Bid Tabulations for the Letting of 8/11/2021 LA DOTD Headquarters
Proposal:H.014543.6
Parish:Calcasieu
Routes:LA 384
Description:LA 384: ICWW MB REPAIR (BLACK BAYOU)
Type Construction:MOVABLE BRIDGE REPAIRS AND RELATED WORK.
Estimated Construction Cost:$366,298.00
Rank | License | Bidder | Construction Bid |
1 | 00044 | Guinn Construction, LLC | $663,800.00 |
2 | 26435 | C.E.C., Inc. | $678,600.00 |
3 | 00009 | Coastal Contractors, Inc. | $940,000.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Guinn Construction, LLC | - 2 - C.E.C., Inc. | - 3 - Coastal Contractors, Inc. |
Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount |
0001 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 20,000.00 | 20,000.00 | 8,000.00 | 8,000.00 | 21,000.00 | 21,000.00 |
0002 | 713-11-00100 | Portable Changeable Message Signs | 2 | EACH | 5,000.00 | 10,000.00 | 27,000.00 | 54,000.00 | 7,500.00 | 15,000.00 |
0003 | 727-01-00100 | Mobilization | 1 | LUMP | 60,000.00 | 60,000.00 | 65,000.00 | 65,000.00 | 94,000.00 | 94,000.00 |
0004 | 820-02-00100 | Temporary Operation & Maintenance of Movable Span (Apron Operation) | 30 | DAY | 2,500.00 | 75,000.00 | 800.00 | 24,000.00 | 500.00 | 15,000.00 |
0005 | TS-821-04100 | Pontoon Bridge Machinery | 1 | LUMP | 170,000.00 | 170,000.00 | 130,000.00 | 130,000.00 | 305,000.00 | 305,000.00 |
0006 | TS-822-09100 | Electrical System (Conductors and Conduit Repairs) | 1 | LUMP | 18,500.00 | 18,500.00 | 88,000.00 | 88,000.00 | 25,000.00 | 25,000.00 |
0007 | TS-822-09100 | Electrical System (Generator Repairs) | 1 | LUMP | 9,000.00 | 9,000.00 | 28,500.00 | 28,500.00 | 100,000.00 | 100,000.00 |
0008 | TS-822-09100 | Electrical System (Limit Switch Repairs) | 1 | LUMP | 8,500.00 | 8,500.00 | 7,000.00 | 7,000.00 | 19,000.00 | 19,000.00 |
0009 | TS-822-09100 | Electrical System (Security Light Repairs) | 1 | LUMP | 6,500.00 | 6,500.00 | 4,250.00 | 4,250.00 | 6,000.00 | 6,000.00 |
0010 | TS-822-09100 | Electrical System (Service Light Repairs) | 1 | LUMP | 5,000.00 | 5,000.00 | 4,250.00 | 4,250.00 | 4,000.00 | 4,000.00 |
0011 | TS-822-09100 | Electrical System (Traffic Gate Mechanism Repairs) | 1 | LUMP | 148,000.00 | 148,000.00 | 139,000.00 | 139,000.00 | 133,000.00 | 133,000.00 |
0012 | TS-822-09100 | Electrical System (Traffic Gate Repairs) | 1 | LUMP | 22,500.00 | 22,500.00 | 17,600.00 | 17,600.00 | 23,000.00 | 23,000.00 |
0013 | TS-822-09100 | Electrical System (Traffic Signal Repairs) | 1 | LUMP | 32,500.00 | 32,500.00 | 60,000.00 | 60,000.00 | 29,000.00 | 29,000.00 |
0014 | TS-822-09100 | Electrical System (Transfer Switch Repairs) | 1 | LUMP | 3,800.00 | 3,800.00 | 12,400.00 | 12,400.00 | 31,000.00 | 31,000.00 |
0015 | TS-823-01200 | Bridge Operator's House Renovation (Gen House Roof) | 1 | LUMP | 25,000.00 | 25,000.00 | 14,400.00 | 14,400.00 | 60,000.00 | 60,000.00 |
0016 | TS-823-01200 | Bridge Operator's House Renovation (Op House Roof) | 1 | LUMP | 49,500.00 | 49,500.00 | 22,200.00 | 22,200.00 | 60,000.00 | 60,000.00 |
| | | | | | | | | | |
| | CONTRACTOR TOTAL | | | | 663,800.00 | | 678,600.00 | | 940,000.00 |