| Item Number |
Item Description |
Quantity |
Unit of Measure |
- 1 - DIAMOND B CONSTRUCTION CO., L.L.C. |
- 2 - GILCHRIST CONSTRUCTION CO. LLC |
- 3 - D & J CONSTRUCTION CO., INC. |
|
| Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
Unit Price | Total Amount |
| 201-01 |
clearing and grubbing
|
lump |
lump |
410,000.00 |
410,000.00 |
1,200,000.00 |
1,200,000.00 |
500,000.00 |
500,000.00 |
|
|
| 202-01 |
removal of structures & obstructions
|
lump |
lump |
200,000.00 |
200,000.00 |
50,000.00 |
50,000.00 |
150,000.00 |
150,000.00 |
|
|
| 202-02-B-01 |
removal of concrete box culverts with headwalls (sta.
39+27.901; 1.5 m x 1.5 m x 15.3 m) |
1   |
ea |
8,000.00 |
8,000.00 |
2,500.00 |
2,500.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-02 |
removal of concrete box culverts (sta. 54+43.930; 3 -
2.4 m x 2.5 m x 17.9 m) |
1   |
ea |
5,000.00 |
5,000.00 |
9,000.00 |
9,000.00 |
10,000.00 |
10,000.00 |
|
|
| 202-02-B-03 |
removal of concrete box culverts (sta. 56+77.614;
4-2.4 m x 2.4 m x 20.1 m) |
1   |
ea |
4,500.00 |
4,500.00 |
9,000.00 |
9,000.00 |
15,000.00 |
15,000.00 |
|
|
| 202-02-B-04 |
removal of concrete box culverts with headwalls (sta.
60+32.181; 0.9 m x 0.9 m x 29.2 m) |
1   |
ea |
4,500.00 |
4,500.00 |
3,600.00 |
3,600.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-05 |
removal of concrete box culverts with headwalls (sta.
63+02.402; 1.2 m x 1.2 m x 29.3 m) |
1   |
ea |
4,500.00 |
4,500.00 |
3,600.00 |
3,600.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-06 |
removal of concrete box culverts with headwalls (sta.
70+39.744; 0.9 m x 0.9 m x 22.9 m) |
1   |
ea |
4,500.00 |
4,500.00 |
3,600.00 |
3,600.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-07 |
removal of concrete box culverts with headwalls (sta.
73+82.455; 0.9 m x 0.9 m x 23.5 m) |
1   |
ea |
4,500.00 |
4,500.00 |
3,600.00 |
3,600.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-08 |
removal of concrete box culverts with headwalls (sta.
78+07.478; 0.6 m x 0.6 m x 32.5 m) |
1   |
ea |
4,500.00 |
4,500.00 |
3,600.00 |
3,600.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-09 |
removal of concrete box culverts with headwalls (sta.
90+50.156; 0.9 m x 0.9 m x 15.6 m) |
1   |
ea |
4,500.00 |
4,500.00 |
3,600.00 |
3,600.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-10 |
removal of concrete box culverts with headwalls (rt.
of sta. 115+06.000; 1.2 m x 1.2 m x 16.3 m) |
1   |
ea |
4,500.00 |
4,500.00 |
3,600.00 |
3,600.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-11 |
removal of concrete box culverts with headwalls (rt.
of sta. 123+03.770; 1,2 m x 1.2 m x 15.5 m) |
1   |
ea |
4,500.00 |
4,500.00 |
3,600.00 |
3,600.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-12 |
removal of concrete box culverts with headwalls (rt.
of sta. 130+24.000; 1.5 m x 1.5 m x 22.1 m) |
1   |
ea |
4,500.00 |
4,500.00 |
3,600.00 |
3,600.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-B-13 |
removal of concrete box culverts with headwalls (lt.
of sta. 132+50.000; 2.4 m x 1.2 m x 14.0 m) |
1   |
ea |
4,500.00 |
4,500.00 |
3,600.00 |
3,600.00 |
5,000.00 |
5,000.00 |
|
|
| 202-02-C |
removal of portland cement concrete pavement
|
72,401   |
sq m |
9.00 |
651,609.00 |
3.50 |
253,403.50 |
8.00 |
579,208.00 |
|
|
| 202-02-D |
removal of concrete walks & drives
|
272   |
sq m |
40.00 |
10,880.00 |
8.00 |
2,176.00 |
25.00 |
6,800.00 |
|
|
| 202-02-G |
removal of surfacing & stabilized base
|
98,784.5 |
sq m |
3.00 |
296,353.50 |
1.75 |
172,872.88 |
4.00 |
395,138.00 |
|
|
| 202-02-H |
removal of guard rail
|
743   |
ln m |
11.00 |
8,173.00 |
15.00 |
11,145.00 |
25.00 |
18,575.00 |
|
|
| 202-02-01 |
removal of 8.4 m x 13.5 m wood frame residence on
pillars (rt. of sta. 82+84.746)(contains friable asbestos) |
1   |
ea |
10,000.00 |
10,000.00 |
3,500.00 |
3,500.00 |
1.00 |
1.00 |
|
|
| 202-02-02 |
removal of underground storage tank (lt. of sta.
