Bid Tabulations for the Letting of 5/12/2021 LA DOTD Headquarters

Proposal:H.013141.6
Parish:Evangeline
Description:GREEN VALLEY ROAD BRIDGE OVER PETITE PASSE
Type Construction:CLEARING AND GRUBBING, REMOVAL OF BRIDGE, GRADING, DRAINAGE STRUCTURES, CLASS II BASE COURSE, ASPHALT CONCRETE PAVEMENT, PRECAST CONCRETE PILES, CONCRETE SLAB SPAN BRIDGE, AND RELATED WORK.
Estimated Construction Cost:$716,617.90
112487Diamond B Construction Co., L.L.C.$722,360.80
259705David Temple dba Northern State Construction, LLC$732,691.10
355505MERRICK, LLC$755,470.70
440312GRAY CONSTRUCTION CORP.$775,548.05
563897TL Hawk, LLC$833,121.10
600044Guinn Construction, LLC$856,599.90
756994Matt L. Guinn Construction, LLC$895,158.00
800009Coastal Contractors, Inc.$991,168.55
939613BAKER PILE DRIVING AND SITE WORK LLC$999,808.78


Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 1 -
Diamond B Construction Co., L.L.C.
- 2 -
David Temple dba Northern State Construction, LLC
- 3 -
MERRICK, LLC
- 4 -
GRAY CONSTRUCTION CORP.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1     LUMP5,000.005,000.008,000.008,000.002,000.002,000.005,000.005,000.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP7,000.007,000.005,000.005,000.002,000.002,000.004,000.004,000.00
0003202-02-00010Removal of DOUBLE DRIVEWAY GATE (14+77 LT)1     EACH1,000.001,000.00500.00500.00500.00500.00500.00500.00
0004202-02-02020Removal of Asphalt Pavement 850.6   SQYD5.004,253.008.507,230.103.002,551.805.504,678.30
0005202-02-03000Removal of Base – Soil Cement, Asphalt, or BCS 736     SQYD6.504,784.008.506,256.004.503,312.005.504,048.00
0006202-02-04501Removal of Bridge (STA 15+29 - 27.5ft x 57ft, PRECAST CONCRETE & TIMBER)1,567.5   LUMP5,000.005,000.0010,000.0010,000.0010,000.0010,000.0044,000.0044,000.00
0007203-02-00100Drainage Excavation 216     CUYD22.004,752.0025.005,400.0020.004,320.0024.005,184.00
0008203-05-00100Excavation and Embankment 1     LUMP9,500.009,500.0014,500.0014,500.0020,000.0020,000.0025,100.0025,100.00
0009204-02-00100Temporary Hay Bales 11     EACH30.00330.0025.00275.0020.00220.0025.00275.00
0010204-05-00100Temporary Sediment Check Dams (Hay) 4     EACH225.00900.00200.00800.00130.00520.00200.00800.00
0011204-06-00100Temporary Silt Fencing 806     LNFT2.502,015.002.001,612.002.251,813.502.001,612.00
0012302-01-00300Class II Base Course (Crushed Stone) 197.7   CUYD55.0010,873.50100.0019,770.00142.0028,073.40171.0033,806.70
0013401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 13     CUYD300.003,900.00100.001,300.00155.002,015.00115.001,495.00
0014502-01-00100Asphalt Concrete 157.32  TON165.0025,957.80200.0031,464.00240.0037,756.80200.0031,464.00
0015701-05-01042Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CMP) 123     LNFT110.0013,530.0080.009,840.0070.008,610.0075.009,225.00
0016701-05-01101Side Drain Pipe (36" RCP/RPVCP/CPEPDW/CMP) 139     LNFT130.0018,070.00120.0016,680.00110.0015,290.00187.0025,993.00
0017701-05-02041Side Drain Pipe (Erosion) (18" RPVCP/CPEPDW/CMP) 204     LNFT80.0016,320.0080.0016,320.0070.0014,280.0075.0015,300.00
0018701-05-02101Side Drain Pipe (Erosion) (36" RPVCP/CPEPDW/CMP) 256     LNFT120.0030,720.00120.0030,720.00110.0028,160.00187.0047,872.00
