February 06, 2014 Error processing SSI file

Letting of 9/27/2006 LA DOTD Headquarters


 
go back
Go Back
 
Lead Project: 014-03-0022
Parish: ALLEN
Routes: US 165
Description: KINDER - OBERLIN
Type Const: grading, drainage structures, lime trmt, subgrade layer, class ii bc, superpave
acp (a-1), pccp (alt. a-2), concrete slab span bridge and related work
Estimated Construction Cost: $33,380,549.57
Maximum Number of Days Allowed for Construction: 950
Calculated Daily User Cost: $1,000.00
 
RankLicenseBidderConstruction Bid Bidder's Proposed
Contract Time
Life Cycle
Cost
Total Bid
1 12312 GILCHRIST CONSTRUCTION CO. LLC $30,166,026.30 825$1,359,000$32,350,026.30
2 04089 H & S CONSTRUCTION CO., INC. $33,079,074.67 950$1,359,000$35,388,074.67
3 42076 AUSTIN BRIDGE & ROAD, LP $39,565,726.60 950$2,614,800$43,130,526.60
 
Item Number Item Description Quantity Unit of Measure - 1 -
GILCHRIST CONSTRUCTION CO. LLC
- 2 -
H & S CONSTRUCTION CO., INC.
- 3 -
AUSTIN BRIDGE & ROAD, LP

 
Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount Unit PriceTotal Amount
201-01 clearing & grubbing lump      LUMP 600,000.00 600,000.00 985,000.00 985,000.00 1,100,000.00 1,100,000.00    
202-01 removal of structures & obstructions lump      LUMP 50,000.00 50,000.00 150,000.00 150,000.00 23,000.00 23,000.00    
202-02-B-01 removal of concrete box culverts (sta. 254+80; 4-9' x
9' x 85')
1      EACH 10,000.00 10,000.00 5,000.00 5,000.00 67,000.00 67,000.00    
202-02-B-02 removal of concrete box culverts (sta. 284+21; 2-9' x
9' x 65')
1      EACH 10,000.00 10,000.00 4,000.00 4,000.00 26,000.00 26,000.00    
202-02-D removal of concrete walks & drives 2,643      SQYD 5.50 14,536.50 8.00 21,144.00 28.00 74,004.00    
202-02-E removal of concrete curbs 1,295.2    LNFT 7.50 9,714.00 8.00 10,361.60 23.00 29,789.60    
202-02-G removal of surfacing & stabilized base 27,332.0    SQYD 4.00 109,328.00 6.00 163,992.00 3.90 106,594.80    
202-02-H removal of guard rail (lt. of sta. 555+12) 524      LNFT 5.00 2,620.00 8.00 4,192.00 11.00 5,764.00    
202-02-I removal of ornamental fence (lt. of sta. 393+26.54 to
sta. 403+38.13)
1,121      LNFT 15.00 16,815.00 10.00 11,210.00 56.00 62,776.00    
202-02-J removal of above ground propane storage tank (lt. of
sta. 219+94)
1      EACH 1,000.00 1,000.00 100.00 100.00 1,000.00 1,000.00    
202-02-01 removal of 40' x 35' railroad caboose with wooden
addition (lt. of sta. 220+00)
1      EACH 5,000.00 5,000.00 2,000.00 2,000.00 4,000.00 4,000.00    
202-02-02 removal of 62' x 39' wood frame & metal shed on piers
(lt. of sta. 233+15)
1      EACH 5,000.00 5,000.00 500.00 500.00 7,000.00 7,000.00    
202-02-03 removal of dilapidated school bus (lt. of sta. 235+05) 1      EACH 500.00 500.00 500.00 500.00 280.00 280.00    
202-02-04 removal of 14' x 75' mobile home (lt. of sta. 242+57) 1      EACH 2,000.00 2,000.00 100.00 100.00 1,000.00 1,000.00    
202-02-05 removal of 12' x 56' mobile home (lt. of sta. 243+58) 1      EACH 2,000.00 2,000.00 100.00 100.00 1,000.00 1,000.00    
202-02-06 removal of 18' x 20' metal shed (lt. of sta. 269+92) 1      EACH 500.00 500.00 100.00 100.00 390.00 390.00    
202-02-07 removal of 30' x 40' wood frame builing on piers (lt.