105+25.000) |
2   |
ea |
13,000.00 |
26,000.00 |
12,000.00 |
24,000.00 |
1.00 |
2.00 |
|
|
| 202-02-03 |
removal of 8.7 m x 15.4 m wood frame residence on
pillars (lt. of sta. 126+30)(contains reg. ext. transite siding) |
1   |
ea |
10,000.00 |
10,000.00 |
2,800.00 |
2,800.00 |
1.00 |
1.00 |
|
|
| 202-02-04 |
removal of 30 m x 25.5 m brick residence with
greenhouse & porch (lt. of sta. 128+30)(cont. reg. ext. trans. siding) |
1   |
ea |
27,000.00 |
27,000.00 |
6,000.00 |
6,000.00 |
1.00 |
1.00 |
|
|
| 202-02-05 |
removal of steel frame wood roof over mobile home with
porches on slab (lt. of sta. 129+25)(cont. non-friable asb.) |
1   |
ea |
10,000.00 |
10,000.00 |
3,600.00 |
3,600.00 |
1.00 |
1.00 |
|
|
| 202-02-06 |
removal of 7.5 m x 18.2 m wood frame residence on
pillars (lt. of sta. 130+60) (contains non-friable asbestos) |
1   |
ea |
10,000.00 |
10,000.00 |
3,600.00 |
3,600.00 |
1.00 |
1.00 |
|
|
| 202-02-07 |
removal of oil drum (lt. of sta. 141+00.000)
|
2   |
ea |
5,000.00 |
10,000.00 |
4,000.00 |
8,000.00 |
1.00 |
2.00 |
|
|
| 202-02-08 |
removal of 15 m x 15 m wood frame residence on slab
(lt. of sta. 157+15) (contains non-friable asbestos) |
1   |
ea |
12,000.00 |
12,000.00 |
3,600.00 |
3,600.00 |
1.00 |
1.00 |
|
|
| 203-01 |
general excavation
|
544,859   |
cu m |
3.29 |
1,792,586.11 |
3.25 |
1,770,791.75 |
5.50 |
2,996,724.50 |
|
|
| 203-02 |
drainage excavation
|
7,142   |
cu m |
10.00 |
71,420.00 |
7.50 |
53,565.00 |
15.00 |
107,130.00 |
|
|
| 203-03 |
muck excavation
|
2,594   |
cu m |
18.00 |
46,692.00 |
9.00 |
23,346.00 |
30.00 |
77,820.00 |
|
|
| 203-04 |
embankment
|
449,650   |
cu m |
3.18 |
1,429,887.00 |
3.40 |
1,528,810.00 |
7.50 |
3,372,375.00 |
|
|
| 203-05-A |
nonplastic embankment (stone)
|
5,383   |
cu m |
50.00 |
269,150.00 |
95.00 |
511,385.00 |
125.00 |
672,875.00 |
|
|
| 204-02 |
temporary hay or straw bales
|
894   |
ea |
15.00 |
13,410.00 |
25.00 |
22,350.00 |
100.00 |
89,400.00 |
|
|
| 204-05-A |
temporary sediment check dams (hay)
|
621   |
ea |
100.00 |
62,100.00 |
160.00 |
99,360.00 |
175.00 |
108,675.00 |
|
|
| 204-05-B |
temporary sediment check dams (stone)
|
94   |
ea |
800.00 |
75,200.00 |
500.00 |
47,000.00 |
600.00 |
56,400.00 |
|
|
| 204-06 |
temporary silt fencing
|
16,308   |
ln m |
16.00 |
260,928.00 |
6.00 |
97,848.00 |
4.00 |
65,232.00 |
|
|
| 204-07 |
temporary stone construction entrance
|
6   |
ea |
5,000.00 |
30,000.00 |
2,200.00 |
13,200.00 |
2,500.00 |
15,000.00 |
|
|
| 302-02-A-01 |
class ii base course (150 mm thick)(stone or recycled
pccp) |
25,150.5 |
sq m |
13.00 |
326,956.50 |
14.00 |
352,107.00 |
20.00 |
503,010.00 |
|
|
| 302-02-D-01 |
class ii base course (300 mm thick)(stone or recycled
pccp) |
510.6 |
sq m |
42.00 |
21,445.20 |
27.00 |
13,786.20 |
50.00 |
25,530.00 |
|
|
| 302-02-E-01 |
class ii base course (350 mm thick)(stone or recycled
pccp) |
43,083.1 |
sq m |
20.00 |
861,662.00 |
28.00 |
1,206,326.80 |
45.00 |
1,938,739.50 |
|
|
| 302-02-G-01 |
class ii base course (200 mm thick)(stone or recycled
pccp) |
229,333.5 |
sq m |
14.00 |
3,210,669.00 |
16.00 |
3,669,336.00 |
30.00 |
6,880,005.00 |
