Bid Tabulations for the Letting of 5/12/2021 LA DOTD Headquarters
Proposal:H.014360.6
Parish:Orleans
Routes:US 90-Z
Description:US 90B:LA 428 OVERPASS (LEVEL APPR SLAB)
Type Construction:MILLING CONCRETE PAVEMENT, ASPHALT CONCRETE OVERLAY, AND RELATED WORK.
Estimated Construction Cost:$117,714.00
Rank | License | Bidder | Construction Bid |
1 | 06276 | Barriere Construction Co., LLC | $147,250.80 |
2 | 00046 | Barber Bros. Contracting Co., L.L.C | $162,000.00 |
3 | 02179 | Boh Bros. Construction Co., LLC. | $255,770.00 |
Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - Barriere Construction Co., LLC | - 2 - Barber Bros. Contracting Co., L.L.C | - 3 - Boh Bros. Construction Co., LLC. |
Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount |
0001 | 202-02-04560 | Removal of Bridge Joint Removal of Seal | 52 | LNFT | 22.00 | 1,144.00 | 125.00 | 6,500.00 | 50.00 | 2,600.00 |
0002 | 502-01-00100 | Asphalt Concrete | 114 | TON | 450.00 | 51,300.00 | 350.00 | 39,900.00 | 1,000.00 | 114,000.00 |
0003 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 25,000.00 | 25,000.00 | 35,000.00 | 35,000.00 | 40,000.00 | 40,000.00 |
0004 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 0.076 | MILE | 100.00 | 7.60 | 500.00 | 38.00 | 5,000.00 | 380.00 |
0005 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.076 | MILE | 100.00 | 7.60 | 19,000.00 | 1,444.00 | 25,000.00 | 1,900.00 |
0006 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 0.076 | MILE | 100.00 | 7.60 | 28,000.00 | 2,128.00 | 35,000.00 | 2,660.00 |
0007 | 713-11-00100 | Portable Changeable Message Signs | 1 | EACH | 1,000.00 | 1,000.00 | 2,000.00 | 2,000.00 | 2,500.00 | 2,500.00 |
0008 | 727-01-00100 | Mobilization | 1 | LUMP | 14,500.00 | 14,500.00 | 30,000.00 | 30,000.00 | 25,000.00 | 25,000.00 |
0009 | 731-02-00100 | Reflectorized Raised Pavement Markers | 50 | EACH | 75.00 | 3,750.00 | 60.00 | 3,000.00 | 55.00 | 2,750.00 |
0010 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 0.038 | MILE | 150,000.00 | 5,700.00 | 100,000.00 | 3,800.00 | 110,000.00 | 4,180.00 |
0011 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.038 | MILE | 75,000.00 | 2,850.00 | 50,000.00 | 1,900.00 | 55,000.00 | 2,090.00 |
0012 | 740-01-00100 | Construction Layout | 1 | LUMP | 10,000.00 | 10,000.00 | 8,000.00 | 8,000.00 | 10,000.00 | 10,000.00 |
0013 | 815-03-00200 | Joint Seal (Preformed Silicone) | 52 | LNFT | 15.00 | 780.00 | 280.00 | 14,560.00 | 300.00 | 15,600.00 |
0014 | NS-600-00220 | Saw Cutting Portland Cement Concrete Pavement | 302 | INLF | 2.00 | 604.00 | 10.00 | 3,020.00 | 5.00 | 1,510.00 |
0015 | NS-602-00001 | Milling Concrete Pavement | 306 | SQYD | 100.00 | 30,600.00 | 35.00 | 10,710.00 | 100.00 | 30,600.00 |
| | | | | | | | | | |
| | CONTRACTOR TOTAL | | | | 147,250.80 | | 162,000.00 | | 255,770.00 |