of sta. 270+00)
1      EACH 3,500.00 3,500.00 100.00 100.00 3,000.00 3,000.00    
202-02-08 removal of 14' x 20' metal shed (lt. of sta. 270+12) 1      EACH 400.00 400.00 100.00 100.00 340.00 340.00    
202-02-09 removal of 14' x 20' metal shed (lt. of sta. 270+78) 1      EACH 400.00 400.00 100.00 100.00 340.00 340.00    
202-02-10 removal of 35' x 60' wood frame building on piers (lt.
of sta. 278+00)
1      EACH 6,000.00 6,000.00 1,000.00 1,000.00 6,000.00 6,000.00    
202-02-11 removal of 30' x 70' brick residence on slab (lt. of
sta. 294+00) (contains non-friable asbestos)
1      EACH 6,000.00 6,000.00 6,500.00 6,500.00 33,000.00 33,000.00    
202-02-12 removal of 44' x 16' wood frame residence on piers
(lt. of sta. 303+00)
1      EACH 2,500.00 2,500.00 1,500.00 1,500.00 2,000.00 2,000.00    
202-02-13 removal of 22' x 18' metal shed (lt. of sta. 303+50) 1      EACH 2,000.00 2,000.00 100.00 100.00 4,500.00 4,500.00    
202-02-14 removal of 66' x 29' brick residence on slab (lt. of
sta. 304+00)
1      EACH 6,000.00 6,000.00 6,000.00 6,000.00 5,000.00 5,000.00    
202-02-15 removal of 40' x 25' wood frame residence on slab (lt.
of sta. 305+50) (contains non-friable asbestos)
1      EACH 4,500.00 4,500.00 3,000.00 3,000.00 16,000.00 16,000.00    
202-02-16 removal of 26' x 12' wood frame shed (lt. of sta.
306+00)
1      EACH 1,000.00 1,000.00 100.00 100.00 880.00 880.00    
202-02-17 removal of 15' x 25' wood frame cabins on piers (lt.
of sta. 313+00)
4      EACH 2,000.00 8,000.00 10.00 40.00 110.00 440.00    
202-02-18 removal of 135' x 30' metal gas station canopy (lt. of
sta. 325+50)
1      EACH 4,000.00 4,000.00 5,000.00 5,000.00 5,000.00 5,000.00    
202-02-19 removal of sewer treatment plant (lt. of sta. 389+00) 1      EACH 2,000.00 2,000.00 3,000.00 3,000.00 1,000.00 1,000.00    
202-02-20 removal of sewer treatment plant (lt. of sta. 393+00) 1      EACH 1,500.00 1,500.00 3,000.00 3,000.00 1,000.00 1,000.00    
202-02-21 removal of 28' x 30' storage building (lt. of sta
458+00)
1      EACH 2,000.00 2,000.00 100.00 100.00 950.00 950.00    
202-02-22 removal of 17' x 8' metal shed (lt. of sta. 458+00) 1      EACH 1,000.00 1,000.00 100.00 100.00 160.00 160.00    
202-02-23 removal of 90' x 50' wood frame residence on slab (lt.
of sta. 459+50)
1      EACH 10,000.00 10,000.00 7,500.00 7,500.00 13,000.00 13,000.00    
202-02-24 removal of 45' x 78' brick residence on slab (lt. of
sta. 572+00) (contains non-friable asbestos)
1      EACH 8,500.00 8,500.00 4,500.00 4,500.00 56,000.00 56,000.00    
202-02-25 removal of 90' x 38' tin building on slab (lt. of sta.
575+00)
1      EACH 7,000.00 7,000.00 6,500.00 6,500.00 8,000.00 8,000.00    
202-02-26 removal of 22' x 33' wood frame residence on piers
(lt. of sta. 595+00)
1      EACH 4,000.00 4,000.00 500.00 500.00 2,000.00 2,000.00    
202-02-27 removal of 18' x 58' wood frame residence on piers
(lt. of sta. 597+50)
1      EACH 4,500.00 4,500.00 500.00 500.00 3,000.00 3,000.00    
202-02-28 removal of 60' x 60' wood frame residence on piers
(lt. of sta. 599+50) (contains non-friable
asbestos)
1      EACH 9,000.00 9,000.00 500.00 500.00 57,000.00 57,000.00    
202-02-29 removal of 30' x 50' wood frame residence on piers
(lt. of sta. 601+00)
1      EACH 5,000.00 5,000.00 500.00 500.00 4,000.00 4,000.00    
202-03-01 relocation of assorted shrubbery (lt. of sta.