0019701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 395     LNFT3.501,382.505.001,975.003.001,185.0012.504,937.50
0020702-03-00100Catch Basins (CB-01) 4     EACH7,500.0030,000.003,500.0014,000.007,500.0030,000.005,500.0022,000.00
0021704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 50     LNFT35.001,750.0025.001,250.0026.001,300.0026.001,300.00
0022704-07-00200Guard Rail Transitions (Double Thrie Beam) 100     LNFT115.0011,500.0090.009,000.0090.009,000.0075.007,500.00
0023704-10-00100Guard Rail End Treatment (Flared) 4     EACH3,000.0012,000.003,250.0013,000.003,500.0014,000.003,000.0012,000.00
0024705-01-00100Barbed Wire Fence 717     LNFT14.0010,038.0012.008,604.0011.007,887.0012.008,604.00
0025705-05-00100Double Swinging Driveway Gates 1     DBGT800.00800.00750.00750.001,000.001,000.00750.00750.00
0026711-01-04000Riprap (55 lb, 18" Thick) 588     SQYD70.0041,160.0065.0038,220.0065.0038,220.0072.0042,336.00
0027711-04-00100Geotextile Fabric 588     SQYD3.001,764.005.002,940.004.752,793.005.753,381.00
0028713-01-00100Temporary Signs and Barricades 1     LUMP17,500.0017,500.005,000.005,000.0010,000.0010,000.006,000.006,000.00
0029716-01-00100Mulch (Vegetative) 0.5   TON3,500.001,750.003,500.001,750.005,000.002,500.003,500.001,750.00
0030717-01-00100Seeding 12     LB25.00300.0025.00300.0040.00480.0025.00300.00
0031718-01-00100Fertilizer 270     LB2.00540.002.00540.002.00540.002.00540.00
0032726-01-00100Bedding Material 6.4   CUYD175.001,120.00100.00640.00150.00960.00186.001,190.40
0033727-01-00100Mobilization 1     LUMP70,000.0070,000.0050,000.0050,000.0075,000.0075,000.0077,200.0077,200.00
0034729-16-00300Object Marker Assembly (Type 3) 4     EACH85.00340.00105.00420.00230.00920.00210.00840.00
0035731-02-00100Reflectorized Raised Pavement Markers 22     EACH20.00440.0075.001,650.0024.00528.0020.00440.00
0036737-03-00100Painted Traffic Striping (Solid Line) (4" Width) 1,700     LNFT1.001,700.004.507,650.001.352,295.001.151,955.00
0037740-01-00100Construction Layout 1     LUMP12,000.0012,000.0010,000.0010,000.0010,000.0010,000.006,150.006,150.00
0038804-01-00200Precast Concrete Piles (14") 1,300     LNFT70.0091,000.00100.00130,000.0085.00110,500.0074.0096,200.00
0039805-12-00100Bridge Superstructure and Substructure (24' Roadway, 90 Degree Crossing) 1,920     SQFT114.00218,880.00110.00211,200.00120.00230,400.0098.00188,160.00
0040805-18-00100Concrete Finish (Class 2 Rubbed Finish) 966     SQFT3.002,898.002.502,415.001.601,545.604.504,347.00
0041805-18-00200Concrete Finish (Class 3 Special Finish) 966     SQFT2.001,932.002.502,415.001.601,545.602.001,932.00
0042813-01-00100Concrete Approach Slabs (Cast-in-Place) (24' Roadway; 90 Degree Crossing; w/o Asphalt)500     SQFT55.0027,500.0065.0032,500.0040.0020,000.0049.7524,875.00
0043NS-500-00340Saw Cutting Asphalt Concrete Pavement 161     INLF1.00161.005.00805.009.001,449.003.15507.15
             
  CONTRACTOR TOTAL   722,360.80 732,691.10 755,470.70 775,548.05



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 5 -
TL Hawk, LLC
- 6 -
Guinn Construction, LLC
- 7 -
Matt L. Guinn Construction, LLC
- 8 -
Coastal Contractors, Inc.