|
|
| 304-01 |
lime
|
3.54 |
Mg |
300.00 |
1,062.00 |
175.00 |
619.50 |
600.00 |
2,124.00 |
|
|
| 304-04-D |
lime treatment (type d) (300 mm thick)
|
234   |
sq m |
17.20 |
4,024.80 |
15.00 |
3,510.00 |
21.00 |
4,914.00 |
|
|
| 304-05 |
lime treatment (type e)
|
2,260.71 |
Mg |
195.00 |
440,838.45 |
20.00 |
45,214.20 |
450.00 |
1,017,319.50 |
|
|
| 305-01-D |
subgrade layer (300 mm thick)
|
299,189   |
sq m |
6.20 |
1,854,971.80 |
7.00 |
2,094,323.00 |
8.00 |
2,393,512.00 |
|
|
| 401-01 |
aggregate surface course (net section)
|
125.0 |
cu m |
150.00 |
18,750.00 |
80.00 |
10,000.00 |
125.00 |
15,625.00 |
|
|
| 401-02 |
aggregate surface course (adjusted vehicular
measurement) |
420   |
cu m |
60.00 |
25,200.00 |
100.00 |
42,000.00 |
145.00 |
60,900.00 |
|
|
| 402-01 |
traffic maintenance aggregate (vehicular measurement)
|
4,150.0 |
cu m |
50.00 |
207,500.00 |
55.00 |
228,250.00 |
60.00 |
249,000.00 |
|
|
| 509-01 |
cold planing asphaltic pavement
|
914   |
sq m |
10.00 |
9,140.00 |
5.00 |
4,570.00 |
20.00 |
18,280.00 |
|
|
| 509-02 |
contractor retained reclaimed asphaltic pavement
|
- 50   |
cu m |
0.10 |
- 5.00 |
0.01 |
- 0.50 |
0.01 |
- 0.50 |
|
|
| 701-01-G |
cross drain pipe (450 mm rcp/pcp)
|
498.3 |
ln m |
188.00 |
93,680.40 |
320.00 |
159,456.00 |
350.00 |
174,405.00 |
|
|
| 701-01-I |
cross drain pipe (600 mm rcp/pcp)
|
30.8 |
ln m |
250.00 |
7,700.00 |
490.00 |
15,092.00 |
600.00 |
18,480.00 |
|
|
| 701-01-K |
cross drain pipe (750 mm rcp/pcp)
|
72.2 |
ln m |
290.00 |
20,938.00 |
495.00 |
35,739.00 |
625.00 |
45,125.00 |
|
|
| 701-01-M |
cross drain pipe (900 mm rcp/pcp)
|
339.5 |
ln m |
375.00 |
127,312.50 |
500.00 |
169,750.00 |
650.00 |
220,675.00 |
|
|
| 701-01-N |
cross drain pipe (1050 mm rcp/pcp)
|
569.4 |
ln m |
500.00 |
284,700.00 |
550.00 |
313,170.00 |
700.00 |
398,580.00 |
|
|
| 701-01-O |
cross drain pipe (1200 mm rcp/pcp)
|
139.0 |
ln m |
580.00 |
80,620.00 |
685.00 |
95,215.00 |
1,000.00 |
139,000.00 |
|
|
| 701-02-E |
cross drain pipe arch (750 mm equiv. rcpa)
|
235.6 |
ln m |
350.00 |
82,460.00 |
400.00 |
94,240.00 |
650.00 |
153,140.00 |
|
|
| 701-03-F |
storm drain pipe (375 mm rcp/pcp)
|
1,581.0 |
ln m |
182.00 |
287,742.00 |
185.00 |
292,485.00 |
275.00 |
434,775.00 |
|
|
| 701-03-G |
storm drain pipe (450 mm rcp/pcp)
|
671.4 |
ln m |
188.00 |
126,223.20 |
220.00 |
147,708.00 |
300.00 |
201,420.00 |
|
|
| 701-03-I |
storm drain pipe (600 mm rcp/pcp)
|
775.9 |
ln m |
250.00 |
193,975.00 |
245.00 |
190,095.50 |
325.00 |
252,167.50 |
|
|
| 701-03-K |
storm drain pipe (750 mm rcp/pcp)
|
126.7 |
ln m |
290.00 |
36,743.00 |
325.00 |
41,177.50 |
400.00 |
50,680.00 |
|
|
| 701-05-G |
side drain pipe (450 mm)
|
689.5 |
ln m |
188.00 |
129,626.00 |
225.00 |
155,137.50 |
250.00 |
172,375.00 |
|
|
| 701-05-I |
side drain pipe (600 mm)
|
166.8 |
ln m |
250.00 |
41,700.00 |
200.00 |
33,360.00 |
325.00 |
54,210.00 |
|
|
| 701-05-I-01 |
side drain pipe (600 mm)(outfall)
|
46.4 |
ln m |
250.00 |
11,600.00 |
280.00 |
12,992.00 |
350.00 |
16,240.00 |
|
|
| 701-05-K |
side drain pipe (750 mm)
|
107.9 |
ln m |
290.00 |
31,291.00 |
230.00 |
24,817.00 |
