Line Number | Item Number | Item Description | Quantity | Unit of Measure | - 1 - D & J CONSTRUCTION CO., LLC | - 2 - GILCHRIST CONSTRUCTION COMPANY, LLC | - 3 - Diamond B Construction Co., L.L.C. |
Unit Price | Total Amount | Unit Price | Total Amount | Unit Price | Total Amount |
0001 | 201-01-00200 | Clearing and Grubbing (Selective) | 3 | LUMP | 12,500.00 | 12,500.00 | 57,000.00 | 57,000.00 | 20,000.00 | 20,000.00 |
0002 | 202-02-06140 | Removal of Curbs (Concrete) | 121 | LNFT | 15.00 | 1,815.00 | 20.00 | 2,420.00 | 32.00 | 3,872.00 |
0003 | 202-02-26300 | Removal of Median / Island | 39 | SQYD | 25.00 | 975.00 | 65.00 | 2,535.00 | 32.00 | 1,248.00 |
0004 | 202-02-32100 | Removal of Pipe (Cross Drain) 24" RCP | 16 | LNFT | 15.00 | 240.00 | 35.00 | 560.00 | 25.00 | 400.00 |
0005 | 202-02-38200 | Removal of Signs | 1 | EACH | 250.00 | 250.00 | 60.00 | 60.00 | 60.00 | 60.00 |
0006 | 203-07-00100 | Borrow (Vehicular Measurement) | 10 | CUYD | 25.00 | 250.00 | 70.00 | 700.00 | 30.00 | 300.00 |
0007 | 204-02-00100 | Temporary Hay Bales | 8 | EACH | 15.00 | 120.00 | 60.00 | 480.00 | 60.00 | 480.00 |
0008 | 401-02-00100 | Aggregate Surface Course (Adjusted Vehicular Measurement) | 2,743 | CUYD | 60.00 | 164,580.00 | 100.00 | 274,300.00 | 120.00 | 329,160.00 |
0009 | 502-01-00100 | Asphalt Concrete | 11,514.5 | TON | 90.00 | 1,036,305.00 | 100.00 | 1,151,450.00 | 120.00 | 1,381,740.00 |
0010 | 502-01-00200 | Asphalt Concrete, Drives, Turnouts and Miscellaneous | 271.7 | TON | 190.00 | 51,623.00 | 100.00 | 27,170.00 | 210.00 | 57,057.00 |
0011 | 509-01-00100 | Milling Asphalt Pavement | 2,936 | SQYD | 5.00 | 14,680.00 | 10.00 | 29,360.00 | 4.50 | 13,212.00 |
0012 | 509-02-00100 | Contractor Retained Reclaimed Asphalt Pavement | -148 | CUYD | 1.00 | -148.00 | 1.00 | -148.00 | 1.00 | -148.00 |
0013 | 510-01-00100 | Pavement Patching (6" Minimum Thickness) | 950 | SQYD | 90.00 | 85,500.00 | 85.00 | 80,750.00 | 80.00 | 76,000.00 |
0014 | 510-01-00200 | Pavement Patching (12" Minimum Thickness) | 39 | SQYD | 120.00 | 4,680.00 | 110.00 | 4,290.00 | 225.00 | 8,775.00 |
0015 | 510-01-00260 | Pavement Patching (16 inch Minimum Thickness) | 1,750 | SQYD | 150.00 | 262,500.00 | 120.00 | 210,000.00 | 123.00 | 215,250.00 |
0016 | 510-02-00100 | Pavement Widening 12" Depth | 311.1 | SQYD | 110.00 | 34,221.00 | 110.00 | 34,221.00 | 110.00 | 34,221.00 |
0017 | 701-10-01060 | Reinforced Concrete Pipe (Extension) (24") | 40 | LNFT | 250.00 | 10,000.00 | 400.00 | 16,000.00 | 350.00 | 14,000.00 |
0018 | 701-15-00100 | Concrete Collar | 5 | EACH | 1,000.00 | 5,000.00 | 3,000.00 | 15,000.00 | 1,000.00 | 5,000.00 |
0019 | 711-01-04000 | Riprap (55 lb, 18" Thick) | 22 | SQYD | 100.00 | 2,200.00 | 225.00 | 4,950.00 | 125.00 | 2,750.00 |
0020 | 711-04-00100 | Geotextile Fabric | 22 | SQYD | 5.00 | 110.00 | 20.00 | 440.00 | 4.00 | 88.00 |
0021 | 713-01-00100 | Temporary Signs and Barricades | 1 | LUMP | 23,000.00 | 23,000.00 | 65,000.00 | 65,000.00 | 18,500.00 | 18,500.00 |