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1     LUMP35,000.0035,000.005,000.005,000.0015,000.0015,000.0045,000.0045,000.00
0002202-01-00100Removal of Structures and Obstructions 1     LUMP6,000.006,000.005,000.005,000.003,500.003,500.0011,000.0011,000.00
0003202-02-00010Removal of DOUBLE DRIVEWAY GATE (14+77 LT)1     EACH500.00500.00500.00500.00550.00550.00385.00385.00
0004202-02-02020Removal of Asphalt Pavement 850.6   SQYD10.008,506.004.003,402.4012.0010,207.209.007,655.40
0005202-02-03000Removal of Base – Soil Cement, Asphalt, or BCS 736     SQYD8.005,888.004.002,944.0011.508,464.009.006,624.00
0006202-02-04501Removal of Bridge (STA 15+29 - 27.5ft x 57ft, PRECAST CONCRETE & TIMBER)1,567.5   LUMP40,000.0040,000.0015,000.0015,000.0030,000.0030,000.0075,000.0075,000.00
0007203-02-00100Drainage Excavation 216     CUYD20.004,320.0015.003,240.0045.009,720.0040.008,640.00
0008203-05-00100Excavation and Embankment 1     LUMP14,546.0014,546.0020,000.0020,000.0035,000.0035,000.0040,000.0040,000.00
0009204-02-00100Temporary Hay Bales 11     EACH57.00627.0025.00275.00150.001,650.0060.00660.00
0010204-05-00100Temporary Sediment Check Dams (Hay) 4     EACH200.00800.00250.001,000.00500.002,000.00200.00800.00
0011204-06-00100Temporary Silt Fencing 806     LNFT3.302,659.804.003,224.005.004,030.002.652,135.90
0012302-01-00300Class II Base Course (Crushed Stone) 197.7   CUYD175.0034,597.50150.0029,655.00165.0032,620.50134.0026,491.80
0013401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 13     CUYD145.001,885.00200.002,600.00200.002,600.00125.001,625.00
0014502-01-00100Asphalt Concrete 157.32  TON175.0027,531.00200.0031,464.00265.0041,689.80175.0027,531.00
0015701-05-01042Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CMP) 123     LNFT80.009,840.00100.0012,300.0060.007,380.00115.0014,145.00
0016701-05-01101Side Drain Pipe (36" RCP/RPVCP/CPEPDW/CMP) 139     LNFT125.0017,375.00175.0024,325.00180.0025,020.00198.0027,522.00
0017701-05-02041Side Drain Pipe (Erosion) (18" RPVCP/CPEPDW/CMP) 204     LNFT75.0015,300.00100.0020,400.0060.0012,240.0096.0019,584.00
0018701-05-02101Side Drain Pipe (Erosion) (36" RPVCP/CPEPDW/CMP) 256     LNFT120.0030,720.00175.0044,800.00180.0046,080.00177.0045,312.00
0019701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 395     LNFT4.501,777.505.001,975.008.503,357.504.751,876.25
0020702-03-00100Catch Basins (CB-01) 4     EACH3,300.0013,200.005,000.0020,000.006,000.0024,000.005,300.0021,200.00
0021704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 50     LNFT25.001,250.0030.001,500.0050.002,500.0025.001,250.00
0022704-07-00200Guard Rail Transitions (Double Thrie Beam) 100     LNFT75.007,500.00105.0010,500.00145.0014,500.0075.007,500.00
0023704-10-00100Guard Rail End Treatment (Flared) 4     EACH3,000.0012,000.004,500.0018,000.003,700.0014,800.003,000.0012,000.00
0024705-01-00100Barbed Wire Fence 717     LNFT9.076,503.1915.0010,755.0016.0011,472.009.106,524.70