400.00 |
43,160.00 |
|
|
| 701-05-M |
side drain pipe (900 mm)
|
16.5 |
ln m |
375.00 |
6,187.50 |
325.00 |
5,362.50 |
600.00 |
9,900.00 |
|
|
| 701-05-N |
side drain pipe (1050 mm)
|
24.4 |
ln m |
500.00 |
12,200.00 |
550.00 |
13,420.00 |
750.00 |
18,300.00 |
|
|
| 701-05-O |
side drain pipe (1200 mm)
|
96.4 |
ln m |
580.00 |
55,912.00 |
550.00 |
53,020.00 |
850.00 |
81,940.00 |
|
|
| 701-06-H |
side drain pipe arch (1200 mm equiv. rcpa)
|
9.8 |
ln m |
700.00 |
6,860.00 |
550.00 |
5,390.00 |
1,250.00 |
12,250.00 |
|
|
| 701-09-N |
fabricating pipe fittings (1050 mm x 1050 mm x 450 mm)
|
1   |
ea |
2,200.00 |
2,200.00 |
3,000.00 |
3,000.00 |
3,800.00 |
3,800.00 |
|
|
| 701-09-O |
fabricating pipe fittings (1200 mm x 1200 mm x 450 mm)
|
2   |
ea |
2,200.00 |
4,400.00 |
3,200.00 |
6,400.00 |
4,000.00 |
8,000.00 |
|
|
| 701-09-Q |
fabricating pipe fittings (1500 mm x 1500 mm x 450 mm)
|
1   |
ea |
2,200.00 |
2,200.00 |
3,500.00 |
3,500.00 |
7,000.00 |
7,000.00 |
|
|
| 702-02-F-01 |
manholes (mh-01)(modified)
|
1   |
ea |
11,000.00 |
11,000.00 |
12,000.00 |
12,000.00 |
5,000.00 |
5,000.00 |
|
|
| 702-03-A |
catch basins (cb-01m)
|
50   |
ea |
2,200.00 |
110,000.00 |
3,000.00 |
150,000.00 |
5,500.00 |
275,000.00 |
|
|
| 702-03-C |
catch basins (cb-06m)
|
65   |
ea |
2,700.00 |
175,500.00 |
4,000.00 |
260,000.00 |
7,000.00 |
455,000.00 |
|
|
| 702-03-D |
catch basins (cb-07m)
|
37   |
ea |
4,300.00 |
159,100.00 |
5,500.00 |
203,500.00 |
11,000.00 |
407,000.00 |
|
|
| 702-03-F |
catch basins (cb-08m)
|
2   |
ea |
6,500.00 |
13,000.00 |
8,500.00 |
17,000.00 |
14,000.00 |
28,000.00 |
|
|
| 702-04-A |
adjusting manholes
|
5   |
ea |
1,000.00 |
5,000.00 |
600.00 |
3,000.00 |
2,500.00 |
12,500.00 |
|
|
| 702-07-A |
cross drain safety end (type 1)
|
1   |
ea |
1,600.00 |
1,600.00 |
1,600.00 |
1,600.00 |
2,000.00 |
2,000.00 |
|
|
| 702-07-B |
cross drain safety end (type 2)
|
6   |
ea |
6,500.00 |
39,000.00 |
7,500.00 |
45,000.00 |
7,500.00 |
45,000.00 |
|
|
| 703-01 |
shoulder underdrain systems
|
3,300   |
ln m |
36.00 |
118,800.00 |
23.00 |
75,900.00 |
30.00 |
99,000.00 |
|
|
| 704-03 |
blocked out guard rail
|
655.32 |
ln m |
55.00 |
36,042.60 |
53.00 |
34,731.96 |
65.00 |
42,595.80 |
|
|
| 704-08-B |
guard rail transitions (double thrie beam)
|
99.06 |
ln m |
166.00 |
16,443.96 |
175.00 |
17,335.50 |
185.00 |
18,326.10 |
|
|
| 704-11-A |
guard rail end treatment (flared)
|
13   |
each |
2,000.00 |
26,000.00 |
2,000.00 |
26,000.00 |
2,100.00 |
27,300.00 |
|
|
| 705-01 |
barbed wire fence
|
2,179   |
ln m |
18.00 |
39,222.00 |
17.00 |
37,043.00 |
18.00 |
39,222.00 |
|
|
| 705-02 |
combination mesh & barbed wire fence
|
226   |
ln m |
18.00 |
4,068.00 |
19.00 |
4,294.00 |
20.00 |
4,520.00 |
|
|
| 705-04 |
single swinging driveway gates
|
3   |
ea |
500.00 |
1,500.00 |
500.00 |
1,500.00 |
500.00 |
1,500.00 |
|
|
| 705-09 |
rebuilt fence
|
1,008   |
ln m |
22.00 |
22,176.00 |
22.00 |
22,176.00 |
25.00 |
25,200.00 |
|
|
| 706-02-C |
concrete drive (150 mm thick)
|
654.7 |
sq m |
55.00 |
36,008.50 |
55.00 |
36,008.50 |
70.00 |
45,829.00 |
|
|
| 708-01 |
right-of-way monument