348+00 to sta. 363+50)
120      EACH 25.00 3,000.00 100.00 12,000.00 230.00 27,600.00    
202-03-02 relocation of gate (lt. of sta. 542+08) 1      EACH 2,000.00 2,000.00 4,000.00 4,000.00 2,500.00 2,500.00    
203-01 general excavation 104,521      CUYD 3.85 402,405.85 5.75 600,995.75 4.20 438,988.20    
203-02 drainage excavation 11,587      CUYD 7.75 89,799.25 14.00 162,218.00 7.00 81,109.00    
203-03 muck excavation 21,000      CUYD 7.00 147,000.00 9.00 189,000.00 8.00 168,000.00    
203-04 embankment 231,197      CUYD 9.00 2,080,773.00 11.00 2,543,167.00 14.00 3,236,758.00    
203-09 geotexile fabric 3,652      SQYD 1.60 5,843.20 2.00 7,304.00 2.70 9,860.40    
204-02 temporary hay or straw bales 742      EACH 20.00 14,840.00 7.50 5,565.00 9.00 6,678.00    
204-05-A temporary sediment check dams (hay) 10      EACH 200.00 2,000.00 125.00 1,250.00 110.00 1,100.00    
204-05-B temporary sediment check dams (stone) 25      EACH 700.00 17,500.00 1,000.00 25,000.00 110.00 2,750.00    
204-06 temporary silt fencing 3,247      LNFT 2.00 6,494.00 1.45 4,708.15 2.30 7,468.10    
204-07 temporary stone construction entrance 8      EACH 2,000.00 16,000.00 3,000.00 24,000.00 3,000.00 24,000.00    
304-05 lime treatment (type e) 1,154.00   TON 50.00 57,700.00 130.00 150,020.00 250.00 288,500.00    
401-02 aggregate surface course (adjusted vehicular
measurement)
423      CUYD 125.00 52,875.00 80.00 33,840.00 92.00 38,916.00    
402-01 traffic maintenance aggregate (vehicular measurement) 450.0    CUYD 75.00 33,750.00 100.00 45,000.00 92.00 41,400.00    
701-01-F cross drain pipe (15" rcp/pcp) 2,363      LNFT 82.00 193,766.00 80.00 189,040.00 59.00 139,417.00    
701-01-I cross drain pipe (24" rcp/pcp) 164      LNFT 100.00 16,400.00 90.00 14,760.00 79.00 12,956.00    
701-01-K cross drain pipe (30" rcp/pcp) 253      LNFT 125.00 31,625.00 100.00 25,300.00 96.00 24,288.00    
701-01-M cross drain pipe (36" rcp/pcp) 156      LNFT 130.00 20,280.00 150.00 23,400.00 120.00 18,720.00    
701-01-N cross drain pipe (42" rcp/pcp) 288      LNFT 150.00 43,200.00 175.00 50,400.00 170.00 48,960.00    
701-02-G cross drain pipe arch (42" equiv. rcpa) 78      LNFT 250.00 19,500.00 220.00 17,160.00 160.00 12,480.00    
701-03-F storm drain pipe (15" rcp/pcp) 806      LNFT 80.00 64,480.00 50.00 40,300.00 59.00 47,554.00    
701-03-G storm drain pipe (18" rcp/pcp) 204      LNFT 55.00 11,220.00 60.00 12,240.00 62.00 12,648.00    
701-03-I storm drain pipe (24" rcp/pcp) 4,823      LNFT 65.00 313,495.00 70.00 337,610.00 79.00 381,017.00    
701-03-K storm drain pipe (30" rcp/pcp) 6,050      LNFT 80.00 484,000.00 80.00 484,000.00 96.00 580,800.00    
701-03-M storm drain pipe (36" rcp/pcp) 128      LNFT 150.00 19,200.00 110.00 14,080.00 120.00 15,360.00    
701-03-N storm drain pipe (42" rcp/pcp) 6,451      LNFT 110.00 709,610.00 120.00 774,120.00 170.00 1,096,670.00    
701-03-O storm drain pipe (48" rcp/pcp) 1,797      LNFT 130.00 233,610.00 180.00 323,460.00 190.00 341,430.00    
701-04-G storm drain pipe arch (42" equiv. rcpa) 2,373      LNFT 140.00 332,220.00 140.00 332,220.00 160.00 379,680.00    
701-05-F side drain pipe (15" rcp/pcp) 160      LNFT 50.00 8,000.00 50.00 8,000.00 59.00 9,440.00    
701-05-G side drain pipe (18" rcp/pcp) 1,171      LNFT 72.00 84,312.00 60.00 70,260.00 62.00 72,602.00    
