A |
temporary pavement legends and symbols (arrow)
|
2   |
EACH |
20.00 |
40.00 |
50.00 |
100.00 |
|
|
|
|
| 713-05-B |
temporary pavement legends and symbols (double arrow)
|
2   |
EACH |
20.00 |
40.00 |
50.00 |
100.00 |
|
|
|
|
| 727-01 |
mobilization
|
lump |
LUMP |
76,000.00 |
76,000.00 |
139,000.00 |
139,000.00 |
|
|
|
|
| 731-02 |
reflectorized raised pavement markers
|
225   |
EACH |
10.00 |
2,250.00 |
6.00 |
1,350.00 |
|
|
|
|
| 732-01-C |
plastic pavement striping (8" width)
|
1,800   |
LNFT |
0.90 |
1,620.00 |
1.00 |
1,800.00 |
|
|
|
|
| 732-01-E |
plastic pavement striping (24" width)
|
206   |
LNFT |
4.00 |
824.00 |
4.00 |
824.00 |
|
|
|
|
| 732-02-A |
plastic pavement striping (solid line) (4" width)
|
4.960 |
MILE |
3,000.00 |
14,880.00 |
2,800.00 |
13,888.00 |
|
|
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
2   |
EACH |
250.00 |
500.00 |
200.00 |
400.00 |
|
|
|
|
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
2   |
EACH |
250.00 |
500.00 |
250.00 |
500.00 |
|
|
|
|
| 740-01 |
construction layout
|
lump |
LUMP |
25,000.00 |
25,000.00 |
22,000.00 |
22,000.00 |
|
|
|
|
| 741-11 |
adjusting water valve and meter box
|
15   |
EACH |
40.00 |
600.00 |
250.00 |
3,750.00 |
|
|
|
|
| S-001 |
remove & replace cb-01 grate
|
1   |
EACH |
850.00 |
850.00 |
1,000.00 |
1,000.00 |
|
|
|
|
| S-002 |
truncated domes for handicap ramps
|
100   |
SQYD |
300.00 |
30,000.00 |
420.00 |
42,000.00 |
|
|
|
|
| S-922 |
sawing and sealing longitudinal joints in asphaltic
concrete overlay |
20,280   |
LNFT |
1.20 |
24,336.00 |
1.30 |
26,364.00 |
|
|
|
|
| S-923 |
sawing and sealing transverse joints in asphaltic
concrete overlay |
25,240   |
LNFT |
1.10 |
27,764.00 |
1.30 |
32,812.00 |
|
|
|
|
| S-927 |
sawcuts in asphaltic concrete lifts
|
45,520   |
LNFT |
0.75 |
34,140.00 |
1.00 |
45,520.00 |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | CONTRACTOR TOTAL |
|
|
|
770,341.00 |
|
1,392,942.70 |
|
|
|
|
|