Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - R. E. Heidt Construction Co., LLC | - 2 - Prairie Contractors LLC | - 3 - SIEMA CONSTRUCTION, LLC |
Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount |
0001 | 202-02-00010 | Removal of DOUBLE 24" SAFETY END TREATMENT | 1 | EACH | 505.00 | 505.00 | 650.00 | 650.00 | 22,250.00 | 22,250.00 |
0002 | 202-02-02020 | Removal of Asphalt Pavement | 3,982.2 | SQYD | 28.00 | 111,501.60 | 5.70 | 22,698.54 | 11.00 | 43,804.20 |
0003 | 202-02-06100 | Removal of Concrete Walks and Drives | 626 | SQYD | 10.10 | 6,322.60 | 12.00 | 7,512.00 | 20.00 | 12,520.00 |
0004 | 203-01-00100 | General Excavation | 1,330 | CUYD | 25.25 | 33,582.50 | 35.00 | 46,550.00 | 37.00 | 49,210.00 |
0005 | 203-07-00100 | Borrow (Vehicular Measurement) | 441 | CUYD | 35.35 | 15,589.35 | 40.00 | 17,640.00 | 47.00 | 20,727.00 |
0006 | 204-02-00100 | Temporary Hay Bales | 10 | EACH | 12.12 | 121.20 | 35.00 | 350.00 | 26.00 | 260.00 |
0007 | 204-05-00100 | Temporary Sediment Check Dams (Hay) | 15 | EACH | 136.35 | 2,045.25 | 150.00 | 2,250.00 | 155.00 | 2,325.00 |
0008 | 204-06-00100 | Temporary Silt Fencing | 4,480 | LNFT | 2.02 | 9,049.60 | 2.25 | 10,080.00 | 2.10 | 9,408.00 |
0009 | 303-01-00200 | In-Place Cement Stabilized Base Course (8-1/2" Thick) | 7,155.6 | SQYD | 12.63 | 90,375.23 | 13.50 | 96,600.60 | 18.00 | 128,800.80 |
0010 | 304-01-00100 | Lime | 47.9 | TON | 282.80 | 13,546.12 | 280.00 | 13,412.00 | 340.00 | 16,286.00 |
0011 | 304-03-00200 | Lime Treatment (Type C) (8-1/2" Thick) | 7,155.6 | SQYD | 6.57 | 47,012.29 | 7.00 | 50,089.20 | 9.00 | 64,400.40 |
0012 | 402-03-00100 | Non-Mainline Traffic Maintenance Surfacing (Aggregate) (Vehicular Measurement) | 137.7 | CUYD | 126.00 | 17,350.20 | 100.00 | 13,770.00 | 140.00 | 19,278.00 |
0013 | 502-01-00100 | Asphalt Concrete | 4,455.6 | TON | 106.00 | 472,293.60 | 112.00 | 499,027.20 | 110.00 | 490,116.00 |
0014 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 36.1 | TON | 170.00 | 6,137.00 | 350.00 | 12,635.00 | 176.00 | 6,353.60 |
0015 | 509-01-00100 | Milling Asphalt Pavement | 6,411 | SQYD | 5.00 | 32,055.00 | 3.00 | 19,233.00 | 4.20 | 26,926.20 |
0016 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -267 | CUYD | 0.01 | -2.67 | 0.01 | -2.67 | 0.01 | -2.67 |
0017 | 510-02-00100 | Pavement Widening 12" THICKNESS | 58.3 | SQYD | 160.00 | 9,328.00 | 180.00 | 10,494.00 | 170.00 | 9,911.00 |
0018 | 701-05-01062 | Side Drain Pipe (24" RCP/RPVCP/CMP) RCP | 76 | LNFT | 126.25 | 9,595.00 | 135.00 | 10,260.00 | 100.00 | 7,600.00 |
0019 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 16 | LNFT | 161.60 | 2,585.60 | 175.00 | 2,800.00 | 100.00 | 1,600.00 |
0020 | 701-15-00100 | Concrete Collar | 2 | EACH | 717.10 | 1,434.20 | 750.00 | 1,500.00 | 560.00 | 1,120.00 |
0021 | 702-03-00100 | Catch Basins (CB-01) CB-SD02 | 1 | EACH | 6,161.00 | 6,161.00 | 6,750.00 | 6,750.00 | 10,000.00 | 10,000.00 |
0022 | 702-08-00100 | Side Drain Safety End (Type 1) | 5 | EACH | 2,626.00 | 13,130.00 | 3,000.00 | 15,000.00 | 2,570.00 | 12,850.00 |
0023 | 702-08-00200 | Side Drain Safety End (Type 2) | 3 | EACH | 3,535.00 | 10,605.00 | 4,000.00 | 12,000.00 | 6,100.00 | 18,300.00 |
0024 | 706-02-00200 | Concrete Drive (6" Thick) | 626 | SQYD | 86.86 | 54,374.36 | 100.00 | 62,600.00 | 82.00 | 51,332.00 |
0025 | 706-03-00100 | Incidental Concrete Paving (4" Thick) | 5 | SQYD | 85.85 | 429.25 | 100.00 | 500.00 | 126.00 | 630.00 |
0026 | 710-01-00100 | Flowable Fill | 26 | CUYD | 151.50 | 3,939.00 | 165.00 | 4,290.00 | 175.00 | 4,550.00 |