701-05-I side drain pipe (24" rcp/pcp) 636      LNFT 75.00 47,700.00 70.00 44,520.00 79.00 50,244.00    
701-05-I-01 side drain pipe (24")(erosion) 130      LNFT 62.00 8,060.00 70.00 9,100.00 79.00 10,270.00    
701-05-K side drain pipe (30" rcp/pcp) 168      LNFT 125.00 21,000.00 80.00 13,440.00 96.00 16,128.00    
701-05-K-01 side drain pipe (30")(erosion) 44      LNFT 82.00 3,608.00 80.00 3,520.00 96.00 4,224.00    
701-05-M-01 side drain pipe (36")(erosion) 96      LNFT 120.00 11,520.00 90.00 8,640.00 120.00 11,520.00    
701-15 concrete collar 1      EACH 1,200.00 1,200.00 1,200.00 1,200.00 1,000.00 1,000.00    
702-02-B manholes (r-cb-11) 3      EACH 3,200.00 9,600.00 3,000.00 9,000.00 14,000.00 42,000.00    
702-02-C manholes (r-cb-11 mod) 2      EACH 4,500.00 9,000.00 5,000.00 10,000.00 14,000.00 28,000.00    
702-02-G manholes (special detail) 12      EACH 9,000.00 108,000.00 8,000.00 96,000.00 14,000.00 168,000.00    
702-03-A catch basins (cb-01) 53      EACH 3,000.00 159,000.00 3,000.00 159,000.00 3,000.00 159,000.00    
702-03-B catch basins (cb-02) 2      EACH 3,600.00 7,200.00 4,000.00 8,000.00 7,000.00 14,000.00    
702-03-C catch basins (cb-06) 2      EACH 6,200.00 12,400.00 4,000.00 8,000.00 7,000.00 14,000.00    
702-03-I catch basins (special detail) 32      EACH 10,000.00 320,000.00 10,000.00 320,000.00 12,000.00 384,000.00    
704-01-B guard rail (single thrie beam)(6'-3" post spacing) 146.0    LNFT 35.00 5,110.00 31.50 4,599.00 35.00 5,110.00    
704-03 blocked out guard rail 1,401.3    LNFT 16.00 22,420.80 15.50 21,720.15 17.00 23,822.10    
704-06 guard rail anchor sections (trailing end) 12.5    LNFT 70.00 875.00 67.00 837.50 75.00 937.50    
704-08-B guard rail transitions (double thrie beam) 150.0    LNFT 55.00 8,250.00 49.00 7,350.00 55.00 8,250.00    
704-11-A guard rail end treatment (flared) 4      EACH 2,000.00 8,000.00 1,850.00 7,400.00 20,000.00 80,000.00    
705-01 barbed wire fence 11,676      LNFT 5.50 64,218.00 6.00 70,056.00 6.00 70,056.00    
705-02 combination mesh & barbed wire fence 1,291      LNFT 6.00 7,746.00 8.00 10,328.00 6.00 7,746.00    
705-06-A chain link fence (4-foot height) 302      LNFT 13.00 3,926.00 15.00 4,530.00 20.00 6,040.00    
705-06-C chain link fence (6-foot height) 1,881      LNFT 22.00 41,382.00 21.00 39,501.00 24.00 45,144.00    
705-09 rebuilt fence 787      LNFT 30.00 23,610.00 20.00 15,740.00 51.00 40,137.00    
706-02-C concrete drive (6" thick) 2,732.8    SQYD 55.00 150,304.00 45.00 122,976.00 43.00 117,510.40    
706-03-C incidental concrete paving (6" thick) 50.3    SQYD 180.00 9,054.00 45.00 2,263.50 96.00 4,828.80    
708-01 right-of-way monument 116      EACH 350.00 40,600.00 180.00 20,880.00 210.00 24,360.00    
708-02 right-of-way monument witness post 116      EACH 350.00 40,600.00 180.00 20,880.00 210.00 24,360.00    
709-01 steel cattle guard 1      EACH 13,000.00 13,000.00 14,000.00 14,000.00 9,000.00 9,000.00    
711-01-D riprap (55 lb, 18" thick) 4,775      SQYD 60.00 286,500.00 55.00 262,625.00 73.00 348,575.00    
711-04 geotextile fabric 4,775      SQYD 2.00 9,550.00 2.00 9,550.00 2.30 10,982.50    
712-04 flexible revetment 1,150      SQYD 55.00 63,250.00 50.00 57,500.00 45.00 51,750.00    
