Bid Tabulations for the Letting of 8/11/2021 LA DOTD Headquarters
Proposal:H.013738.6
Parish:Livingston
Routes:LA 441
Description:LA 441: LA 42 - I-12 COA
Type Construction:MILLING ASPHALT CONCRETE, IN-PLACE CEMENT TREATED BASE COURSE, ASPHALT CONCRETE OVERLAY AND RELATED WORK.
Estimated Construction Cost:$1,211,802.85
Rank | License | Bidder | Construction Bid |
1 | 06276 | Barriere Construction Co., LLC | $1,057,675.66 |
2 | 00046 | Barber Bros. Contracting Co., L.L.C | $1,154,593.73 |
3 | 12031 | R.J. Daigle & Sons Contractors, Inc | $1,182,598.11 |
4 | 69570 | Bridging The Gap, L.L.C. | $1,606,289.94 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barriere Construction Co., LLC | - 2 - Barber Bros. Contracting Co., L.L.C | - 3 - R.J. Daigle & Sons Contractors, Inc | - 4 - Bridging The Gap, L.L.C. |
Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount |
0001 | 202-02-38300 | Removal of Sign and U-Channel Post | 12 | EACH | 14.50 | 174.00 | 15.00 | 180.00 | 16.50 | 198.00 | 16.31 | 195.72 |
0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 17 | CUYD | 60.00 | 1,020.00 | 30.00 | 510.00 | 26.53 | 451.01 | 137.44 | 2,336.48 |
0003 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 12 | EACH | 165.00 | 1,980.00 | 100.00 | 1,200.00 | 165.00 | 1,980.00 | 37.56 | 450.72 |
0004 | 204-06-00100 | Temporary Silt Fencing | 800 | LNFT | 3.00 | 2,400.00 | 1.00 | 800.00 | 2.20 | 1,760.00 | 4.36 | 3,488.00 |
0005 | 303-02-00100 | Removal of Existing Patches | 50 | SQYD | 1.00 | 50.00 | 20.00 | 1,000.00 | 21.24 | 1,062.00 | 189.11 | 9,455.50 |
0006 | 303-03-00400 | In-Place Cement Treated Base Course (12" Thick) | 30,138.8 | SQYD | 8.25 | 248,645.10 | 8.00 | 241,110.40 | 8.45 | 254,672.86 | 12.58 | 379,146.10 |
0007 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 603 | CUYD | 30.00 | 18,090.00 | 40.00 | 24,120.00 | 17.61 | 10,618.83 | 114.73 | 69,182.19 |
0008 | 402-01-00100 | Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 15 | CUYD | 150.00 | 2,250.00 | 75.00 | 1,125.00 | 88.74 | 1,331.10 | 112.18 | 1,682.70 |
0009 | 502-01-00100 | Asphalt Concrete | 6,428.3 | TON | 89.50 | 575,332.85 | 85.00 | 546,405.50 | 85.32 | 548,462.56 | 109.48 | 703,770.28 |
0010 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 452.6 | TON | 1.00 | 452.60 | 145.00 | 65,627.00 | 142.94 | 64,694.64 | 142.11 | 64,318.99 |
0011 | 509-01-00100 | Milling Asphalt Pavement | 26,603 | SQYD | 2.25 | 59,856.75 | 2.75 | 73,158.25 | 2.32 | 61,718.96 | 2.08 | 55,334.24 |
0012 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -1,501 | CUYD | 1.00 | -1,501.00 | 0.00 | 0.00 | 0.01 | -15.01 | 5.44 | -8,165.44 |
0013 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 63,000.00 | 63,000.00 | 43,000.00 | 43,000.00 | 67,614.00 | 67,614.00 | 73,399.04 | 73,399.04 |
0014 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 8.216 | MILE | 45.00 | 369.72 | 300.00 | 2,464.80 | 141.38 | 1,161.58 | 617.24 | 5,071.24 |
0015 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 18.588 | MILE | 1.00 | 18.59 | 750.00 | 13,941.00 | 825.09 | 15,336.77 | 816.07 | 15,169.11 |
0016 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 8.22 | MILE | 1.00 | 8.22 | 1,250.00 | 10,275.00 | 1,375.00 | 11,302.50 | 1,360.89 | 11,186.52 |
0017 | 716-01-00100 | Mulch (Vegetative) | 1.5 | TON | 775.00 | 1,162.50 | 1,000.00 | 1,500.00 | 880.00 | 1,320.00 | 3,624.65 | 5,436.98 |
0018 | 717-01-00100 | Seeding | 45 | LB | 18.00 | 810.00 | 11.00 | 495.00 | 16.50 | 742.50 | 43.50 | 1,957.50 |
0019 | 718-01-00100 | Fertilizer | 1,494 | LB | 0.75 | 1,120.50 | 1.00 | 1,494.00 | 0.50 | 747.00 | 2.17 | 3,241.98 |
0020 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 1.00 | 1.00 | 2,000.00 | 2,000.00 | 2,500.00 | 2,500.00 | 38,058.76 | 38,058.76 |
0021 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 4.109 | MILE | 300.00 | 1,232.70 | 320.00 | 1,314.88 | 286.07 | 1,175.46 | 3,602.24 | 14,801.60 |
0022 | 727-01-00100 | Mobilization | 1 | LUMP | 37,450.00 | 37,450.00 | 80,000.00 | 80,000.00 | 90,000.00 | 90,000.00 | 75,000.00 | 75,000.00 |
0023 | 729-16-00200 | Object Marker Assembly (Type 2) | 12 | EACH | 85.00 | 1,020.00 | 80.00 | 960.00 | 82.50 | 990.00 | 81.56 | 978.72 |
0024 | 731-02-00100 | Reflectorized Raised Pavement Markers | 272 | EACH | 8.50 | 2,312.00 | 8.00 | 2,176.00 | 8.25 | 2,244.00 | 8.15 | 2,216.80 |
0025 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 12 | LNFT | 18.50 | 222.00 | 21.00 | 252.00 | 22.00 | 264.00 | 21.75 | 261.00 |
0026 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 4.647 | MILE | 5,000.00 | 23,235.00 | 4,700.00 | 21,840.90 | 4,953.20 | 23,017.52 | 4,896.43 | 22,753.71 |
0027 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 2.055 | MILE | 1,475.00 | 3,031.13 | 1,600.00 | 3,288.00 | 1,654.01 | 3,398.99 | 1,635.06 | 3,360.05 |
0028 | 735-01-00100 | Mailboxes | 53 | EACH | 18.00 | 954.00 | 21.00 | 1,113.00 | 22.00 | 1,166.00 | 184.08 | 9,756.24 |
0029 | 735-02-00100 | Mailbox Supports (Single) | 53 | EACH | 150.00 | 7,950.00 | 135.00 | 7,155.00 | 143.00 | 7,579.00 | 46.65 | 2,472.45 |
0030 | 740-01-00100 | Construction Layout | 1 | LUMP | 4,500.00 | 4,500.00 | 6,000.00 | 6,000.00 | 5,000.00 | 5,000.00 | 38,058.76 | 38,058.76 |
0031 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 88 | INLF | 6.00 | 528.00 | 1.00 | 88.00 | 1.18 | 103.84 | 21.75 | 1,914.00 |
| | | | | | | | | | | | |
| | CONTRACTOR TOTAL | | | | 1,057,675.66 | | 1,154,593.73 | | 1,182,598.11 | | 1,606,289.94 |