|
157   |
ea |
110.00 |
17,270.00 |
400.00 |
62,800.00 |
135.00 |
21,195.00 |
|
|
| 708-02 |
right-of-way monument witness post
|
157   |
ea |
110.00 |
17,270.00 |
400.00 |
62,800.00 |
85.00 |
13,345.00 |
|
|
| 712-01-C |
concrete cast-in-place revetment (150 mm thick)
|
215   |
sq m |
75.00 |
16,125.00 |
95.00 |
20,425.00 |
105.00 |
22,575.00 |
|
|
| 712-03 |
stone revetment
|
18   |
sq m |
100.00 |
1,800.00 |
95.00 |
1,710.00 |
175.00 |
3,150.00 |
|
|
| 712-04 |
flexible revetment
|
3,431   |
sq m |
70.00 |
240,170.00 |
60.00 |
205,860.00 |
75.00 |
257,325.00 |
|
|
| 713-01 |
temporary signs & barricades
|
lump |
lump |
280,000.00 |
280,000.00 |
260,000.00 |
260,000.00 |
1,000,000.00 |
1,000,000.00 |
|
|
| 713-05-A |
temporary pavement markings (solid line)(100 mm width)
|
34.147 |
km |
375.00 |
12,805.13 |
500.00 |
17,073.50 |
600.00 |
20,488.20 |
|
|
| 713-05-A-01 |
temporary pavement markings (solid line)(100 mm width)
(type i removable) |
35.227 |
km |
10,000.00 |
352,270.00 |
500.00 |
17,613.50 |
4,500.00 |
158,521.50 |
|
|
| 713-08 |
temporary precast concrete barrier (contractor
furnished) |
100   |
ea |
700.00 |
70,000.00 |
850.00 |
85,000.00 |
1,100.00 |
110,000.00 |
|
|
| 713-09 |
temporary precast concrete barrier (department
furnished) |
350   |
ea |
150.00 |
52,500.00 |
275.00 |
96,250.00 |
400.00 |
140,000.00 |
|
|
| 716-01-A |
mulch (vegetative)
|
13.2 |
hctr |
1,500.00 |
19,800.00 |
1,400.00 |
18,480.00 |
1,400.00 |
18,480.00 |
|
|
| 717-01 |
seeding
|
4,924   |
kg |
12.00 |
59,088.00 |
13.00 |
64,012.00 |
12.00 |
59,088.00 |
|
|
| 717-01-A |
seeding (u.s. forest service)
|
308   |
kg |
12.00 |
3,696.00 |
13.00 |
4,004.00 |
12.00 |
3,696.00 |
|
|
| 718-01 |
fertilizer
|
162,218   |
kg |
0.59 |
95,708.62 |
0.65 |
105,441.70 |
0.65 |
105,441.70 |
|
|
| 718-01-A |
fertilizer (u.s. forest service)
|
5,034   |
kg |
0.59 |
2,970.06 |
0.65 |
3,272.10 |
0.65 |
3,272.10 |
|
|
| 718-02-A |
agricultural lime (u.s. forest service)
|
36.8 |
kg |
90.00 |
3,312.00 |
1.10 |
40.48 |
1.00 |
36.80 |
|
|
| 720-01-A |
erosion control system, slope protection (type a)
|
137,095   |
sq m |
1.34 |
183,707.30 |
1.50 |
205,642.50 |
1.25 |
171,368.75 |
|
|
| 720-01-C |
erosion control system, flexible channel liner (type c)
|
14,408   |
sq m |
2.00 |
28,816.00 |
1.80 |
25,934.40 |
1.60 |
23,052.80 |
|
|
| 720-01-D |
erosion control system, flexible channel liner (type d)
|
14,999   |
sq m |
2.00 |
29,998.00 |
1.80 |
26,998.20 |
1.60 |
23,998.40 |
|
|
| 721-01 |
asphalt mulch
|
432,297   |
l |
0.72 |
311,253.84 |
0.55 |
237,763.35 |
0.50 |
216,148.50 |
|
|
| 722-02 |
project site laboratory (equipped)
|
1   |
ea |
50,000.00 |
50,000.00 |
60,000.00 |
60,000.00 |
30,000.00 |
30,000.00 |
|
|
| 724-01-B |
pavement patching (300 mm minimum thickness)
|
343   |
sq m |
100.00 |
34,300.00 |
90.00 |
30,870.00 |
250.00 |
85,750.00 |
|
|
| 725-01 |
temporary detour roads
|
233.6 |
ln m |
400.00 |
93,440.00 |
500.00 |
116,800.00 |
750.00 |
175,200.00 |
|
|
| 726-01 |
bedding material
|
2,496.2 |
cu m |
80.00 |
199,696.00 |
65.00 |
162,253.00 |
145.00 |
361,949.00 |
|
|
| 727-01 |