713-01 temporary signs & barricades lump      LUMP 200,000.00 200,000.00 185,000.00 185,000.00 250,000.00 250,000.00    
713-05-A-01 temporary pavement markings (solid line)(4" width)
(type i removable)
6.873  MILE 16,000.00 109,968.00 15,000.00 103,095.00 10,000.00 68,730.00    
713-09 temporary precast concrete barrier (department
furnished)
52      EACH 350.00 18,200.00 180.00 9,360.00 320.00 16,640.00    
716-01-A mulch (vegetative) 133.00   ACRE 650.00 86,450.00 650.00 86,450.00 680.00 90,440.00    
717-01 seeding 3,990      LB 6.50 25,935.00 7.50 29,925.00 9.00 35,910.00    
718-01 fertilizer 133,000      LB 0.40 53,200.00 0.25 33,250.00 0.35 46,550.00    
720-01-B erosion control system, slope protection (type b) 3,659      SQYD 1.10 4,024.90 1.10 4,024.90 2.80 10,245.20    
720-01-C erosion control system, flexible channel liner (type c) 425      SQYD 2.60 1,105.00 2.50 1,062.50 3.10 1,317.50    
721-01 asphalt mulch 4,423      GAL 1.60 7,076.80 2.50 11,057.50 2.30 10,172.90    
722-02 project site laboratory (equipped) 1      EACH 60,000.00 60,000.00 36,000.00 36,000.00 50,000.00 50,000.00    
724-01-B pavement patching (12" minimum thickness) 1,039      SQYD 80.00 83,120.00 100.00 103,900.00 95.00 98,705.00    
725-02 temporary detour roads 1,204.4    SQYD 90.00 108,396.00 100.00 120,440.00 80.00 96,352.00    
726-01 bedding material 9,933.4    CUYD 75.00 745,005.00 55.00 546,337.00 73.00 725,138.20    
727-01 mobilization lump      LUMP 2,800,000.00 2,800,000.00 3,100,000.00 3,100,000.00 3,800,000.00 3,800,000.00    
729-16-C object marker assembly (type 3) 53      EACH 75.00 3,975.00 70.00 3,710.00 78.00 4,134.00    
731-02 reflectorized raised pavement markers 3,744      EACH 5.00 18,720.00 6.00 22,464.00 7.00 26,208.00    
732-02-A plastic pavement striping (solid line) (4" width) 36.827  MILE 2,300.00 84,702.10 2,200.00 81,019.40 3,000.00 110,481.00    
732-02-C plastic pavement striping (solid line) (8" width) 0.312  MILE 4,500.00 1,404.00 4,300.00 1,341.60 13,000.00 4,056.00    
732-02-E plastic pavement striping (solid line) (24" width) 0.305  MILE 13,000.00 3,965.00 12,800.00 3,904.00 24,000.00 7,320.00    
732-04-A plastic pavement legends & symbols (arrow) 25      EACH 160.00 4,000.00 145.00 3,625.00 340.00 8,500.00    
732-04-C plastic pavement legends & symbols (only) 19      EACH 160.00 3,040.00 165.00 3,135.00 340.00 6,460.00    
732-05 removal of existing markings 8.604  MILE 4,200.00 36,136.80 6,000.00 51,624.00 4,000.00 34,416.00    
735-01 mailboxes 30      EACH 50.00 1,500.00 6.00 180.00 17.00 510.00    
735-02 mailbox supports (single) 21      EACH 150.00 3,150.00 145.00 3,045.00 160.00 3,360.00    
735-03 mailbox supports (double) 3      EACH 210.00 630.00 250.00 750.00 230.00 690.00    
735-04 mailbox supports (multiple) 1      EACH 450.00 450.00 360.00 360.00 440.00 440.00    
740-01 construction layout lump      LUMP 380,000.00 380,000.00 350,000.00 350,000.00 750,000.00 750,000.00    
740-02 utility oversight and coordination lump      LUMP 80,000.00 80,000.00 50,000.00 50,000.00 35,000.00 35,000.00    
744-01 traffic control management lump      LUMP 140,000.00 140,000.00 150,000.00 150,000.00 35,000.00 35,000.00    
803-03 steel sheet pile wall 25,470      SQFT 20.00 509,400.00 20.00 509,400.00 39.00 993,330.00    
