Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Diamond B Construction Co., L.L.C. | - 2 - GILCHRIST CONSTRUCTION COMPANY, LLC | - 3 - D & J CONSTRUCTION CO., LLC |
Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount |
0001 | 202-02-00020 | Removal of Winn Rock (3.5" Depth) | 920 | SQYD | 15.00 | 13,800.00 | 10.00 | 9,200.00 | 10.00 | 9,200.00 |
0002 | 202-02-00020 | Removal of Winn Rock (40" Depth) | 2,778 | SQYD | 48.00 | 133,344.00 | 25.00 | 69,450.00 | 25.00 | 69,450.00 |
0003 | 202-02-02020 | Removal of Asphalt Pavement | 463.5 | SQYD | 28.00 | 12,978.00 | 12.00 | 5,562.00 | 10.00 | 4,635.00 |
0004 | 202-02-14500 | Removal of Guard Rail | 1,674 | LNFT | 15.00 | 25,110.00 | 10.00 | 16,740.00 | 35.00 | 58,590.00 |
0005 | 202-02-32100 | Removal of Pipe (Cross Drain) (24" CMP) | 25 | LNFT | 10.00 | 250.00 | 110.00 | 2,750.00 | 20.00 | 500.00 |
0006 | 202-02-32100 | Removal of Pipe (Cross Drain) (24" RCP) | 16 | LNFT | 10.00 | 160.00 | 210.00 | 3,360.00 | 20.00 | 320.00 |
0007 | 202-02-32100 | Removal of Pipe (Cross Drain) (30" RCP) | 42 | LNFT | 12.00 | 504.00 | 80.00 | 3,360.00 | 20.00 | 840.00 |
0008 | 202-02-32100 | Removal of Pipe (Cross Drain) (36" CMPA) | 40 | LNFT | 15.00 | 600.00 | 130.00 | 5,200.00 | 20.00 | 800.00 |
0009 | 202-02-32100 | Removal of Pipe (Cross Drain) (36" RCP) | 8 | LNFT | 10.00 | 80.00 | 140.00 | 1,120.00 | 20.00 | 160.00 |
0010 | 202-02-32100 | Removal of Pipe (Cross Drain) (48" CMPA) | 80 | LNFT | 12.00 | 960.00 | 90.00 | 7,200.00 | 20.00 | 1,600.00 |
0011 | 203-05-00100 | Excavation and Embankment | 1 | LUMP | 25,000.00 | 25,000.00 | 75,000.00 | 75,000.00 | 75,000.00 | 75,000.00 |
0012 | 203-07-00100 | Borrow (Vehicular Measurement) | 5,723 | CUYD | 20.00 | 114,460.00 | 26.00 | 148,798.00 | 30.00 | 171,690.00 |
0013 | 303-03-00400 | In-Place Cement Treated Base Course (12" Thick) | 155,229.2 | SQYD | 9.25 | 1,435,870.10 | 9.00 | 1,397,062.80 | 10.00 | 1,552,292.00 |
0014 | 304-01-00100 | Lime | 57.87 | TON | 254.00 | 14,698.98 | 250.00 | 14,467.50 | 280.00 | 16,203.60 |
0015 | 304-03-00400 | Lime Treatment (Type C) (12" Thick) | 6,124 | SQYD | 5.25 | 32,151.00 | 5.00 | 30,620.00 | 15.00 | 91,860.00 |
0016 | 309-01-12000 | In-Place Cement Treated Subgrade (12" Thick) | 119,516 | SQYD | 7.45 | 890,394.20 | 9.75 | 1,165,281.00 | 9.00 | 1,075,644.00 |
0017 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 3,861 | CUYD | 44.00 | 169,884.00 | 40.00 | 154,440.00 | 30.00 | 115,830.00 |
0018 | 502-01-00100 | Asphalt Concrete | 28,634.8 | TON | 89.00 | 2,548,497.20 | 95.00 | 2,720,306.00 | 112.00 | 3,207,097.60 |
0019 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 1,894.4 | TON | 130.00 | 246,272.00 | 95.00 | 179,968.00 | 165.00 | 312,576.00 |
0020 | 509-01-00100 | Milling Asphalt Pavement | 141,490 | SQYD | 1.55 | 219,309.50 | 1.65 | 233,458.50 | 2.25 | 318,352.50 |
0021 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -3,858 | CUYD | 1.00 | -3,858.00 | 1.00 | -3,858.00 | 1.00 | -3,858.00 |
0022 | 701-01-01001 | Cross Drain Pipe (24" RCP) | 24 | LNFT | 340.00 | 8,160.00 | 190.00 | 4,560.00 | 190.00 | 4,560.00 |
0023 | 701-01-01003 | Cross Drain Pipe (24" RCP/RPVCP/CPEPDW) | 40 | LNFT | 190.00 | 7,600.00 | 190.00 | 7,600.00 | 195.00 | 7,800.00 |
0024 | 701-01-01023 | Cross Drain Pipe (30" RCP/RPVCP/CPEPDW) | 48 | LNFT | 245.00 | 11,760.00 | 200.00 | 9,600.00 | 210.00 | 10,080.00 |
0025 | 701-01-01042 | Cross Drain Pipe (36" RCP/RPVCP/CPEPDW) | 48 | LNFT | 255.00 | 12,240.00 | 275.00 | 13,200.00 | 230.00 | 11,040.00 |
0026 | 701-01-01082 | Cross Drain Pipe (48" RCP/RPVCP/CPEPDW) | 96 | LNFT | 345.00 | 33,120.00 | 290.00 | 27,840.00 | 300.00 | 28,800.00 |