0025705-05-00100Double Swinging Driveway Gates 1     DBGT873.13873.133,000.003,000.00900.00900.00875.00875.00
0026711-01-04000Riprap (55 lb, 18" Thick) 588     SQYD67.0039,396.0080.0047,040.0078.5046,158.0081.0047,628.00
0027711-04-00100Geotextile Fabric 588     SQYD6.503,822.005.002,940.004.002,352.003.752,205.00
0028713-01-00100Temporary Signs and Barricades 1     LUMP8,500.008,500.0015,000.0015,000.0012,000.0012,000.005,500.005,500.00
0029716-01-00100Mulch (Vegetative) 0.5   TON3,478.001,739.005,000.002,500.004,000.002,000.003,478.001,739.00
0030717-01-00100Seeding 12     LB33.74404.8850.00600.0085.001,020.0034.00408.00
0031718-01-00100Fertilizer 270     LB1.32356.402.00540.005.501,485.001.33359.10
0032726-01-00100Bedding Material 6.4   CUYD175.001,120.00200.001,280.00300.001,920.00186.001,190.40
0033727-01-00100Mobilization 1     LUMP80,000.0080,000.0078,500.0078,500.0045,000.0045,000.0095,000.0095,000.00
0034729-16-00300Object Marker Assembly (Type 3) 4     EACH200.00800.00125.00500.00200.00800.00200.00800.00
0035731-02-00100Reflectorized Raised Pavement Markers 22     EACH20.00440.00100.002,200.0050.001,100.0020.00440.00
0036737-03-00100Painted Traffic Striping (Solid Line) (4" Width) 1,700     LNFT1.151,955.007.0011,900.006.5011,050.003.005,100.00
0037740-01-00100Construction Layout 1     LUMP29,000.0029,000.006,000.006,000.0020,000.0020,000.0015,000.0015,000.00
0038804-01-00200Precast Concrete Piles (14") 1,300     LNFT135.00175,500.0090.00117,000.0080.00104,000.0078.00101,400.00
0039805-12-00100Bridge Superstructure and Substructure (24' Roadway, 90 Degree Crossing) 1,920     SQFT85.00163,200.00125.00240,000.00128.00245,760.00140.00268,800.00
0040805-18-00100Concrete Finish (Class 2 Rubbed Finish) 966     SQFT1.251,207.504.003,864.005.004,830.002.001,932.00
0041805-18-00200Concrete Finish (Class 3 Special Finish) 966     SQFT1.201,159.204.003,864.005.004,830.002.502,415.00
0042813-01-00100Concrete Approach Slabs (Cast-in-Place) (24' Roadway; 90 Degree Crossing; w/o Asphalt)500     SQFT50.0025,000.0060.0030,000.0062.5031,250.0055.0027,500.00
0043NS-500-00340Saw Cutting Asphalt Concrete Pavement 161     INLF2.00322.0012.502,012.502.00322.0015.002,415.00
             
  CONTRACTOR TOTAL   833,121.10 856,599.90 895,158.00 991,168.55



Line
Number
Item NumberItem DescriptionQuantityUnit of
Measure
- 9 -
BAKER PILE DRIVING AND SITE WORK LLC
Unit PriceTotal
Amount
0001201-01-00100Clearing and Grubbing 1     LUMP12,434.5012,434.50
0002202-01-00100Removal of Structures and Obstructions 1     LUMP11,243.9111,243.91
0003202-02-00010Removal of DOUBLE DRIVEWAY GATE (14+77 LT)1     EACH1,909.401,909.40
0004202-02-02020Removal of Asphalt Pavement 850.6   SQYD7.106,039.26
0005202-02-03000Removal of Base – Soil Cement, Asphalt, or BCS 736     SQYD12.799,413.44
0006202-02-04501Removal of Bridge (STA 15+29 - 27.5ft x 57ft, PRECAST CONCRETE & TIMBER)1,567.5   LUMP38,971.5238,971.52
