Bid Tabulations for the Letting of 8/11/2021 LA DOTD Headquarters
Proposal:H.011517.6
Parish:Lafourche
Routes:LA 654
Description:LA 654: LA 308 - GHEENS S. CUT RD.
Type Construction:MILLING ASPHALT CONCRETE, PAVEMENT PATCHING, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$364,294.79
Rank | License | Bidder | Construction Bid |
1 | 06276 | Barriere Construction Co., LLC | $388,756.97 |
2 | 62139 | HUEY P. STOCKSTILL, LLC | $417,989.87 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barriere Construction Co., LLC | - 2 - HUEY P. STOCKSTILL, LLC |
Unit Price | Total Amount | Unit Price | Total Amount |
0001 | 202-02-00040 | Removal of Removal of Aggregate Drives | 13 | CUYD | 250.00 | 3,250.00 | 105.00 | 1,365.00 |
0002 | 203-07-00100 | Borrow (Vehicular Measurement) | 200 | CUYD | 25.00 | 5,000.00 | 60.00 | 12,000.00 |
0003 | 502-01-00100 | Asphalt Concrete | 1,662.7 | TON | 106.00 | 176,246.20 | 115.00 | 191,210.50 |
0004 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 30 | TON | 106.00 | 3,180.00 | 205.00 | 6,150.00 |
0005 | 509-01-00100 | Milling Asphalt Pavement | 4,792 | SQYD | 4.00 | 19,168.00 | 2.75 | 13,178.00 |
0006 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -173 | CUYD | 0.01 | -1.73 | 0.01 | -1.73 |
0007 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 1,230.46 | SQYD | 75.00 | 92,284.50 | 75.00 | 92,284.50 |
0008 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 30,000.00 | 30,000.00 | 24,500.00 | 24,500.00 |
0009 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 1.704 | MILE | 100.00 | 170.40 | 150.00 | 255.60 |
0010 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 1.704 | MILE | 100.00 | 170.40 | 1,000.00 | 1,704.00 |
0011 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 3.408 | MILE | 100.00 | 340.80 | 1,500.00 | 5,112.00 |
0012 | 717-01-00100 | Seeding | 25 | LB | 18.00 | 450.00 | 2.00 | 50.00 |
0013 | 718-01-00100 | Fertilizer | 1,000 | LB | 0.50 | 500.00 | 0.15 | 150.00 |
0014 | 727-01-00100 | Mobilization | 1 | LUMP | 30,000.00 | 30,000.00 | 41,000.00 | 41,000.00 |
0015 | 731-02-00100 | Reflectorized Raised Pavement Markers | 80 | EACH | 22.00 | 1,760.00 | 20.00 | 1,600.00 |
0016 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 1.136 | MILE | 7,700.00 | 8,747.20 | 5,000.00 | 5,680.00 |
0017 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.568 | MILE | 3,400.00 | 1,931.20 | 1,500.00 | 852.00 |
0018 | 732-05-00100 | Removal of Existing Markings | 0.16 | MILE | 3,500.00 | 560.00 | 12,500.00 | 2,000.00 |
0019 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 14,900.00 | 14,900.00 |
0020 | NS-719-00002 | Tree Trimming | 1 | LUMP | 5,000.00 | 5,000.00 | 4,000.00 | 4,000.00 |
| | | | | | | | |
| | CONTRACTOR TOTAL | | | | 388,756.97 | | 417,989.87 |