0027 | 701-08-00100 | Relaying Pipe (48" RCP) | 16 | LNFT | 170.00 | 2,720.00 | 150.00 | 2,400.00 | 150.00 | 2,400.00 |
0028 | 701-15-00100 | Concrete Collar | 5 | EACH | 2,400.00 | 12,000.00 | 2,500.00 | 12,500.00 | 1,000.00 | 5,000.00 |
0029 | 701-17-00100 | Trench Excavation Safety Protection (Depth >5 feet) | 211 | LNFT | 10.00 | 2,110.00 | 1.00 | 211.00 | 2.00 | 422.00 |
0030 | 704-03-00200 | Blocked Out Guard Rail - 31", (6'-3" Post Spacing) | 737.5 | LNFT | 29.00 | 21,387.50 | 35.00 | 25,812.50 | 28.00 | 20,650.00 |
0031 | 704-06-00200 | Guard Rail Bridge Attachments (Single Thrie Beam) | 350 | LNFT | 60.00 | 21,000.00 | 42.00 | 14,700.00 | 65.00 | 22,750.00 |
0032 | 704-07-00200 | Guard Rail Transitions (Double Thrie Beam) | 700 | LNFT | 95.00 | 66,500.00 | 110.00 | 77,000.00 | 100.00 | 70,000.00 |
0033 | 704-10-00310 | Guard Rail End Treatment, NCHRP 350 - 31" (TL-3 Flared) | 28 | EACH | 3,550.00 | 99,400.00 | 3,100.00 | 86,800.00 | 3,300.00 | 92,400.00 |
0034 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 85 | SQYD | 110.00 | 9,350.00 | 235.00 | 19,975.00 | 100.00 | 8,500.00 |
0035 | 711-04-00100 | Geotextile Fabric | 85 | SQYD | 2.00 | 170.00 | 2.00 | 170.00 | 5.00 | 425.00 |
0036 | 712-02-00100 | Sacked Concrete Revetment | 6 | SQYD | 420.00 | 2,520.00 | 2,100.00 | 12,600.00 | 400.00 | 2,400.00 |
0037 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 70,000.00 | 70,000.00 | 75,000.00 | 75,000.00 | 65,000.00 | 65,000.00 |
0038 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 34.097 | MILE | 154.00 | 5,250.94 | 210.00 | 7,160.37 | 200.00 | 6,819.40 |
0039 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 9.517 | MILE | 800.00 | 7,613.60 | 1.00 | 9.52 | 500.00 | 4,758.50 |
0040 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 123.597 | MILE | 1,200.00 | 148,316.40 | 1.00 | 123.60 | 100.00 | 12,359.70 |
0041 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 4,500.00 | 4,500.00 | 20,000.00 | 20,000.00 | 10,000.00 | 10,000.00 |
0042 | 726-01-00100 | Bedding Material | 71.6 | CUYD | 10.00 | 716.00 | 160.00 | 11,456.00 | 100.00 | 7,160.00 |
0043 | 727-01-00100 | Mobilization | 1 | LUMP | 227,000.00 | 227,000.00 | 540,000.00 | 540,000.00 | 450,000.00 | 450,000.00 |
0044 | 729-16-00200 | Object Marker Assembly (Type 2) | 4 | EACH | 100.00 | 400.00 | 60.00 | 240.00 | 100.00 | 400.00 |
0045 | 729-16-00300 | Object Marker Assembly (Type 3) | 28 | EACH | 105.00 | 2,940.00 | 95.00 | 2,660.00 | 110.00 | 3,080.00 |
0046 | 731-02-00100 | Reflectorized Raised Pavement Markers | 2,582 | EACH | 7.00 | 18,074.00 | 7.10 | 18,332.20 | 7.00 | 18,074.00 |
0047 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 41.199 | MILE | 4,200.00 | 173,035.80 | 4,200.00 | 173,035.80 | 4,000.00 | 164,796.00 |
0048 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 3.172 | MILE | 1,650.00 | 5,233.80 | 1,600.00 | 5,075.20 | 1,250.00 | 3,965.00 |
0049 | 732-05-00100 | Removal of Existing Markings | 0.325 | MILE | 12,000.00 | 3,900.00 | 12,000.00 | 3,900.00 | 7,000.00 | 2,275.00 |
0050 | 735-01-00100 | Mailboxes | 15 | EACH | 1.00 | 15.00 | 11.00 | 165.00 | 5.00 | 75.00 |
0051 | 735-02-00100 | Mailbox Supports (Single) | 15 | EACH | 265.00 | 3,975.00 | 155.00 | 2,325.00 | 160.00 | 2,400.00 |
0052 | 739-01-00100 | Hydro-Seeding | 16.6 | ACRE | 2,100.00 | 34,860.00 | 1,400.00 | 23,240.00 | 3,000.00 | 49,800.00 |
0053 | 740-01-00100 | Construction Layout | 1 | LUMP | 50,000.00 | 50,000.00 | 15,000.00 | 15,000.00 | 85,000.00 | 85,000.00 |
| | | | | | | | | | |
| | CONTRACTOR TOTAL | | | | 6,946,333.02 | | 7,452,176.99 | | 8,251,972.30 |