mobilization
|
lump |
lump |
2,700,000.00 |
2,700,000.00 |
3,600,000.00 |
3,600,000.00 |
4,500,000.00 |
4,500,000.00 |
|
|
| 729-01-A |
sign (type a)(r1-1)((0.762 m x 0.762 m)
|
1.20 |
sq m |
150.00 |
180.00 |
140.00 |
168.00 |
150.00 |
180.00 |
|
|
| 729-01-B |
sign (type a)(r1-2)((0.914 m x 0.914 m)
|
0.36 |
sq m |
500.00 |
180.00 |
450.00 |
162.00 |
500.00 |
180.00 |
|
|
| 729-16-B |
object marker assembly (type 2)
|
40   |
ea |
65.00 |
2,600.00 |
80.00 |
3,200.00 |
80.00 |
3,200.00 |
|
|
| 729-16-C |
object marker assembly (type 3)
|
20   |
ea |
76.00 |
1,520.00 |
80.00 |
1,600.00 |
80.00 |
1,600.00 |
|
|
| 729-17 |
milepost assembly (ground mounted)
|
18   |
ea |
126.00 |
2,268.00 |
80.00 |
1,440.00 |
125.00 |
2,250.00 |
|
|
| 729-19-B |
dead end road installation (type b)
|
2   |
ea |
1,250.00 |
2,500.00 |
5,500.00 |
11,000.00 |
3,500.00 |
7,000.00 |
|
|
| 729-21 |
u-channel post (12 foot)
|
2   |
ea |
130.00 |
260.00 |
140.00 |
280.00 |
125.00 |
250.00 |
|
|
| 731-02 |
reflectorized raised pavement markers
|
4,486   |
ea |
5.00 |
22,430.00 |
6.00 |
26,916.00 |
6.00 |
26,916.00 |
|
|
| 732-01-A |
plastic pavement striping (100 mm width)
|
3,222   |
ln m |
1.50 |
4,833.00 |
1.50 |
4,833.00 |
2.00 |
6,444.00 |
|
|
| 732-01-C |
plastic pavement striping (200 mm width)
|
955   |
ln m |
3.00 |
2,865.00 |
3.00 |
2,865.00 |
7.50 |
7,162.50 |
|
|
| 732-01-E |
plastic pavement striping (600 mm width)
|
1,156   |
ln m |
8.50 |
9,826.00 |
10.00 |
11,560.00 |
12.00 |
13,872.00 |
|
|
| 732-02-A |
plastic pavement striping (solid line)(100 mm width)
|
59.170 |
km |
1,500.00 |
88,755.00 |
1,500.00 |
88,755.00 |
1,500.00 |
88,755.00 |
|
|
| 732-03-C |
plastic pavement striping (broken line)(200 mm width)
|
0.021 |
km |
1,007.62 |
21.16 |
1,100.00 |
23.10 |
3,000.00 |
63.00 |
|
|
| 732-04-A |
plastic pavement legends & symbols (arrow)
|
58   |
ea |
1,000.00 |
58,000.00 |
200.00 |
11,600.00 |
400.00 |
23,200.00 |
|
|
| 732-04-B |
plastic pavement legends & symbols (double arrow)
|
10   |
ea |
200.00 |
2,000.00 |
200.00 |
2,000.00 |
400.00 |
4,000.00 |
|
|
| 732-04-C |
plastic pavement legends & symbols (only)
|
32   |
ea |
200.00 |
6,400.00 |
200.00 |
6,400.00 |
400.00 |
12,800.00 |
|
|
| 732-04-D |
plastic pavement legends & symbols (rr crossing)
|
8   |
ea |
425.00 |
3,400.00 |
450.00 |
3,600.00 |
750.00 |
6,000.00 |
|
|
| 732-05 |
removal of existing markings
|
2.430 |
km |
2,700.00 |
6,561.00 |
6,500.00 |
15,795.00 |
5,000.00 |
12,150.00 |
|
|
| 735-01 |
mailboxes
|
48   |
ea |
25.00 |
1,200.00 |
50.00 |
2,400.00 |
15.00 |
720.00 |
|
|
| 735-02 |
mailbox supports (single)
|
48   |
ea |
150.00 |
7,200.00 |
150.00 |
7,200.00 |
150.00 |
7,200.00 |
|
|
| 736-01 |
trenching and backfilling
|
18   |
ln m |
25.00 |
450.00 |
26.00 |
468.00 |
30.00 |
540.00 |
|
|
| 736-03-A |
jacked or bored conduit (51.0 mm , sch. 80)
|
25   |
ln m |
100.00 |
2,500.00 |
100.00 |
2,500.00 |
110.00 |
2,750.00 |
|
|
| 736-04-A |
signal support (9.1 m strain pole)
|
4   |
ea |
8,000.00 |
32,000.00 |
7,500.00 |
30,000.00 |
7,500.00 |
30,000.00 |
|
|
| 736-05-B |
signal heads (1-section y)(l.e.d.)