804-01-C precast concrete piles (16") 1,152      LNFT 62.00 71,424.00 55.00 63,360.00 63.00 72,576.00    
805-01 class a concrete 15.92   CUYD 1,300.00 20,696.00 800.00 12,736.00 790.00 12,576.80    
805-01-B class a concrete (box culvert headwalls) 146.43   CUYD 1,100.00 161,073.00 1,000.00 146,430.00 2,000.00 292,860.00    
805-01-F class a concrete (bents) 44.88   CUYD 825.00 37,026.00 750.00 33,660.00 790.00 35,455.20    
805-03 class aa concrete 179.30   CUYD 550.00 98,615.00 650.00 116,545.00 680.00 121,924.00    
805-12-A-01 reinforced concrete box culverts (4'x 3')(extension) 92.0    LNFT 300.00 27,600.00 300.00 27,600.00 450.00 41,400.00    
805-12-B-01 reinforced concrete box culverts (5'x 3')(extension) 24.0    LNFT 700.00 16,800.00 650.00 15,600.00 560.00 13,440.00    
805-12-C-01 reinforced concrete box culverts (6'x 3')(extension) 93.0    LNFT 400.00 37,200.00 400.00 37,200.00 620.00 57,660.00    
805-12-E-01 reinforced concrete box culverts (4'x 4')(extension) 500.0    LNFT 450.00 225,000.00 400.00 200,000.00 510.00 255,000.00    
805-12-I-01 reinforced concrete box culverts (5'x 5')(extension) 296.0    LNFT 460.00 136,160.00 500.00 148,000.00 560.00 165,760.00    
805-12-V reinforced concrete box culverts (9'x 9') 768.0    LNFT 800.00 614,400.00 700.00 537,600.00 930.00 714,240.00    
805-12-X reinforced concrete box culverts (10'x 10') 337.0    LNFT 1,000.00 337,000.00 900.00 303,300.00 1,100.00 370,700.00    
805-12-Y-01 reinforced concrete box culverts (2'x 2')(extension) 9.0    LNFT 625.00 5,625.00 500.00 4,500.00 3,200.00 28,800.00    
805-12-Z-01 reinforced concrete box culverts (2'x 3')(extension) 5.0    LNFT 1,000.00 5,000.00 700.00 3,500.00 4,000.00 20,000.00    
806-01 deformed reinforcing steel 56,226      LB 0.85 47,792.10 1.50 84,339.00 3.20 179,923.20    
807-06 structural metalwork lump      LUMP 50,000.00 50,000.00 50,000.00 50,000.00 101,000.00 101,000.00    
810-01 concrete railing (barrier) 200.00   LNFT 48.00 9,600.00 80.00 16,000.00 68.00 13,600.00    
813-01 concrete approach slabs 364.44   SQYD 185.00 67,421.40 185.00 67,421.40 200.00 72,888.00    
S-001 rumble strips (ground-in) 17.2    MILE 1,100.00 18,920.00 800.00 13,760.00 910.00 15,652.00    
S-002 dynamic message sign unit 2      EACH 24,000.00 48,000.00 25,000.00 50,000.00 37,000.00 74,000.00    
S-003 sawcutting of asphaltic concrete pavement - full depth 7,100      LNFT 2.00 14,200.00 6.00 42,600.00 3.70 26,270.00    
S-004 sawcutting of concrete pavement - full depth 270      LNFT 7.00 1,890.00 12.00 3,240.00 3.70 999.00    
S-005 traffic maintenance superpave asphaltic concrete 115.0    TON 82.00 9,430.00 100.00 11,500.00 150.00 17,250.00    
S-006 plugging existing water wells 1      EACH 1,100.00 1,100.00 500.00 500.00 6,000.00 6,000.00    
S-007 lightweight aggregate backfill 4,512.0    TON 100.00 451,200.00 82.00 369,984.00 40.00 180,480.00    
S-008 precast concrete sheet pile wall cap 919      LNFT 150.00 137,850.00 150.00 137,850.00 290.00 266,510.00    
S-101 retroreflective sheeting panels lump      LUMP 1,600.00 1,600.00 4,000.00 4,000.00 960.00 960.00    
 SUBTOTAL GENERAL       16,197,571.70   17,421,798.95   21,560,883.40    
                       
ALTERNATE A                      
                       