0022 | 713-02-00300 | Temporary Pavement Markings (8" Width) | 128 | LNFT | 0.20 | 25.60 | 0.25 | 32.00 | 0.30 | 38.40 |
0023 | 713-02-00500 | Temporary Pavement Markings (24" Width) | 116 | LNFT | 0.30 | 34.80 | 0.35 | 40.60 | 0.80 | 92.80 |
0024 | 713-03-01000 | Temporary Pavement Markings (Broken Line) (4" Width) (4' Length) | 7.814 | MILE | 200.00 | 1,562.80 | 210.00 | 1,640.94 | 175.00 | 1,367.45 |
0025 | 713-03-02000 | Temporary Pavement Markings (Broken Line) (4" Width) (10' Length) | 5.455 | MILE | 400.00 | 2,182.00 | 10.50 | 57.28 | 500.00 | 2,727.50 |
0026 | 713-04-01000 | Temporary Pavement Markings (Solid Line) (4" Width) | 23.119 | MILE | 700.00 | 16,183.30 | 10.50 | 242.75 | 950.00 | 21,963.05 |
0027 | 716-01-00100 | Mulch (Vegetative) | 1 | TON | 800.00 | 800.00 | 1,100.00 | 1,100.00 | 1,000.00 | 1,000.00 |
0028 | 717-01-00100 | Seeding | 40 | LB | 12.00 | 480.00 | 21.00 | 840.00 | 15.00 | 600.00 |
0029 | 718-01-00100 | Fertilizer | 700 | LB | 1.00 | 700.00 | 1.25 | 875.00 | 1.00 | 700.00 |
0030 | 724-01-00100 | Rumble Strips (Centerline) | 7.814 | MILE | 300.00 | 2,344.20 | 525.00 | 4,102.35 | 300.00 | 2,344.20 |
0031 | 726-01-00100 | Bedding Material | 13.7 | CUYD | 100.00 | 1,370.00 | 145.00 | 1,986.50 | 140.00 | 1,918.00 |
0032 | 727-01-00100 | Mobilization | 1 | LUMP | 75,000.00 | 75,000.00 | 230,000.00 | 230,000.00 | 200,000.00 | 200,000.00 |
0033 | 729-01-00102 | Sign (Type A)(Furnish and Install) | 5.2 | SQFT | 40.00 | 208.00 | 60.00 | 312.00 | 60.00 | 312.00 |
0034 | 729-16-00200 | Object Marker Assembly (Type 2) | 6 | EACH | 70.00 | 420.00 | 80.00 | 480.00 | 75.00 | 450.00 |
0035 | 729-21-00100 | U-Channel Post | 1 | EACH | 200.00 | 200.00 | 120.00 | 120.00 | 125.00 | 125.00 |
0036 | 731-02-00100 | Reflectorized Raised Pavement Markers | 1,380 | EACH | 6.00 | 8,280.00 | 9.00 | 12,420.00 | 6.50 | 8,970.00 |
0037 | 732-01-02040 | Plastic Pavement Striping (8" Width) (Thermoplastic 125 mil) | 128 | LNFT | 4.00 | 512.00 | 6.00 | 768.00 | 4.00 | 512.00 |
0038 | 732-01-02080 | Plastic Pavement Striping (24" Width) (Thermoplastic 125 mil) | 116 | LNFT | 12.00 | 1,392.00 | 16.00 | 1,856.00 | 16.00 | 1,856.00 |
0039 | 732-02-02000 | Plastic Pavement Striping (Solid Line) (4" Width) (Thermoplastic 90 mil) | 23.119 | MILE | 3,600.00 | 83,228.40 | 4,300.00 | 99,411.70 | 4,000.00 | 92,476.00 |
0040 | 732-03-02000 | Plastic Pavement Striping (Broken Line) (4" Width) (Thermoplastic 90 mil) | 5.455 | MILE | 900.00 | 4,909.50 | 1,900.00 | 10,364.50 | 1,000.00 | 5,455.00 |
0041 | 732-03-02010 | Plastic Pavement Striping (Dotted Line)(4" W)(2' L)(Thermo 90 mil) | 0.047 | MILE | 4,000.00 | 188.00 | 1,800.00 | 84.60 | 4,800.00 | 225.60 |
0042 | 735-01-00100 | Mailboxes | 1 | EACH | 5.00 | 5.00 | 1.00 | 1.00 | 5.00 | 5.00 |
0043 | 735-02-00100 | Mailbox Supports (Single) | 1 | EACH | 500.00 | 500.00 | 275.00 | 275.00 | 250.00 | 250.00 |
0044 | 740-01-00100 | Construction Layout | 1 | LUMP | 6,000.00 | 6,000.00 | 30,000.00 | 30,000.00 | 7,500.00 | 7,500.00 |
| | | | | | | | | | |
| | CONTRACTOR TOTAL | | | | 1,916,926.60 | | 2,373,548.22 | | 2,532,853.00 |