|
4   |
each |
800.00 |
3,200.00 |
800.00 |
3,200.00 |
1,000.00 |
4,000.00 |
|
|
| 736-05-C |
signal heads (1-section r)(l.e.d.)
|
4   |
each |
800.00 |
3,200.00 |
800.00 |
3,200.00 |
1,000.00 |
4,000.00 |
|
|
| 736-06-A |
signal service (pole mounted for flasher switch
assembly) |
1   |
ea |
1,200.00 |
1,200.00 |
1,200.00 |
1,200.00 |
1,500.00 |
1,500.00 |
|
|
| 736-10-A |
underground junction box (type f)
|
2   |
ea |
700.00 |
1,400.00 |
650.00 |
1,300.00 |
700.00 |
1,400.00 |
|
|
| 736-10-B |
underground junction box (type h)
|
1   |
ea |
1,700.00 |
1,700.00 |
1,600.00 |
1,600.00 |
2,000.00 |
2,000.00 |
|
|
| 736-11-A |
conduit (76.2 mm, sch. 80)
|
25   |
ln m |
22.51 |
562.75 |
22.00 |
550.00 |
25.00 |
625.00 |
|
|
| 736-12-A |
conductor (3c power)
|
35   |
ln m |
14.00 |
490.00 |
13.00 |
455.00 |
15.00 |
525.00 |
|
|
| 739-01 |
hydro-seeding
|
33.9 |
hctr |
2,000.00 |
67,800.00 |
2,200.00 |
74,580.00 |
2,000.00 |
67,800.00 |
|
|
| 739-01-A |
hydro-seeding (u.s. forest service)
|
5.4 |
hctr |
2,000.00 |
10,800.00 |
2,200.00 |
11,880.00 |
2,000.00 |
10,800.00 |
|
|
| 740-01 |
construction layout
|
lump |
lump |
550,000.00 |
550,000.00 |
380,000.00 |
380,000.00 |
450,000.00 |
450,000.00 |
|
|
| 740-02 |
utility oversight and coordination
|
lump |
lump |
75,000.00 |
75,000.00 |
60,000.00 |
60,000.00 |
50,000.00 |
50,000.00 |
|
|
| 744-01 |
traffic control management
|
lump |
lump |
75,000.00 |
75,000.00 |
160,000.00 |
160,000.00 |
150,000.00 |
150,000.00 |
|
|
| 804-01-B |
precast concrete piles (350 mm)
|
930.0 |
ln m |
155.00 |
144,150.00 |
135.00 |
125,550.00 |
150.00 |
139,500.00 |
|
|
| 804-01-C |
precast concrete piles (400 mm)
|
2,142.0 |
ln m |
200.00 |
428,400.00 |
140.00 |
299,880.00 |
190.00 |
406,980.00 |
|
|
| 804-01-D |
precast concrete piles (450 mm)
|
1,224.0 |
ln m |
262.00 |
320,688.00 |
145.00 |
177,480.00 |
250.00 |
306,000.00 |
|
|
| 804-05 |
precast concrete test piles
|
1   |
ea |
1.00 |
1.00 |
20,000.00 |
20,000.00 |
1.00 |
1.00 |
|
|
| 804-09 |
loading test piles
|
1   |
ea |
1.00 |
1.00 |
5,000.00 |
5,000.00 |
1.00 |
1.00 |
|
|
| 804-13 |
precast concrete indicator piles
|
3   |
ea |
1.00 |
3.00 |
10,000.00 |
30,000.00 |
1.00 |
3.00 |
|
|
| 804-17 |
dynamic monitoring
|
1   |
ea |
2,000.00 |
2,000.00 |
1,000.00 |
1,000.00 |
5,500.00 |
5,500.00 |
|
|
| 805-01-B |
class a concrete (box culvert headwalls)
|
130.37 |
cu m |
1,400.00 |
182,518.00 |
1,400.00 |
182,518.00 |
1,250.00 |
162,962.50 |
|
|
| 805-01-F |
class a concrete (bents)
|
238.60 |
cu m |
860.00 |
205,196.00 |
850.00 |
202,810.00 |
900.00 |
214,740.00 |
|
|
| 805-03 |
class aa concrete
|
962.00 |
cu m |
750.00 |
721,500.00 |
650.00 |
625,300.00 |
750.00 |
721,500.00 |
|
|
| 805-12-E-01 |
reinforced concrete box culverts (extension)(1200 mm x
1200 mm) (cast-in-place) |
643.10 |
ln m |
1,500.00 |
964,650.00 |
1,600.00 |
1,028,960.00 |
1,500.00 |
964,650.00 |
|
|
| 805-12-I-01 |
reinforced concrete box culverts (extension)(1500 mm x
1500 mm) (cast-in-place) |
327.80 |
ln m |
1,700.00 |
557,260.00 |
2,200.00 |
721,160.00 |
1,600.00 |
524,480.00 |
|
|
| 805-12-S-01 |
reinforced concrete box culverts (extension)(2400 mm x
2400 mm) (cast-in-place) |
107.40 |
ln m |
2,600.00 |
279,240.00 |
2,700.00 |
289,980.00 |
2,800.00 |
300,720.00 |
|
|
| 806-01 |
deformed reinforcing steel
|
132,086   |
kg |
2.00 |
264,172.00 |
1.70 |
224,546.20 |
2.00 |
264,172.00 |
|
|
| 810-01 |
concrete railing (f shape pl 2)
|
444.00 |
ln m |
200.00 |
88,800.00 |
220.00 |
97,680.00 |