ALTERNATE A1 superpave asphaltic concrete pavement                    
203-05-A nonplastic embankment (stone) 4,778      CUYD 0.00 0.00 0.00 0.00 58.00 277,124.00    
302-02-C-01 class ii base course (10" thick)(stone or recycled
pccp)
162,875.2    SQYD 0.00 0.00 0.00 0.00 19.00 3,094,628.80    
302-02-E-01 class ii base course (7" thick)(stone or recycled pccp) 15,614.1    SQYD 0.00 0.00 0.00 0.00 18.00 281,053.80    
302-02-F-01 class ii base course (17" thick)(stone or recycled
pccp)
46,162.2    SQYD 0.00 0.00 0.00 0.00 24.00 1,107,892.80    
305-01-D subgrade layer (12" thick)(6% cement treated) 224,282      SQYD 0.00 0.00 0.00 0.00 6.00 1,345,692.00    
502-01 superpave asphaltic concrete 71,624.9    TON 0.00 0.00 0.00 0.00 130.00 9,311,237.00    
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
14,987.8    TON 0.00 0.00 0.00 0.00 160.00 2,398,048.00    
707-01 concrete curb 452.6    LNFT 0.00 0.00 0.00 0.00 14.00 6,336.40    
707-03 combination concrete curb and gutter 384.3    LNFT 0.00 0.00 0.00 0.00 28.00 10,760.40    
732-03-A plastic pavement striping (broken line)(4" width) 17.207  MILE 0.00 0.00 0.00 0.00 10,000.00 172,070.00    
 SUBTOTAL ALT A1               18,004,843.20    
                       
ALTERNATE A2 portland cement concrete pavement                    
203-05-A nonplastic embankment (stone) 4,775      CUYD 100.00 477,500.00 80.00 382,000.00 0.00 0.00    
302-02-C-01 class ii base course (10" thick)(stone or recycled
pccp)
163,320.2    SQYD 14.00 2,286,482.80 22.50 3,674,704.50 0.00 0.00    
302-02-E-01 class ii base course (7" thick)(stone or recycled pccp) 15,565.4    SQYD 12.00 186,784.80 16.50 256,829.10 0.00 0.00    
302-02-F-01 class ii base course (17" thick)(stone or recycled
pccp)
45,837.6    SQYD 28.00 1,283,452.80 33.50 1,535,559.60 0.00 0.00    
305-01-D subgrade layer (12" thick)(6% cement treated) 224,354      SQYD 7.00 1,570,478.00 7.00 1,570,478.00 0.00 0.00    
502-01 superpave asphaltic concrete 4,425.9    TON 88.00 389,479.20 90.00 398,331.00 0.00 0.00    
502-01-A superpave asphaltic concrete, drives, turnouts and
miscellaneous
2,053.5    TON 120.00 246,420.00 105.00 215,617.50 0.00 0.00    
601-01-I portland cement concrete pavement (9" thick) 135,754.6    SQYD 42.00 5,701,693.20 44.00 5,973,202.40 0.00 0.00    
601-02-I portland cement concrete pavement (9" thick)
(crossovers & turnouts)
26,796.8    SQYD 65.00 1,741,792.00 59.00 1,581,011.20 0.00 0.00    
601-04 portland cement concrete pavement coring 205      EACH 90.00 18,450.00 100.00 20,500.00 0.00 0.00    
707-01 concrete curb 836.9    LNFT 14.00 11,716.60 11.00 9,205.90 0.00 0.00    
732-03-A plastic pavement striping (broken line)(4" width) 8.604  MILE 800.00 6,883.20 630.00 5,420.52 0.00 0.00    
732-03-A-01 plastic pvmt striping (broken line)(4"width)preformed
marking tape (type v)
8.604  MILE 5,500.00 47,322.00 4,000.00 34,416.00 0.00 0.00    
 SUBTOTAL ALT A2       13,968,454.60   15,657,275.72        
                       
 ITEM TOTAL (CONSTRUCTION BID)       30,166,026.30   33,079,074.67   39,565,726.60    
 Number of Days Bid at $1,000 per day.     825 825,000.00 950 950,000.00 950 950,000.00    
 Life Cycle Cost       1,359,000.00   1,359,000.00   2,614,800.00    
 TOTAL BID       32,350,026.30   35,388,074.67   43,130,526.60    