0007203-02-00100Drainage Excavation 216     CUYD27.315,898.96
0008203-05-00100Excavation and Embankment 1     LUMP23,447.4023,447.40
0009204-02-00100Temporary Hay Bales 11     EACH172.281,895.08
0010204-05-00100Temporary Sediment Check Dams (Hay) 4     EACH537.552,150.20
0011204-06-00100Temporary Silt Fencing 806     LNFT4.313,473.86
0012302-01-00300Class II Base Course (Crushed Stone) 197.7   CUYD104.7820,715.01
0013401-02-00100Aggregate Surface Course (Adjusted Vehicular Measurement) 13     CUYD212.822,766.66
0014502-01-00100Asphalt Concrete 157.32  TON247.5338,941.42
0015701-05-01042Side Drain Pipe (18" RCP/RPVCP/CPEPDW/CMP) 123     LNFT109.3513,450.05
0016701-05-01101Side Drain Pipe (36" RCP/RPVCP/CPEPDW/CMP) 139     LNFT164.0122,797.39
0017701-05-02041Side Drain Pipe (Erosion) (18" RPVCP/CPEPDW/CMP) 204     LNFT109.3522,307.40
0018701-05-02101Side Drain Pipe (Erosion) (36" RPVCP/CPEPDW/CMP) 256     LNFT164.0141,986.56
0019701-17-00100Trench Excavation Safety Protection (Depth >5 feet) 395     LNFT50.4919,943.55
0020702-03-00100Catch Basins (CB-01) 4     EACH5,467.0321,868.12
0021704-03-00200Blocked Out Guard Rail - 31", (6'-3" Post Spacing) 50     LNFT30.371,518.50
0022704-07-00200Guard Rail Transitions (Double Thrie Beam) 100     LNFT121.4912,149.00
0023704-10-00100Guard Rail End Treatment (Flared) 4     EACH3,037.2412,148.96
0024705-01-00100Barbed Wire Fence 717     LNFT10.737,693.41
0025705-05-00100Double Swinging Driveway Gates 1     DBGT2,610.592,610.59
0026711-01-04000Riprap (55 lb, 18" Thick) 588     SQYD48.8328,712.04
0027711-04-00100Geotextile Fabric 588     SQYD3.652,146.20
0028713-01-00100Temporary Signs and Barricades 1     LUMP4,130.644,130.64
0029716-01-00100Mulch (Vegetative) 0.5   TON3,644.691,822.35
0030717-01-00100Seeding 12     LB151.861,822.32
0031718-01-00100Fertilizer 270     LB6.751,822.50
0032726-01-00100Bedding Material 6.4   CUYD298.261,908.86
0033727-01-00100Mobilization 1     LUMP88,800.0088,800.00
0034729-16-00300Object Marker Assembly (Type 3) 4     EACH151.86607.44
0035731-02-00100Reflectorized Raised Pavement Markers 22     EACH36.45801.90
0036737-03-00100Painted Traffic Striping (Solid Line) (4" Width) 1,700     LNFT2.434,131.00
0037740-01-00100Construction Layout 1     LUMP15,357.1315,357.13
0038804-01-00200Precast Concrete Piles (14") 1,300     LNFT121.38157,794.00
0039805-12-00100Bridge Superstructure and Substructure (24' Roadway, 90 Degree Crossing) 1,920     SQFT147.56283,315.20
0040805-18-00100Concrete Finish (Class 2 Rubbed Finish) 966     SQFT5.485,293.68
0041805-18-00200Concrete Finish (Class 3 Special Finish) 966     SQFT4.284,134.48
0042813-01-00100Concrete Approach Slabs (Cast-in-Place) (24' Roadway; 90 Degree Crossing; w/o Asphalt)500     SQFT76.7838,390.00
0043NS-500-00340Saw Cutting Asphalt Concrete Pavement 161     INLF6.491,044.89
       
  CONTRACTOR TOTAL   999,808.78