200.00 |
88,800.00 |
|
|
| 813-01 |
concrete approach slabs
|
1,476.00 |
sq m |
185.00 |
273,060.00 |
220.00 |
324,720.00 |
200.00 |
295,200.00 |
|
|
| S-001 |
sawcutting asphaltic concrete pavement
|
231   |
ln m |
13.00 |
3,003.00 |
35.00 |
8,085.00 |
20.00 |
4,620.00 |
|
|
| S-002 |
rumble strips (ground-in)
|
51.8 |
km |
400.00 |
20,720.00 |
600.00 |
31,080.00 |
600.00 |
31,080.00 |
|
|
| S-003 |
flasher switch (flasher assembly; 2 circuit; pole
mounted cabinet) |
1   |
each |
8,000.00 |
8,000.00 |
7,200.00 |
7,200.00 |
10,000.00 |
10,000.00 |
|
|
| S-004 |
restoration of the camp claiborne entrance
|
lump |
lump |
8,000.00 |
8,000.00 |
22,000.00 |
22,000.00 |
25,000.00 |
25,000.00 |
|
|
| S-101 |
retroreflective sheeting panels
|
lump |
lump |
8,000.00 |
8,000.00 |
4,500.00 |
4,500.00 |
10,000.00 |
10,000.00 |
|
|
| | SUBTOTAL GENERAL |
|
|
|
25,652,494.88 |
|
27,309,734.32 |
|
39,448,810.15 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A |
pavement options
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A1 |
superpave asphaltic concrete pavement
|
|
|
|
|
|
|
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
102,830.9 |
Mg |
69.00 |
7,095,332.10 |
76.00 |
7,815,148.40 |
105.00 |
10,797,244.50 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
14,038.2 |
Mg |
80.50 |
1,130,075.10 |
95.00 |
1,333,629.00 |
115.00 |
1,614,393.00 |
|
|
| 707-03 |
combination concrete curb and gutter
|
3,264.9 |
ln m |
47.00 |
153,450.30 |
60.00 |
195,894.00 |
65.00 |
212,218.50 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(100 mm width)
|
31.971 |
km |
525.00 |
16,784.78 |
600.00 |
19,182.60 |
600.00 |
19,182.60 |
|
|
| | SUBTOTAL ALT A1 |
|
|
|
8,395,642.28 |
|
9,363,854.00 |
|
12,643,038.60 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| ALTERNATE A2 |
portland cement concrete pavement
|
|
|
|
|
|
|
|
|
|
|
| 502-01 |
superpave asphaltic concrete
|
8,893.8 |
Mg |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
|
|
| 502-01-A |
superpave asphaltic concrete, drives, turnouts and
miscellaneous |
1,639.5 |
Mg |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
|
|
| 601-01-G |
portland cement concrete pavement (200 mm thick)
|
201,651.1 |
sq m |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
|
|
| 601-02-G |
portland cement concrete pavement (200 mm thick)
(crossovers & turnouts) |
26,890.9 |
sq m |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
|
|
| 601-04 |
portland cement concrete pavement coring
|
252   |
ea |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
|
|
| 707-01 |
concrete curb
|
3,242.6 |
ln m |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
|
|
| 707-03 |
combination concrete curb and gutter
|
22.3 |
ln m |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
|
|
| 732-03-A |
plastic pavement striping (broken line)(100 mm width)
|
31.971 |
km |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
|
|
| 732-03-A-01 |
plastic pvmt striping(broken line)(100mmwidth)
preformed marking tape (type v) |
31.971 |
km |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
0.00 |
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
| | ITEM TOTAL (CONSTRUCTION BID) |
|
|
|
34,048,137.16 |
|
36,673,588.32 |
|
52,091,848.75 |
|
|
| | Number of Days Bid at $1,000 per day. |
|
|
850 |
850,000.00 |
850 |
850,000.00 |
975 |
975,000.00 |
|
|
| | Life Cycle Cost |
|
|
|
3,495,500.00 |
|
3,495,500.00 |
|
3,495,500.00 |
|
|
| | TOTAL BID |
|
|
|
38,393,637.16 |
|
41,019,088.32 |
|
56,562,348.75 |
|
|
|