0027 | 711-04-00100 | Geotextile Fabric | 25 | SQYD | 3.03 | 75.75 | 4.00 | 100.00 | 35.00 | 875.00 |
0028 | 712-02-00100 | Sacked Concrete Revetment | 20 | SQYD | 378.75 | 7,575.00 | 450.00 | 9,000.00 | 280.00 | 5,600.00 |
0029 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 9,808.11 | 9,808.11 | 25,000.00 | 25,000.00 | 63,500.00 | 63,500.00 |
0030 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 600 | LNFT | 0.51 | 306.00 | 0.01 | 6.00 | 0.75 | 450.00 |
0031 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 90 | LNFT | 0.80 | 72.00 | 0.01 | 0.90 | 1.00 | 90.00 |
0032 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 3.816 | MILE | 770.00 | 2,938.32 | 100.00 | 381.60 | 1,030.00 | 3,930.48 |
0033 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 0.085 | MILE | 1,010.00 | 85.85 | 1.00 | 0.09 | 1,030.00 | 87.55 |
0034 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 6.251 | MILE | 1,363.50 | 8,523.24 | 1.00 | 6.25 | 1,391.00 | 8,695.14 |
0035 | 713-05-00220 | Temporary Pavement Legends & Symbols (Arrow - Left Turn) | 12 | EACH | 25.25 | 303.00 | 1.00 | 12.00 | 26.00 | 312.00 |
0036 | 722-02-00100 | Project Site Laboratory (Equipped) | 1 | EACH | 6,565.00 | 6,565.00 | 10,000.00 | 10,000.00 | 21,100.00 | 21,100.00 |
0037 | 724-01-00100 | Rumble Strips (Centerline) | 0.038 | MILE | 1,313.00 | 49.89 | 1,300.00 | 49.40 | 1,340.00 | 50.92 |
0038 | 724-02-00100 | Rumble Strips (Shoulder/Edge) | 0.848 | MILE | 1,313.00 | 1,113.42 | 1,300.00 | 1,102.40 | 1,340.00 | 1,136.32 |
0039 | 726-01-00100 | Bedding Material | 31 | CUYD | 96.96 | 3,005.76 | 110.00 | 3,410.00 | 142.00 | 4,402.00 |
0040 | 727-01-00100 | Mobilization | 1 | LUMP | 79,500.00 | 79,500.00 | 100,000.00 | 100,000.00 | 125,000.00 | 125,000.00 |
0041 | 731-02-00100 | Reflectorized Raised Pavement Markers | 571 | EACH | 6.06 | 3,460.26 | 6.25 | 3,568.75 | 6.25 | 3,568.75 |
0042 | 732-01-01040 | Plastic Pavement Striping (8" Width) (Thermoplastic 90 mil) | 200 | LNFT | 3.29 | 658.00 | 3.35 | 670.00 | 3.50 | 700.00 |
0043 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 30 | LNFT | 14.65 | 439.50 | 15.00 | 450.00 | 15.00 | 450.00 |
0044 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 2.084 | MILE | 3,939.00 | 8,208.88 | 4,100.00 | 8,544.40 | 4,017.00 | 8,371.43 |
0045 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 0.028 | MILE | 1,717.00 | 48.08 | 2,000.00 | 56.00 | 1,751.00 | 49.03 |
0046 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.044 | MILE | 2,323.00 | 102.21 | 2,500.00 | 110.00 | 2,370.00 | 104.28 |
0047 | 732-03-02030 | Plastic Pavement Striping (Dotted Line)(8" W)(2' L)(Thermo 90 mil) | 0.133 | MILE | 7,878.00 | 1,047.77 | 8,500.00 | 1,130.50 | 8,050.00 | 1,070.65 |
0048 | 732-04-01080 | Plastic Pavement Legends and Symbols (Arrow - Left Turn) | 4 | EACH | 353.50 | 1,414.00 | 375.00 | 1,500.00 | 361.00 | 1,444.00 |
0049 | 735-01-00100 | Mailboxes | 4 | EACH | 25.25 | 101.00 | 35.00 | 140.00 | 21.00 | 84.00 |
0050 | 735-02-00100 | Mailbox Supports (Single) | 4 | EACH | 202.00 | 808.00 | 250.00 | 1,000.00 | 181.00 | 724.00 |
0051 | 739-01-00100 | Hydro-Seeding | 0.72 | ACRE | 3,181.50 | 2,290.68 | 5,000.00 | 3,600.00 | 5,150.00 | 3,708.00 |
0052 | 740-01-00100 | Construction Layout | 1 | LUMP | 2,000.00 | 2,000.00 | 500.00 | 500.00 | 9,500.00 | 9,500.00 |
0053 | NS-500-00340 | Saw Cutting Asphalt Concrete Pavement | 72,800 | INLF | 0.90 | 65,520.00 | 1.00 | 72,800.00 | 1.32 | 96,096.00 |
| | | | | | | | | | |
| | CONTRACTOR TOTAL | | | | 1,175,085.00 | | 1,181,827.16 | | 1,391,655.08 |