Lead Project: 102-01-0041
Parish: CADDO
Routes: LA 511
Description: WEST 70TH STREET (PINES ROAD TO BUNCOMBE ROAD)
Type Const: grading, pavement patching, superpave asphaltic concrete pavement, and related work.
Estimated Construction Cost: $366,986.85
 
RankLicenseBidderConstruction Bid
1 36374 BEST-YET BUILDERS, LLC $433,198.95
2 17464 BENTON & BROWN, LLC. $477,423.63
3 08584 MADDEN CONTRACTING CO., INC. $627,835.40
 
Item Number Item Description Quantity Unit of Measure - 1 -
BEST-YET BUILDERS, LLC
- 2 -
BENTON & BROWN, LLC.
- 3 -
MADDEN CONTRACTING CO., INC.

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
202-02-D removal of concrete walks & drives 9      SQYD 13.50 121.50 50.00 450.00 56.00 504.00    
203-08 borrow (vehicular measurement) 400      CUYD 15.00 6,000.00 20.00 8,000.00 20.00 8,000.00    
502-01 superpave asphaltic concrete 3,983.7    TON 75.00 298,777.50 75.00 298,777.50 88.80 353,752.56    
502-01-A superpave asphaltic concrete, drives, turnouts, and
miscellaneous
130.0    TON 75.00 9,750.00 75.00 9,750.00 242.40 31,512.00    
706-01-A concrete walk (4" thick) 9.0    SQYD 45.00 405.00 175.00 1,575.00 75.00 675.00    
712-01-A concrete cast-in-place revetment (4" thick) 25      SQYD 48.00 1,200.00 125.00 3,125.00 75.00 1,875.00    
712-04 flexible revetment 20      SQYD 75.00 1,500.00 150.00 3,000.00 85.00 1,700.00    
713-01 temporary signs and barricades lump      LUMP 5,000.00 5,000.00 25,000.00 25,000.00 52,000.00 52,000.00    
713-03-D temporary pavement markings (12" width) 132      LNFT 0.62 81.84 1.00 132.00 0.56 73.92    
713-03-E temporary pavement markings (24" width) 562      LNFT 1.85 1,039.70 2.00 1,124.00 1.68 944.16    
713-04-A temporary pavement markings (broken line) (4" width)
(4' length)
1.030  MILE 0.01 0.01 350.00 360.50 625.00 643.75    
713-04-B temporary pavement markings (broken line) (4" width)
(10' length)
0.583  MILE 349.00 203.47 375.00 218.63 317.00 184.81    
713-05-A temporary pavement markings (solid line) (4" width) 2.432  MILE 699.00 1,699.97 725.00 1,763.20 633.00 1,539.46    
713-06-A temporary pavement legends and symbols (arrow) 6      EACH 60.00 360.00 65.00 390.00 54.00 324.00    
713-06-C temporary pavement legends and symbols (only) 6      EACH 60.00 360.00 65.00 390.00 54.00 324.00    
716-01-A mulch (vegetative) 0.90   ACRE 600.00 540.00 1,600.00 1,440.00 3,000.00 2,700.00    
724-01-B pavement patching (12" minimum thickness) 550      SQYD 65.00 35,750.00 65.00 35,750.00 88.10 48,455.00    
727-01 mobilization lump      LUMP 20,000.00 20,000.00 41,000.00 41,000.00 52,000.00 52,000.00    
731-02 reflectorized raised pavement markers 286      EACH 5.99 1,713.14 6.50 1,859.00 5.40 1,544.40    
732-01-D plastic pavement striping (12" width) 132      LNFT 1.30 171.60 1.50 198.00 1.17 154.44    
732-01-E plastic pavement striping (24" width) 562      LNFT 3.86 2,169.32 4.00 2,248.00 3.51 1,972.62    
732-02-A plastic pavement striping (solid line) (4" width) 2.432  MILE 3,200.00 7,782.40 2,700.00 6,566.40 2,365.00 5,751.68    
732-03-A plastic pavement striping (broken line) (4" width) 0.583  MILE 765.00 446.00 800.00 466.40 694.00 404.60    
732-04-A plastic pavement legends and symbols (arrow) 6      EACH 160.00 960.00 200.00 1,200.00 145.00 870.00    
732-04-C plastic pavement legends and symbols (only) 6      EACH 170.00 1,020.00 200.00 1,200.00 155.00 930.00    
739-01 hydro-seeding 0.90   AC 1,275.00 1,147.50 1,600.00 1,440.00 2,000.00 1,800.00    
740-01 construction layout lump      LUMP 5,000.00 5,000.00 10,000.00 10,000.00 17,200.00 17,200.00    
744-01 traffic control management lump      LUMP 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00 10,000.00    
S-001 surface preparation lump      LUMP 20,000.00 20,000.00 10,000.00 10,000.00 30,000.00 30,000.00    
                       
 CONTRACTOR TOTAL       433,198.95   477,423.63   627,835.40    